Nine associations representing construction contractors, subcontractors, and design professionals petitioned the Office of Federal Procurement Policy (OFPP) to alter how the office handles change orders.
The groups want the Federal Acquisition Regulation (FAR) amended to "make explicit" that before ordering a change to a construction contract, the contracting officer must assure that funds are available to pay for additional work being ordered.
“Our members are facing increasing numbers of instances in which a Contracting Officer will direct a change in the scope of work on a construction project, lacking funds available to pay for the increased costs being imposed upon the contractor,” the associations wrote in a March 18 letter to OFCPP Administrator Anne Rung.
The groups signing the letter included the Design-Build Institute of America, the American Council of Engineering Companies, the American Subcontractors Association, the Associated General Contractors of America, the Mechanical Contractors Association of America, the National Association of Surety Bond Producers, the National Electrical Contractors Association, the Sheet Metal and Air Conditioning Contractors’ National Association and The Surety & Fidelity Association of America.
They also recommended an amendment that would allow contracting officers to continue to make changes in the work within the general scope of the contract, at any time and without notice to sureties, “but only if funds are available to pay the costs of such changes.”
Related Stories
Codes and Standards | Mar 27, 2017
Bills in Maryland Legislature would restrict use of wood in multifamily construction
American Wood Council and design and construction professionals are speaking out against the measure.
Codes and Standards | Mar 23, 2017
New manual of IT connectivity guidelines for commercial developments, redevelopments released
Mobile capacity planning, conduit points of entry, and electrical resiliency are covered.
Codes and Standards | Mar 22, 2017
Brick Industry Assn. study finds brick buildings cost less than precast, metal, and glass
The study compares costs in five categories of construction.
Codes and Standards | Mar 21, 2017
Calif. shopping center is first to earn BREEAM USA In-Use certification
The certification measures and monitors environmental performance of existing buildings.
Codes and Standards | Mar 20, 2017
Professional liability insurance rates for architects and engineers expected to be stable in 2017
Premiums leveled off in 2015, and claims have been stable, helping to hold costs down.
Codes and Standards | Mar 15, 2017
Energy Star program at risk
The standard-setting initiative for energy-efficient products may be a victim of Trump budget cuts.
Codes and Standards | Mar 14, 2017
Timber Innovation Act to promote tall wood buildings introduced in Congress
The measure has bipartisan support.
Codes and Standards | Mar 13, 2017
U.S. House and Senate have voted to repeal Dept. of Labor’s 'blacklisting' rule
The rule mandates labor compliance review for federal construction contractors.
Codes and Standards | Mar 9, 2017
WiredScore forms Connectivity Advisory Committee
The committee's creation is an important step forward for the group that evaluates internet connectivity in buildings.
Codes and Standards | Mar 8, 2017
New guide examines multifamily high-performance ventilation
The focus is on cost and performance of various systems.