flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

High-rise Art Deco courthouse gets a makeover in Amarillo, Texas

High-rise Art Deco courthouse gets a makeover in Amarillo, Texas

Recognized as one of the most significant Art Deco courthouses in Texas, the Potter County Courthouse is modernized and restored to its 1930s aesthetic. 


By David Barista, Editor-in-Chief | October 15, 2013
The project restored the buildings courtrooms and public corridors to their ori
The project restored the buildings courtrooms and public corridors to their original, warm terra cotta hues. It also involved r

Completed in 1932, the Potter County Courthouse is recognized as one of the most significant high-rise Art Deco courthouses in Texas, and among the most prominent in the country. Local architect W.C. Townes, of Townes, Lightfoot and Funk, designed the eight-story structure with a terra cotta fac?ade adorned in decorative figural and botanical bas-relief depicting the region’s cultural and natural history.

After more than 80 years of use, the courthouse was long overdue for an interior modernization and exterior restoration. The $15.5 million effort was undertaken as part of the Texas Historic Courthouse Preservation Program, a state-funded program that covered about one-third of the project’s cost. It included a complete fac?ade restoration—including repairing and re-anchoring damaged units and replacing mortar joints—and an overhaul of the interior spaces to meet current building and accessibility codes and the operational and functional needs of the county’s administrative offices and courts.

The original mechanical systems were replaced with a four-pipe scheme utilizing a 200-ton chiller and 250-ton cooling tower. An additional 60-ton, air-cooled chiller was placed on the roof, and 12 air-handling units were located on the various roofs at the fifth, sixth, and eighth floors. The new system, combined with automatic controls and enhanced thermal roof insulation, is expected to reduce energy costs by 20% annually.

POTTER COUNTY COURTHOUSE
Amarillo, Texas

 
Building Team 
Submitting firm: JQ (structural engineer) 
Owner: Potter County 
Architect: ArchiTexas 
MEP engineer: Johnson Consulting Engineers 
Construction manager: Southwest General Contractors 
General contractor: Journeyman Construction
 
General Information 
Size: 62,390 sf 
Construction cost: $15.5 million 
Construction time: November 2009 to August 2012 
Delivery method: Design-bid-build

The Reconstruction Awards judges hailed the Building Team for its painstaking efforts in preserving the historical elements of the building while modernizing the structure. To accommodate the new mechanical systems and other modern amenities, such as fire/life safety systems, information technology infrastructure, and high-density shelving units, the team devised several creative structural solutions:

• Tunnel expansion. To preserve the courthouse’s original, first-floor terrazzo floors, the team utilized the facility’s underfloor utility tunnels to run new insulated piping. Deemed inadequate to handle the new systems, the existing tunnels had to be carefully reinforced and expanded. In total, more than 200 feet of concrete- and masonry-lined tunnel was added on to the existing layout, allowing for the terrazzo flooring to remain intact.

• Clay tile floor removal. The added weight of the rooftop mechanical units and high-density shelving meant that certain areas of the existing structure on floors two through six would need to be reinforced. However, because the plaster ceiling finish was applied directly to the original clay tile and reinforced concrete joist floor system, structural members could not be inserted below the original ceiling level.

The solution involved removing portions of the original clay tile forms to allow the installation of new steel beams constructed from steel T-sections between the existing concrete joists, thereby increasing the floor load capacity. The use of T-sections in lieu of standard wide-flange sections facilitated access for completion of field connections to the existing structure and the placement of non-shrink grout between the top of the steel members and the underside of the original floor slab to provide full load transfer.

• Use of CFRP strips. In order to accommodate new stairs, vertical chases, and mechanical infrastructure, numerous openings of various sizes had to be cut into the slab on floors seven and eight. The original floor structure on these levels is eight-inch reinforced concrete slabs spanning the concrete beams.

To maintain the structural integrity and continuity of the floor slabs, strips of laminated, 1?4-inch-thick carbon fiber reinforcement polymer (CFRP) were used to redistribute the loads adjacent to and around the openings. Larger openings for the stairs and chases called for additional reinforcement, and CFRP strips were placed on top or below the slab, corresponding to the tension zone of the slab system.

In several locations, strips were placed in both directions around the openings to properly distribute the load.

“We liked how the team carefully pre- served the clay-tile floor and the reinforced concrete slab with the strengthening schemes hidden out of sight,” said judge K. Nam Shiu, Senior VP, Director of Restoration Services, Walker Restoration Consultants (www.walkerrestoration.com). “They successfully provided up-to-date floor functionality while keeping the layout and look of the original building.”

 

The Building Team took careful measures to avoid disturbing the historical elements in the building. This included expanding an existing utility tunnel (above) and applying special structural reinforcement polymer to select concrete frame members (top). Photo: Brenda Bagot

Related Stories

| Feb 17, 2012

MacInnis joins Gilbane board of directors

MacInnis is the chairman and recently retired CEO of Connecticut-based EMCOR Group, Inc.

| Feb 16, 2012

Gain greater agility and profitability with ArchiCAD BIM software

White paper was written with the sole purpose of providing accurate, reliable information about critical issues related to BIM and what ArchiCAD with advanced technology such as the GRAPHISOFT BIM Server provide as an answer to address these issues.

| Feb 16, 2012

TLC Engineering for Architecture opens Chattanooga office

TLC Engineering for Architecture provides mechanical, electrical, structural, plumbing, fire protection, communication, technology, LEED, commissioning and energy auditing services.

| Feb 16, 2012

Summit Design + Build begins build-out for Emmi Solutions in Chicago

The new headquarters will total 20,455 sq. ft. and feature a loft-style space with exposed masonry and mechanical systems, 15 foot clear ceilings, two large rooftop skylights and private offices with full glass partition walls.

| Feb 16, 2012

Highland named president of McCarthy Building Companies’ California region

Highland moved into this new role in January 2012 following a six-month transition period with Carter Chappell, the company’s former president, California region.

| Feb 16, 2012

Big-box retailers not just for DIYers

Nearly half of all contractor purchases made from stores like Home Depot and Lowe's.

| Feb 16, 2012

4.8-megawatt solar power system completed at Jersey Gardens Mall

Solar array among the largest rooftop systems in North America.

| Feb 15, 2012

Fourth-generation Ryan to lead Ryan Companies AE team

Ryan leads a team of eight architects, four civil engineers, two landscape architects and two virtual building specialists in their efforts to realize their customer’s vision and needs through Ryan’s integrated project delivery system.

| Feb 15, 2012

NAHB sees gradual improvement in multifamily sales for boomers

However, since the conditions of the current overall housing market are limiting their ability to sell their existing homes, this market is not recovering as quickly as might have been expected.

| Feb 15, 2012

Skanska secures $87M contract for subway project

The construction value of the project is $261.9 M. Skanska will include its full share, $87 M, in the bookings for Skanska USA Civil for the first quarter 2012.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021