Three Dykema Gossett attorneys discuss how supply-chain problems are complicating these agreements.


By John Caulfield, Senior Editor | October 28, 2022
Supply chain snags complicate construction contracts
A knotty supply chain heightens the importance of well-crafted construction contracts. Image: Pixabay

Global supply-chain delays and shortages have had an impact on construction contracts in terms of enforceability and risk, and have increased the likelihood of litigation to settle differences between parties, as well as the need to negotiate contracts that anticipate and minimize potential disputes.

“The allocation of risk is paramount to [achieving] the best possible outcome,” stated David Vanderhider, a Partner in the San Antonio office of Dykema Gossett, a Detroit-based national law firm with a substantial construction litigation practice.

During an October 26 webinar that explored the legal considerations of supply-chain impacts on contracts, Vanderhider was joined by two Partners from Dykema Gossett’s Chicago office: Steven Mroczkowski, who is Co-leader of the firm’s Construction Group; and Melanie Chico, Asset Practice Group Leader.

Chico predicted that supply-chain problems, including those related to costs and labor, are likely to spill into 2023. To which Vanderhider followed that earlier attention to planning will be needed to prepare for delays and cost overruns. Mroczkowksi added that collaboration is the key to allocating risk fairly, and he’s been seeing fewer take-it-or-leave-it clauses on contracts. But he also noted that “there’s no one-size-fits-all” solution.

Contractual risk and reward

The bulk of the webinar was taken up with the partners discussing different contract clauses. For example, Mroczkowski has seen an uptick in litigation over the applicability of force majeure, which is intended to excuse nonperformance following a particular event. (This is commonly known as the “Act of God” provision.) Such clauses are enforceable when the event is beyond the reasonable control of the party. And what is often being litigated, he said, is whether the affected party took sufficient steps to reduce its risk.

Mroczkowski cautioned that force majeure can vary by jurisdiction and how a project’s financing is structured, which is why he advises clients to customize the language of their contracts to the realities of the given project. “Sometimes, risk allocation boils down to an amendment in a contract,” observed Chico.

Another growing area of dispute, the partners said, is a contract’s Notice requirement, which spells out when a party is entitled to additional compensation or time. Chico said that too many notice clauses are loosely drawn up, and lack specificity when it comes to who, what, when, and why.

Indeed, the partners agreed that the precision of a particular clause’s language usually determines each party’s level of protection in a contract, especially at a time when outside forces that affect contractual agreements are in flux.

Litigate or arbitrate

Contracts are still being written too loosely
Construction contracts are still being written too loosely, leaving doors open for interpretation.
 

During the webinar, the partners touched on suspension and termination provisions, limitation of liability clauses, waivers for consequential damages (which owners are generally interested in), safety requirements, and insurance requirements. (Vanderhider said that insurance policies covering errors and omissions/professional liability “are trending,” and revolve around notice provisions.)

He said he’s been seeing contracts with more provisions that allow owners to withhold payments, with a notorious change in emphasis from “pay when paid” to “pay if paid,” which shifts more risk onto subcontractors. Chico added there are options “to be creative here,” such as payment clauses that kick in or are capped at certain thresholds, are limited to certain building materials, are tied to index pricing, or offer early payment for supply and storage actions.

The partners also took some time to debate how best to resolve disputes in general.

Vanderhider typically favors litigation, claiming that arbitration doesn’t always save time or money, and can place limits on the presentation of evidence and witnesses. “Many of the more common contract forms don’t reflect the reality of today’s economic climate,” he asserted. But Vanderhider also conceded that arbitration makes it easier for parties to keep evidence private

Chico, on the other hand, prefers arbitration, “mostly because it’s faster” than letting a lawsuit play out. She and Vanderhider agreed that dispute clauses in contracts are most effective when they are consistent throughout the construction chain. Mroczkowski recommended, too, that contracts include a provision mandating some level of arbitration so as not to halt the project while the parties try to resolve differences.

In conclusion, Mroczkowski cited four takeaways for contractual risk mitigation:

•Focus on your priorities

•Be proactive anticipating supply-chain impacts

•Ensure consistency in certain key contract terms

•Ensure compliance with local laws.

Related Stories

| Nov 13, 2013

First look: Renzo Piano's addition to Louis Kahn's Kimbell Art Museum [slideshow]

The $135 million, 101,130-sf colonnaded pavilion by the famed architect opens later this month. 

| Nov 11, 2013

4 trends driving the recovering commercial construction sector

Jones Lang LaSalle research reveals a four-point “new look” for the post-recession construction industry.

| Nov 8, 2013

Oversized healthcare: How did we get here and how do we right-size?

Healthcare facilities, especially our nation's hospitals, have steadily become larger over the past couple of decades. The growth has occurred despite stabilization, and in some markets, a decline in inpatient utilization.

| Nov 8, 2013

Can Big Data help building owners slash op-ex budgets?

Real estate services giant Jones Lang LaSalle set out to answer these questions when it partnered with Pacific Controls to develop  IntelliCommand, a 24/7 real-time remote monitoring and control service for its commercial real estate owner clients. 

| Nov 8, 2013

S+T buildings embrace 'no excuses' approach to green labs

Some science-design experts once believed high levels of sustainability would be possible only for low-intensity labs in temperate zones. But recent projects prove otherwise. 

| Nov 8, 2013

Net-zero bellwether demonstrates extreme green, multifamily style

The 10-unit zHome in Issaquah Highlands, Wash., is the nation’s first net-zero multifamily project, as certified this year by the International Living Future Institute.

| Nov 8, 2013

Walkable solar pavement debuts at George Washington University

George Washington University worked with supplier Onyx Solar to design and install 100 sf of walkable solar pavement at its Virginia Science and Technology Campus in Ashburn, Va.

| Nov 6, 2013

PECI tests New Buildings Institute’s plug load energy use metrics at HQ

Earlier this year, PECI used the NBI metrics to assess plug load energy use at PECI headquarters in downtown Portland, Ore. The study, which informed an energy-saving campaign, resulted in an 18 percent kWh reduction of PECI’s plug load.

| Nov 5, 2013

Net-zero movement gaining traction in U.S. schools market

As more net-zero energy schools come online, school officials are asking: Is NZE a more logical approach for school districts than holistic green buildings? 

| Nov 5, 2013

New IECC provision tightens historic building exemption

The International Energy Conservation Code has been revised to eliminate what has been seen as a blanket exemption for historic buildings.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021