Integrated Design Group completes UCSB data center

Integrated Design Group completes UCSB data center

Firm uses European standard of power at USCB North Hall Research Data Center.


By Posted by Tim Gregorski, Senior Editor | July 9, 2012
By utilizing the 415/240 V AC power distribution system, which is standard in mo
By utilizing the 415/240 V AC power distribution system, which is standard in most European and Asian countries, ID was able to

Integrated Design Group(ID) completed construction at the North Hall Data Center located at the University of California at Santa Barbara (UCSB). Integral to the university’s computing operations, the data center, which contained enterprise computing capabilities and all campus network connections, was fully operational during the project, allowing the university community to access the servers normally and not cause disruption to the institution’s computing.

A major client goal was for the new research data center to become flexible and scalable in order to provide the opportunity for future expansion as needed. Although the existing facility posed significant limitations on interior clearances, restricting both the depth of the raised floor and the overall height within the computer room, ID was able to nearly double the raised floor space by using innovative cooling technology. With updated mechanical and electrical systems, the research data center is now able to support the latest in high performance computing.

By utilizing the 415/240 V AC power distribution system, which is standard in most European and Asian countries, ID was able to implement efficiency gains within  the data center, and provide monetary savings for the university. This application offers a significant amount of energy improvement over North America’s standard of 208/120 V. Delivering  power to IT loads at 415/240 V instead of 208/120 V eliminates power distribution unit (PDU) transformers. This elimination not only offers energy efficiency gain, but also reduces copper costs and floor loading while freeing up additional space within the data center. +

Related Stories

| May 7, 2014

Design competition: $900,000 on the line in Las Vegas revitalization challenge

Las Vegas Mayor Carolyn Goodman wants your economic development ideas for remaking four areas within the city, including the Cashman Center and the Las Vegas Medical District.

| May 6, 2014

'Beyond' is artist's cinematic take on 2.5 years of development in the UAE

Seven-minute video offers a time-lapse trip through the built environments of Abu Dhabi and Dubai.

| May 6, 2014

'Ugliest building in New Jersey' finally getting facelift

After a decade of false starts and mishaps, the American Dream mall in the Meadowlands may finally get built.

| May 5, 2014

Toronto residential tower to feature drawer-like facade scheme

Some of the apartments in the new River City development will protrude from the building at different lengths, creating a drawer-like "push-pull" effect.

| May 5, 2014

Tragic wired glass injury makes headlines yet again

In the story, a high school student pushed open a hallway door glazed with wired glass. His arm not only broke the glass, but penetrated it, causing severe injuries. SPONSORED CONTENT

| May 3, 2014

Health system capital planning for the future: The benefits of master plan portfolio analysis and ambulatory market modeling

Money continues to be scarce, yet U.S. health systems need to invest and re-invest in their physical future. Healthcare facilities planning experts from CBRE Healthcare outline tools and strategies for identifying where to best allocate precious resources.

| May 3, 2014

4 easy steps to being a great project manager

Managing a team of people, especially creative people, is a task that not everyone is up for. Keeping your team on the same page while maintaining a schedule and budget that can keep your corporation happy will take confidence and bountiful people skills. Here are some tips for effectively managing a project. SPONSORED CONTENT

Sponsored | | May 3, 2014

Fire-rated glass floor system captures light in science and engineering infill

In implementing Northwestern University’s Engineering Life Sciences infill design, Flad Architects faced the challenge of ensuring adequate, balanced light given the adjacent, existing building wings. To allow for light penetration from the fifth floor to the ground floor, the design team desired a large, central atrium. One potential setback with drawing light through the atrium was meeting fire and life safety codes. 

| May 2, 2014

World's largest outdoor chandelier tops reworked streetscape for Cleveland's PlayhouseSquare

Streetscape project includes monumental gateway portals, LED signage, and a new plaza, fire pit, sidewalk café, and alfresco dining area. 

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021