A new Illinois law sets the maximum retainage clients can withhold from contractor payments on private projects.
The change went into effect on August 20, and is expected to help many general contractors and subcontractors receive bigger checks earlier in the project timeline.
The new rule forbids customers from withholding more than 10% retainage from contractor payments, and orders retainage to be reduced to 5% after a contractor has completed half of the work.
The new law applies to all construction contracts. Twenty states have enacted legislation that caps private contract retainage at 10% or less. One state, New Mexico, prohibits any retainage from being withheld from a construction contract.
The legislation can be considered a codification of what already is standard industry practice. But, it should provide some relief because general contractors and subcontractors will be able to pay bills sooner with the additional 5%.
Related Stories
Codes and Standards | Nov 28, 2016
Marines plan first net zero energy military base
The Albany, Ga., site will have ground source heat pumps and a biomass generator.
Codes and Standards | Nov 18, 2016
Mahesh Ramanujam takes reins as U.S. Green Building Council President and CEO
Ramanujam brings his tech and business consulting background to the post.
Codes and Standards | Nov 18, 2016
Canada GBC launching Zero Carbon Buildings Initiative
First step toward Zero Carbon Building Standard.
Codes and Standards | Nov 17, 2016
Santa Monica, Calif., passes historic net-zero ordinance
Includes more stringent commercial, multifamily building standards.
Codes and Standards | Nov 14, 2016
Six more states approve legal marijuana, creating opportunities for developers
Federal prohibition complicates the picture.
Codes and Standards | Nov 14, 2016
Los Angeles voters approve billions to tackle traffic and homelessness
The approved measures will create new rail lines and permanent housing.
Codes and Standards | Nov 9, 2016
NRMCA updates environmental impacts of concrete
The EPD now includes 88 companies, 72 mixes.
Codes and Standards | Nov 9, 2016
Louisiana flood projections require urgent action, officials say
The 'no net loss’ prediction now seems unrealistic.
Codes and Standards | Nov 8, 2016
American Concrete Institute offers new guide for repair of concrete buildings
The guide provides assistance on assessment and rehab.
Codes and Standards | Nov 7, 2016
The AISC prequalified seismic moment connection standard is now available
You can download the 2016 version for free.