Building Team Awards

Texas technopark: TechnipFMC John T. Gremp Campus

June 12, 2017
2 min read

The 173-acre TechnipFMC John T. Gremp Campus is the first element in north Houston’s Generation Park planned community. The 1.7 million-sf complex was completed in March 2016. Two months later, FMC Technologies and European oil and gas equipment technology company Technip formally announced their merger.

The new campus consolidates manufacturing, offices, and amenities for thousands of employees who were spread across six locations in the Houston area.

The Building Team, led by design giant Gensler, developer Trammell Crow, and contractor D.E. Harvey Builders, successfully dealt with requests from the owner after work had already begun.

First, TechnipFMC wanted to change two primary office buildings that were connected at only one level into a single building that would be connected on all levels. The project team used 3D visualization for fast design approval to insert a multi-level vertical connector into shared amenity space on each level.

Next, the owner added a new sophisticated process equipment product line to the project scope very late in the design process. The Building Team created a new design that allowed for placement of an in-ground rail system, underground utility distribution system, and automated welding machine system; all this, after most of the structure was already built.

TechnipFMC then announced that it was developing a new subsea equipment system that was significantly larger and heavier than the original building was designed for. The Building Team modified floor thicknesses, added 50 tons to the crane capacity, revised equipment circulation, and increased the size of the testing area without affecting foundation pours that were already in progress.

 

The Technip FMC campus in north Houston is marked by a 369,000-sf LEED Gold office building. The 2,036-space parking garage gives priority space to fuel-efficient vehicles. Landscape irrigation uses non-potable water. Photo: Ryan Gobuty/Gensler.

 

Building Team – Submitting firm, architect, interior architect Gensler Developer Trammell Crow Co. Structural engineer Cardno Haynes Whaley Mechanical engineer Wylie Consulting Engineers Contractor D.E. Harvey Builders

General Information – Size 1.7 million sf Construction cost Confidential Construction period April 2014 to March 2016 Delivery method Design-bid-build

 

Return to the 2017 Building Team Awards landing page

Sign up for Building Design+Construction Newsletters