Nine associations representing construction contractors, subcontractors, and design professionals petitioned the Office of Federal Procurement Policy (OFPP) to alter how the office handles change orders.
The groups want the Federal Acquisition Regulation (FAR) amended to "make explicit" that before ordering a change to a construction contract, the contracting officer must assure that funds are available to pay for additional work being ordered.
“Our members are facing increasing numbers of instances in which a Contracting Officer will direct a change in the scope of work on a construction project, lacking funds available to pay for the increased costs being imposed upon the contractor,” the associations wrote in a March 18 letter to OFCPP Administrator Anne Rung.
The groups signing the letter included the Design-Build Institute of America, the American Council of Engineering Companies, the American Subcontractors Association, the Associated General Contractors of America, the Mechanical Contractors Association of America, the National Association of Surety Bond Producers, the National Electrical Contractors Association, the Sheet Metal and Air Conditioning Contractors’ National Association and The Surety & Fidelity Association of America.
They also recommended an amendment that would allow contracting officers to continue to make changes in the work within the general scope of the contract, at any time and without notice to sureties, “but only if funds are available to pay the costs of such changes.”
Related Stories
Codes and Standards | Jul 12, 2017
New International Building Code allows weather-resistive barriers above 40 feet
Danger of propagating flames now deemed negligible.
Codes and Standards | Jul 10, 2017
New mass plywood panel project moves ahead with federal grant
New material is substitute for concrete and steel in multi-story projects.
Codes and Standards | Jul 6, 2017
Trump ups ante on apprenticeships, gives private sector more room to design them
Initiative aimed at alleviating construction industry worker shortage.
Codes and Standards | Jul 6, 2017
Flawed modeling to blame for green buildings failure to live up to hype on energy efficiency
Explains energy performance gap from expected savings to actual savings.
Codes and Standards | Jul 5, 2017
Research study examines tall timber buildings worldwide
Industry group developing criteria for categorizing wide range of construction approaches to tall timber buildings.
Codes and Standards | Jun 30, 2017
AAMA releases new document on aluminum fenestration and energy efficiency
The free download addresses entrances, storefront framing, curtain walls, windows and skylight fenestration systems.
Codes and Standards | Jun 29, 2017
Fire codes prevent cladding used on Grenfell Tower from being used in U.S.
Reports suggest an extra $6,300 for fire-resistant cladding could have prevented the tragedy.
Codes and Standards | Jun 28, 2017
Minimum Design Loads and Associated Criteria for Buildings and Other Structures, Standards ASCE/SEI 7-16, has been updated
The document is used for determining design loads including dead, live, soil, flood, tsunami, snow, rain, atmospheric ice, earthquake, wind, and fire.
Codes and Standards | Jun 27, 2017
Cold-formed steel framing engineering guide for building projects released
Better sound attenuation for subfloors and exterior continuous insulation are among the matters addressed.
Codes and Standards | Jun 26, 2017
L.A.’s new ordinance requires energy and water efficiency benchmarking
Structures 20,000 sf and larger must demonstrate steps to boost efficiency.