Nine associations representing construction contractors, subcontractors, and design professionals petitioned the Office of Federal Procurement Policy (OFPP) to alter how the office handles change orders.
The groups want the Federal Acquisition Regulation (FAR) amended to "make explicit" that before ordering a change to a construction contract, the contracting officer must assure that funds are available to pay for additional work being ordered.
“Our members are facing increasing numbers of instances in which a Contracting Officer will direct a change in the scope of work on a construction project, lacking funds available to pay for the increased costs being imposed upon the contractor,” the associations wrote in a March 18 letter to OFCPP Administrator Anne Rung.
The groups signing the letter included the Design-Build Institute of America, the American Council of Engineering Companies, the American Subcontractors Association, the Associated General Contractors of America, the Mechanical Contractors Association of America, the National Association of Surety Bond Producers, the National Electrical Contractors Association, the Sheet Metal and Air Conditioning Contractors’ National Association and The Surety & Fidelity Association of America.
They also recommended an amendment that would allow contracting officers to continue to make changes in the work within the general scope of the contract, at any time and without notice to sureties, “but only if funds are available to pay the costs of such changes.”
Related Stories
Modular Building | Feb 23, 2015
Edge construction: The future of modular
Can innovative project delivery methods, namely modular construction, bring down costs and offer a solution for housing in urban markets? FXFOWLE’s David Wallance discusses the possibilities for modular.
| Feb 23, 2015
6 trends changing the way city dwellers live
Across the cultural grid, from food to retail to transportation, America's urban areas are already undergoing a major metamorphosis. Here are the six major trends shaping our cities, from Fast Company.
Green | Feb 23, 2015
State of the green union, and the next big shift in sustainability
The history of the green movement offers cues that we are on the precipice of another significant shift in the green union.
| Feb 23, 2015
Where are the iconic green buildings?
What does a green building look like? How would you know one if you saw one? Maybe a trivial question to some, but of great interest to architects, designers, and other members of the Building Team as the rapid evolution of sustainable buildings continues apace.
Sports and Recreational Facilities | Feb 21, 2015
Pumped-up recreation centers help build body, mind, and spirit
Adopting facility layouts from Asian and European models, today’s sports and recreational buildings are becoming social hubs that accommodate a variety of community needs.
University Buildings | Feb 20, 2015
Penn strengthens campus security by reviving its surrounding neighborhood
In 1996, the University of Pennsylvania’s sprawling campus in Philadelphia was in the grip of an unprecedented crime wave. But instead of walling themselves off from their surrounding neighborhoods, the school decided to support the community.
Sports and Recreational Facilities | Feb 20, 2015
Chargers, Raiders propose joint stadium in Carson
Two rival teams may bring the NFL back to Los Angeles.
Cultural Facilities | Feb 20, 2015
‘Floating’ park on New York’s Hudson River moves one step closer to reality
The developers envision the 2.4-acre space as a major performance arts venue.
Multifamily Housing | Feb 19, 2015
Is multifamily construction getting too frothy for demand?
Contractors are pushing full speed ahead, but CoStar Group thinks a slowdown might be in order this year.
Architects | Feb 19, 2015
Illustrator Federico Babina imagines architecture from nowhere
The illustrator imagines architecture where past, present, and future intertwine.