How to develop a healthcare capital project using a 'true north charter'

How to develop a healthcare capital project using a 'true north charter'

Because healthcare projects take years to implement, developing a true north charter is essential for keeping the entire team on track and moving in the right direction. 


By Steve Higgs and Lora Schwartz, CBRE Healthcare | March 19, 2014
Birmingham (UK) Super Hospital under construction. Photo: Oosoom via Wikimedia Commons

Finding true north is just as essential for project teams and capital projects as it is for personal journeys and accurate navigation. Ask any surveyor. They will tell you that true north by definition is not magnetic North. To find true north from a magnetic compass you have to know the local magnetic variation and how it has varied over time. If you want to get from a point at the bottom of a map to one at the top, you must head true north.

Metaphorically, true north refers to one’s direction in life, as we are often uncertain where we stand, where we are going, and what is the right path for us personally. Knowing our true north enables us to follow the right path. 

The same holds true for the life of a healthcare project. Most healthcare projects can take four to five years or more to come to fruition when you account for the time vested in pre- and post-construction. Because healthcare projects take years to implement and given the size of the teams involved, developing a "true north charter" is essential for a healthcare capital project in order to keep the entire team on track and moving in the right direction. 

Defining a true north for a capital project takes time and effort, but can yield great benefits and the impact can be transformational. By communicating a shared vision and mission between the client, the project team, and the project, a true north charter can help inspire. 

The charter outlines the required conditions of satisfaction that should be strategic, operational, and project specific in nature. The charter should also assign measurable goals to help the team track and assess their achievements through the life of the project. The underlying benefit of defining a true north charter is developing team dynamics built on trust, accountability, transparency, respect, and collaboration. 

 

FINDING BALANCE IN CHOPPY WATERS

Navigating the capital planning and implementation process was much easier when the economy was humming. There was adequate access to funding, and the key driver for planning was volume. However, the healthcare industry has been rapidly evolving under the Affordable Care Act (ACA) and a soft economy. Healthcare reform has compelled health systems, hospitals, and physician groups to reduce costs and improve the quality of care-all with more regulatory requirements and less capital. 

Changes to reimbursement methods, along with reductions in healthcare provider compensation, are forcing health systems to rethink their approach to balancing their assets and liabilities, including health care real estate. These factors, particularly when combined with a projected increase in demand for ~79 million aging baby boomers and ~30 million newly insured patients, has operators and owners of real estate repositioning portfolio requirements.

 

SETTING VISION AND MISSION

Finding true north in these choppy waters requires a keen sense of the market and a strong sense of the institution’s purpose. This starts with the mission and vision of the organization. While all health institutions exist to serve the community, the current market has forced many organizations to focus their efforts on meeting the greatest needs and offers specialization only when the market can support it financially.  

A comprehensive strategic plan should highlight the organization’s vision, mission, and key areas of focus and be the baseline navigational tool for the institution and any capital spending. The true north for a capital project is then guided by the organization’s vision and mission statements, and further developed into a tangible project mission statement, guiding principles, target metrics, and target future state operations.   
 

 

One Midwest health system’s vision and mission states: 

“Our mission is to improve the health of the communities we serve through quality health care, education and research. Our vision is to be the best for those who need us. We value safety, compassion, respect and integrity.” 

A sample of a project mission statement that could accompany such a corporate mission statement could be: “Through collaboration, team integration, and best practices, the project team endeavors to provide the expanded and improved facility within the owner’s schedule, efficiency, and budget goals while providing high levels of quality, safety, and team satisfaction. By delivering the XYZ Health System New Tower Project, the project team will meet the expectations set by the Health System board, administration, caregivers, support staff, and community through our innovation, collaboration, and professionalism."

 

STAYING ON TRACK

While the preceding project mission statement provides a framework for positive motivation and influence, it does not deliver the tangible metrics needed to offer feedback to the project team or client to know if the project is on the right path or that the desired outcomes have been achieved. In order to provide continuous feedback and help steer towards the projects "true north," goals must be tangible and measurable. 

Guiding principles or goals should address the organization’s strategic and operational goals of the project, as well as the project-specific goals that address team performance. Each specific goal can then be supported by a tactic that can be mapped, tested, and monitored through specific key performance indicators, or KPIs. Prior to construction, KPIs for each tactic should be captured to establish baseline data in order for progress reports and post-occupancy data to be available for feedback and for comparison to future state.


 

Example strategic goal areas
- Increase Market Share
- Accommodate Private Bed Model
- Invest in New Model of Care
- Invest in Infrastructure to Decrease Operational Costs

Example Operational Goal Areas
- Maximize Staff Efficiency
- Improve Occupancy Efficiency by 15% (throughput)
- Reduce Cycle Times by 10%
- Reduce Medical Errors
- Increase Patient Satisfaction Scores
- Increase Flexibility of the Space

Example Project Goal Areas
- Safety During Construction
- Schedule Adherence
- Quality Product
- Cost Control
- Community Relationships
- Communication and Commitments
- Team Behavior and Relationships

 

ACHIEVING TRUE NORTH

Perhaps the greatest benefit to setting a capital project’s true north is the ability to provide feedback. It helps build trust for the project team, creates accountability, provides transparency, affords respect, and encourages collaboration for the entire team. Two reporting tools used to inform leadership and project teams on the success in navigating toward true north are the project status report (PSR) and the after action review (AAR).

The PSR, as its name suggests, provides an overview of your project’s trajectory. More than a reporting mechanism, the PSR should be a management tool that aides the team in achieving the established KPIs.

While many KPIs are tangible and measurable, others related to team dynamics and communication which may only be measured through a survey.  

Still, other outcomes can only be measured post-occupancy. The AAR is a structured debrief process and knowledge management tool that provides accountability and insight. Perhaps the greatest benefit of the AAR is the lessons learned that can be applied to future work, teams, and processes. The AAR is developed by the entire project team after project completion. It captures true-north desired outcomes, measurable goals, tactics, and pre-construction metrics in order to summarize the capital project’s process, work products and post construction results. 

 

CONCLUSION

Regardless of the terminology used, be sure to invest time in identifying the direction and process that will deliver the desired results for your project. By following the old adage of “plan your work and work your plan,” your project team will set the foundation to follow true north and ultimately achieve success. And in the process, you will find the underlying benefit of continual improvement. 

About the Authors
Steve Higgs is Managing Director and Lora Schwartz is Principal Consultant with CBRE Healthcare. 

Related Stories

Architects | Dec 10, 2018

The art and science of drawing: Humanizing the design process with a bit of controlled mayhem

Hand drawing reveals a dimension beyond those available in a CAD drawing or digital rendering.

Architects | Dec 7, 2018

2019 AIA Gold Medal awarded to Lord Richard Rogers, Hon. FAIA

The Gold Medal honors an individual whose significant body of work has had a lasting influence on the theory and practice of architecture.

3D Printing | Dec 7, 2018

Additive manufacturing heads to the jobsite

Prototype mobile 3D printing shop aims to identify additive manufacturing applications for construction jobsites.

Architects | Dec 6, 2018

Payette honored with 2019 AIA Architecture Firm Award

The award recognizes a firm that has consistently produced distinguished architecture for at least 10 years.

Biophilic Design | Nov 19, 2018

Biophilic design: What is it? Why it matters? And how do we use it?

As we continue to move toward the city and spend more time indoors, our day-to-day interaction with quality nature is shrinking. One contemporary concept to reverse this effect is biophilic design, a strategic approach to tap into—and harness—nature in the built environment.

Architects | Nov 6, 2018

Kohn Pedersen Fox opens three new offices

Following exciting current work, new commissions, and upcoming opportunities, global architecture firm embraces the future with new outposts.

Architects | Oct 2, 2018

Gensler, in latest report, highlights where resilient design could make the greatest impact on the built environment

The firm showcases its own recent projects as demonstrations for what can work in six areas.

Architects | Sep 24, 2018

Assembly (and rigorous planning) required: Managing the pros and cons of modular construction

While offering efficiency and flexibility, modular construction requires extensive planning and collaboration to avoid potential challenges.

Architects | Sep 19, 2018

Back it up: Parking lot trends

There are two shifts that we are seeing in parking lot planning and design – and these shifts are rooted in parking’s place at the intersection of environment, transportation, and market behavior.

Architects | Sep 14, 2018

We’ve entered the golden age of brain science. What does it mean for AEC firms?

New research from the SMPS Foundation explores the known principles and most recent research surrounding the human brain and behavioral science. The goal: to discover connections between the science and the AEC business. 

boombox1
boombox2
native1

More In Category

Warehouses

California bill would limit where distribution centers can be built

A bill that passed the California legislature would limit where distribution centers can be located and impose other rules aimed at reducing air pollution and traffic. Assembly Bill 98 would tighten building standards for new warehouses and ban heavy diesel truck traffic next to sensitive sites including homes, schools, parks and nursing homes.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021