Integrated Design Group(ID) completed construction at the North Hall Data Center located at the University of California at Santa Barbara (UCSB). Integral to the university’s computing operations, the data center, which contained enterprise computing capabilities and all campus network connections, was fully operational during the project, allowing the university community to access the servers normally and not cause disruption to the institution’s computing.
A major client goal was for the new research data center to become flexible and scalable in order to provide the opportunity for future expansion as needed. Although the existing facility posed significant limitations on interior clearances, restricting both the depth of the raised floor and the overall height within the computer room, ID was able to nearly double the raised floor space by using innovative cooling technology. With updated mechanical and electrical systems, the research data center is now able to support the latest in high performance computing.
By utilizing the 415/240 V AC power distribution system, which is standard in most European and Asian countries, ID was able to implement efficiency gains within the data center, and provide monetary savings for the university. This application offers a significant amount of energy improvement over North America’s standard of 208/120 V. Delivering power to IT loads at 415/240 V instead of 208/120 V eliminates power distribution unit (PDU) transformers. This elimination not only offers energy efficiency gain, but also reduces copper costs and floor loading while freeing up additional space within the data center. +
Related Stories
| Sep 22, 2010
Satellier, Potential + Semac close investment deal
Satellier, a world leader in providing CAD and Building Information Modeling (BIM) outsourced services to the architecture, engineering and construction industry, announces a strategic minority investment from India-based top engineering firm Potential + Semac, ushering in the next evolution of the global architecture support industry.
| Sep 21, 2010
New BOMA-Kingsley Report Shows Compression in Utilities and Total Operating Expenses
A new report from the Building Owners and Managers Association (BOMA) International and Kingsley Associates shows that property professionals are trimming building operating expenses to stay competitive in today’s challenging marketplace. The report, which analyzes data from BOMA International’s 2010 Experience Exchange Report® (EER), revealed a $0.09 (1.1 percent) decrease in total operating expenses for U.S. private-sector buildings during 2009.
| Sep 21, 2010
Forecast: Existing buildings to earn 50% of green building certifications
A new report from Pike Research forecasts that by 2020, nearly half the green building certifications will be for existing buildings—accounting for 25 billion sf. The study, “Green Building Certification Programs,” analyzed current market and regulatory conditions related to green building certification programs, and found that green building remain robust during the recession and that certifications for existing buildings are an increasing area of focus.
| Sep 21, 2010
Middough Inc. Celebrates its 60th Anniversary
Middough Inc., a top ranking U.S. architectural, engineering and management services company, announces the celebration of its 60th anniversary, says President and CEO, Ronald R. Ledin, PE.
| Sep 16, 2010
Gehry’s Santa Monica Place gets a wave of changes
Omniplan, in association with Jerde Partnership, created an updated design for Santa Monica Place, a shopping mall designed by Frank Gehry in 1980.
| Sep 16, 2010
Green recreation/wellness center targets physical, environmental health
The 151,000-sf recreation and wellness center at California State University’s Sacramento campus, called the WELL (for “wellness, education, leisure, lifestyle”), has a fitness center, café, indoor track, gymnasium, racquetball courts, educational and counseling space, the largest rock climbing wall in the CSU system.
| Sep 13, 2010
Community college police, parking structure targets LEED Platinum
The San Diego Community College District's $1.555 billion construction program continues with groundbreaking for a 6,000-sf police substation and an 828-space, four-story parking structure at San Diego Miramar College.
| Sep 13, 2010
Campus housing fosters community connection
A 600,000-sf complex on the University of Washington's Seattle campus will include four residence halls for 1,650 students and a 100-seat cafe, 8,000-sf grocery store, and conference center with 200-seat auditorium for both student and community use.