Nine associations representing construction contractors, subcontractors, and design professionals petitioned the Office of Federal Procurement Policy (OFPP) to alter how the office handles change orders.
The groups want the Federal Acquisition Regulation (FAR) amended to "make explicit" that before ordering a change to a construction contract, the contracting officer must assure that funds are available to pay for additional work being ordered.
“Our members are facing increasing numbers of instances in which a Contracting Officer will direct a change in the scope of work on a construction project, lacking funds available to pay for the increased costs being imposed upon the contractor,” the associations wrote in a March 18 letter to OFCPP Administrator Anne Rung.
The groups signing the letter included the Design-Build Institute of America, the American Council of Engineering Companies, the American Subcontractors Association, the Associated General Contractors of America, the Mechanical Contractors Association of America, the National Association of Surety Bond Producers, the National Electrical Contractors Association, the Sheet Metal and Air Conditioning Contractors’ National Association and The Surety & Fidelity Association of America.
They also recommended an amendment that would allow contracting officers to continue to make changes in the work within the general scope of the contract, at any time and without notice to sureties, “but only if funds are available to pay the costs of such changes.”
Related Stories
Codes and Standards | Nov 15, 2018
New versions of DOE’s EnergyPlus engine and the OpenStudio software development kit released
New offerings resolve over 70 bugs and offer new features.
Codes and Standards | Nov 14, 2018
Obsolete safety standards may have been used in cleanup of former naval shipyard
San Francisco redevelopment site work may have been racked by fraud.
Codes and Standards | Nov 13, 2018
New York City’s new construction safety requirements are delayed
Some contractors say they weren’t ready for ‘massive initiative’.
Codes and Standards | Nov 9, 2018
Cities have multiple strategies to reduce parking requirements
Each community has to find its own mix of solutions.
Codes and Standards | Nov 8, 2018
Denver replaces green roof mandate with cool roof option
Less costly light-colored roofs can cut project costs by about 1.5%.
Codes and Standards | Nov 7, 2018
New report addresses sound transmission of wood-framed assemblies
AWC document provides empirical sound transmission model.
Codes and Standards | Nov 6, 2018
AIA releases 13 new and updated contract documents
Includes new Contractor-Subcontractor Master Agreement.
Codes and Standards | Nov 2, 2018
New Milwaukee Bucks home called world’s first bird-friendly sports arena
Design will make bird collisions less likely.
Codes and Standards | Nov 1, 2018
Several barriers holding back widespread construction of zero energy buildings
Code improvements and voluntary programs could add momentum.
Codes and Standards | Oct 31, 2018
Boston’s new flood protection plan centers on new parks
Initiative would add 67 acres of public open space.