Hospital serving New Hampshire’s largest metro is expanding its ED

Healthcare Facilities

Hospital serving New Hampshire’s largest metro is expanding its ED

A pandemic delay led the design-build team to rethink the addition’s reception, waiting, and triage areas.


By John Caulfield, Senior Editor | June 25, 2021
Rendering of expansion to Elliot Hospital's Emergency Department
Rendering of expansion to Elliot Hospital's Emergency Department

Earlier this week, Elliot Hospital, a 296-bed acute care facility in Manchester, N.H., broke ground on a 22,000-sf Emergency Department expansion that is designed to accommodate population growth in Greater Manchester, which increased by 3.17% over a decade to 113,035 in 2020.

BOND Building Construction is the GC on this project, which when completed in early 2023 will add three new trauma bays, 32 private rooms, four pediatric exam rooms, and six psychiatric evaluation rooms. It will also bump up the hospital’s capacity to treat patients to around 65,000 per year, compared to 57,000 currently.

The hospital's existing ED is a 32-bed, full-service Level II Trauma Center, according to the hospital’s website. “The additional space will improve operational workflows for staff to provide outstanding care and document at the bedside,” said John Leary, RN, Director of Emergency Services at Elliot Hospital.

BOND is providing design-build services for the project, whose designers include Environments for Health Architecture (e4h), Simon Design, Fuss & O’Neil, and BR+A Consulting Engineers. The expanded ED will house acute treatment, circulation, nurse station and staff areas, reception and waiting, security, support space, and an Xray machine.

 

REASSESSING SPACES AND SAFETY

Team from Bond Building Construction

The design-build team from BOND Building Construction, at the groundbreaking of the new addition to Elliot Hospital's ED.

 

This project was delayed by the COVID-19 outbreak, which gave the design-build team the time to redesign the reception, waiting room, and triage areas, and to add a rapid treatment area to the floorplan. BOND states that these modifications will allow the hospital to isolate infectious patients, increase ventilation and air filtration systems, and add more oxygen port, making it better equipped to handle future pandemics.

Phase 1 of the expansion—which will include construction of the new building (on an existing parking lot) and moving reception, triage and rapid triages into it—is scheduled for completion next February.

Elliot Hospital is a member of Solution Health, a regional healthcare organization that represents Southern New Hampshire Health and Elliot Health System. Neither disclosed the cost of the ED expansion, which has been in the works since 2017 when the hospital decided to reconstruct the layout of its Psychiatric Evaluation program.

Related Stories

University Buildings | Aug 19, 2021

School of Medicine completes on California University of Science and Medicine’s new Colton campus

The project was designed and built to address critical public health needs in an underserved region.

Resiliency | Aug 19, 2021

White paper outlines cost-effective flood protection approaches for building owners

A new white paper from Walter P Moore offers an in-depth review of the flood protection process and proven approaches.

Healthcare Facilities | Aug 18, 2021

20 years after developing the first open core hospital design here is what the firm has learned

Hospitals have traditionally used a “racetrack” layout, which accommodates patient rooms around the exterior and situates work areas and offstage functions in a central block.

Healthcare Facilities | Aug 5, 2021

Animal health, a huge market getting bigger, is fertile territory for engineering firm CRB

Regulatory compliance is seminal to any project’s design.

Healthcare Facilities | Aug 4, 2021

When the hospital becomes home

Patients and their loved ones need a variety of meaningful spaces outside the patient room to enhance feelings of optimism and control.

Healthcare Facilities | Aug 3, 2021

New 9-story outpatient facility planned on Washington University Medical Campus

Lawrence Group and Perkins Eastman are designing the project.

Healthcare Facilities | Jul 27, 2021

Texas Oncology continues to expand its reach

It is replacing and consolidating a number of its cancer care centers.

Contractors | Jul 23, 2021

The aggressive growth of Salas O'Brien, with CEO Darin Anderson

Engineering firm Salas O'Brien has made multiple acquisitions over the past two years to achieve its Be Local Everywhere business model. In this exclusive interview for HorizonTV, BD+C's John Caulfield sits down with the firm's Chairman and CEO, Darin Anderson, to discuss its business model.

Daylighting Designs | Jul 9, 2021

New daylighting diffusers come in three shape options

Solatube introduces its newest technology innovation to its commercial product line, the OptiView Shaping Diffusers.

boombox1
boombox2
native1

More In Category

Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.




Mass Timber

British Columbia hospital features mass timber community hall

The Cowichan District Hospital Replacement Project in Duncan, British Columbia, features an expansive community hall featuring mass timber construction. The hall, designed to promote social interaction and connection to give patients, families, and staff a warm and welcoming environment, connects a Diagnostic and Treatment (“D&T”) Block and Inpatient Tower.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021