Nine associations representing construction contractors, subcontractors, and design professionals petitioned the Office of Federal Procurement Policy (OFPP) to alter how the office handles change orders.
The groups want the Federal Acquisition Regulation (FAR) amended to "make explicit" that before ordering a change to a construction contract, the contracting officer must assure that funds are available to pay for additional work being ordered.
“Our members are facing increasing numbers of instances in which a Contracting Officer will direct a change in the scope of work on a construction project, lacking funds available to pay for the increased costs being imposed upon the contractor,” the associations wrote in a March 18 letter to OFCPP Administrator Anne Rung.
The groups signing the letter included the Design-Build Institute of America, the American Council of Engineering Companies, the American Subcontractors Association, the Associated General Contractors of America, the Mechanical Contractors Association of America, the National Association of Surety Bond Producers, the National Electrical Contractors Association, the Sheet Metal and Air Conditioning Contractors’ National Association and The Surety & Fidelity Association of America.
They also recommended an amendment that would allow contracting officers to continue to make changes in the work within the general scope of the contract, at any time and without notice to sureties, “but only if funds are available to pay the costs of such changes.”
Related Stories
Codes and Standards | Nov 15, 2017
NBI stretch code a tool for accelerating efficiency standards
It provides a strategy to leapfrog minimum code requirements.
Codes and Standards | Nov 14, 2017
California bill would require purchase of low-carbon construction products
Contractors would have to source products based on greenhouse gas impact, not price, on state projects.
Codes and Standards | Nov 13, 2017
New AIA contract document for facility support services released
Updated form intended to be used with owner-architect agreements.
Codes and Standards | Nov 9, 2017
NIBS, NBI issue guidance document to help communities achieve energy goals
Outcome-based codes compliance path looks at building’s actual performance.
Codes and Standards | Nov 7, 2017
Underwriters Laboratories launches wellness certification
First certification program that verifies products’ compliance with the WELL Building Standard.
Codes and Standards | Nov 6, 2017
Registration now open for Canada’s first Zero Carbon Building (ZCB) program
Standard is designed to be applicable across many types of new and existing buildings.
Codes and Standards | Nov 6, 2017
AIA releases new architect commissioning document
It will be used with the standard form for owner/consultant contracts.
Codes and Standards | Nov 2, 2017
ASHRAE releases new version of Thermal Comfort Standard
Update includes calculations from direct solar radiation.
Codes and Standards | Nov 1, 2017
Drone users can now get instant authorization from FAA
Skyward offers app to receive permission for low altitude flights.
Codes and Standards | Oct 31, 2017
Real estate giant launches global tenant health and wellness certification initiative
Tishman Speyer will use Fitwel health certification system to guide building improvements.