Guardian Building, Detroit, Mich.

Guardian Building, Detroit, Mich.


By By Robert Cassidy, Editorial Director | October 12, 2010

The relocation and consolidation of hundreds of employees from seven departments of Wayne County, Mich., into the historic Guardian Building in downtown Detroit is a refreshing tale of smart government planning and clever financial management that will benefit taxpayers in the economically distressed region for years to come.

The Guardian Building was designed by Wirt C. Rowland, of Smith Hinchman and Grylls (now SmithGroup) and completed in 1929 as the Union Guardian Building. It combined Native American, Aztec, and Arts & Crafts influences in an inspiring display of Art Deco enthusiasm, with polychromed terra cotta on its exterior, travertine marble from Italy and Numidian marble from Africa on the walls and floors, Monel metal in the ornamental screen in the lobby, custom tiles by Mary Chase Stratton’s Pewabic Pottery, and sculpted architectural reliefs by Corrado Parducci—no wonder people called it “The Cathedral of Finance.” It has been designated a National Historic Landmark.

For two decades, the county had been paying $5.2 million a year in rent for space at 600 Randolph in Detroit—more than $100 million total. Seven years ago, as the lease was running out, the county purchased the Guardian Building (along with another building and a parking structure) for $14 million and bonded another $13.5 million for tenant improvements.

By 2008, with construction costs at favorable levels, the county bonded for another $30 million to change the project scope and accelerate the capital improvement schedule. The Building Team brought the project in at $33,261,000 in construction costs, $11,535,000 (25.7%) below budget.

The HVAC system was upgraded, improving indoor air quality and energy efficiency, and a distributed direct digital controls system was installed, along with video conferencing technology, flat screen monitors for public presentations, electronic faxing to reduce the use of paper, and Voice Over IP, which eliminated 3,500 land lines and will save $500,000 in phone costs.

Instead of shelling out $5.2 million a year at 600 Randolph, plus $1 million at another building, the annual operating costs for the county’s space in the Guardian Building is only $1.9 million. With payment of the debt service, taxpayers will come out $2 million ahead every year—and the county owns a historic building with an estimated current value of $60-100 million. BD+C

PROJECT SUMMARY

Building Team

Owner: Department of Economic Development, Wayne County, Mich.

Submitting firm: SmithGroup (architect, AOR, SE/MEP engineer)

Property manager: Sterling Group

Construction administrator: Hines

General contractor: Sachse Construction/Tooles Contracting Group JV

General Information

Area: 495,600 rentable sf

Construction Cost: $33,261,000

Construction time: September 2008 to December 2009

Delivery method: PM/GC

Related Stories

| Jul 18, 2012

Green expert Kats joins GreenWizard as an advisor

Kats' role is to help further expand GreenWizard’s impact in the sustainable construction industry.

| Jul 18, 2012

Construction employment stagnates in June

Lack of hiring in construction combined with job growth elsewhere threatens to create skilled-labor gap once contractors are ready to hire again.

| Jul 18, 2012

Legat & Kingscott relocates architecture/interior design office

Move enables the architecture/interior design firm to better serve its expanding clientele.

| Jul 18, 2012

Alcoa appoints Hunter Architectural Manager

Hunter to operate with the goal of driving specification, new product adoption and overall demand for the Alcoa BCS North America product range.

| Jul 17, 2012

AIA and Architecture for Humanity select Disaster Response Grant recipients

Awards help each group implement their locally driven preparedness project in the second half of the year.  

| Jul 17, 2012

KM/Plaza changes name to Plaza Construction

Lands new projects including the Perry South Beach Hotel and Dadeland Mall Kendall Wing Expansion.

| Jul 17, 2012

Dr. Phillips Charities Headquarters Building receives LEED Silver

The building incorporates sustainable design features, environmentally-friendly building products, energy efficient systems, and environmentally sensitive construction practices.

| Jul 16, 2012

BD+C Under 40 Leadership Summit scheduled

Attendee registration for U40 Summit II now open.

| Jul 16, 2012

Construction spending at 2 ½ year peak

Construction economist Ken Simonson says that four private nonresidential categories each posted 12-month spending increases of more than 25%: power and energy construction, 35%; hotels, 29%; educational and manufacturing, 27% apiece.

| Jul 16, 2012

Chen named design director at Heery

Chen comes to Heery from his own firm, Mark Chen Architect, a design and planning consulting firm, based in New York City, whose recent work includes large-scale planning studies for mixed-use projects.

boombox1
boombox2
native1

More In Category

Warehouses

California bill would limit where distribution centers can be built

A bill that passed the California legislature would limit where distribution centers can be located and impose other rules aimed at reducing air pollution and traffic. Assembly Bill 98 would tighten building standards for new warehouses and ban heavy diesel truck traffic next to sensitive sites including homes, schools, parks and nursing homes.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021