Nine associations representing construction contractors, subcontractors, and design professionals petitioned the Office of Federal Procurement Policy (OFPP) to alter how the office handles change orders.
The groups want the Federal Acquisition Regulation (FAR) amended to "make explicit" that before ordering a change to a construction contract, the contracting officer must assure that funds are available to pay for additional work being ordered.
“Our members are facing increasing numbers of instances in which a Contracting Officer will direct a change in the scope of work on a construction project, lacking funds available to pay for the increased costs being imposed upon the contractor,” the associations wrote in a March 18 letter to OFCPP Administrator Anne Rung.
The groups signing the letter included the Design-Build Institute of America, the American Council of Engineering Companies, the American Subcontractors Association, the Associated General Contractors of America, the Mechanical Contractors Association of America, the National Association of Surety Bond Producers, the National Electrical Contractors Association, the Sheet Metal and Air Conditioning Contractors’ National Association and The Surety & Fidelity Association of America.
They also recommended an amendment that would allow contracting officers to continue to make changes in the work within the general scope of the contract, at any time and without notice to sureties, “but only if funds are available to pay the costs of such changes.”
Related Stories
Codes and Standards | Nov 9, 2016
NRMCA updates environmental impacts of concrete
The EPD now includes 88 companies, 72 mixes.
Codes and Standards | Nov 9, 2016
Louisiana flood projections require urgent action, officials say
The 'no net loss’ prediction now seems unrealistic.
Codes and Standards | Nov 8, 2016
American Concrete Institute offers new guide for repair of concrete buildings
The guide provides assistance on assessment and rehab.
Codes and Standards | Nov 7, 2016
The AISC prequalified seismic moment connection standard is now available
You can download the 2016 version for free.
Codes and Standards | Nov 4, 2016
Obama Administration makes a push for denser, more affordable cities
The administration calls for zoning code changes and other measures to create more housing.
Codes and Standards | Nov 3, 2016
OSHA proposes safety standards changes to reduce employer costs
The changes include clarification on excavation standard and reporting job-related hearing loss.
Codes and Standards | Nov 2, 2016
New resources available to reduce plug loads using advanced power strips
A tenant education program can boost efficiency in office buildings.
Codes and Standards | Oct 26, 2016
Design industry lagging in meeting AIA 2030 Commitment goals, says AIA
Only 4% of projects have met the 70% energy savings target.
Codes and Standards | Oct 25, 2016
Concerns over megaquake in Oregon provoke debate over school building standards
According to advocates, communities should consider increased resiliency.
Codes and Standards | Oct 24, 2016
Building energy codes projected to save $126 billion in energy costs from 2010-2040
Commercial and residential structures are both included in the total.