Guardian Building, Detroit, Mich.

Guardian Building, Detroit, Mich.


By By Robert Cassidy, Editorial Director | October 12, 2010

The relocation and consolidation of hundreds of employees from seven departments of Wayne County, Mich., into the historic Guardian Building in downtown Detroit is a refreshing tale of smart government planning and clever financial management that will benefit taxpayers in the economically distressed region for years to come.

The Guardian Building was designed by Wirt C. Rowland, of Smith Hinchman and Grylls (now SmithGroup) and completed in 1929 as the Union Guardian Building. It combined Native American, Aztec, and Arts & Crafts influences in an inspiring display of Art Deco enthusiasm, with polychromed terra cotta on its exterior, travertine marble from Italy and Numidian marble from Africa on the walls and floors, Monel metal in the ornamental screen in the lobby, custom tiles by Mary Chase Stratton’s Pewabic Pottery, and sculpted architectural reliefs by Corrado Parducci—no wonder people called it “The Cathedral of Finance.” It has been designated a National Historic Landmark.

For two decades, the county had been paying $5.2 million a year in rent for space at 600 Randolph in Detroit—more than $100 million total. Seven years ago, as the lease was running out, the county purchased the Guardian Building (along with another building and a parking structure) for $14 million and bonded another $13.5 million for tenant improvements.

By 2008, with construction costs at favorable levels, the county bonded for another $30 million to change the project scope and accelerate the capital improvement schedule. The Building Team brought the project in at $33,261,000 in construction costs, $11,535,000 (25.7%) below budget.

The HVAC system was upgraded, improving indoor air quality and energy efficiency, and a distributed direct digital controls system was installed, along with video conferencing technology, flat screen monitors for public presentations, electronic faxing to reduce the use of paper, and Voice Over IP, which eliminated 3,500 land lines and will save $500,000 in phone costs.

Instead of shelling out $5.2 million a year at 600 Randolph, plus $1 million at another building, the annual operating costs for the county’s space in the Guardian Building is only $1.9 million. With payment of the debt service, taxpayers will come out $2 million ahead every year—and the county owns a historic building with an estimated current value of $60-100 million. BD+C

PROJECT SUMMARY

Building Team

Owner: Department of Economic Development, Wayne County, Mich.

Submitting firm: SmithGroup (architect, AOR, SE/MEP engineer)

Property manager: Sterling Group

Construction administrator: Hines

General contractor: Sachse Construction/Tooles Contracting Group JV

General Information

Area: 495,600 rentable sf

Construction Cost: $33,261,000

Construction time: September 2008 to December 2009

Delivery method: PM/GC

Related Stories

Giants 400 | Sep 10, 2015

MILITARY SECTOR GIANTS: Clark Group, HDR, Fluor top rankings of nation's largest military sector AEC firms

BD+C's rankings of the nation's largest military sector design and construction firms, as reported in the 2015 Giants 300 Report

Museums | Sep 9, 2015

Bauhaus Museum Dessau names two design winners

The German museum chose one sleek, no-nonsense concept and one colorful, complex entry.

Giants 400 | Sep 8, 2015

RETAIL SECTOR GIANTS: Callison RTKL, PCL Construction, Jacobs among top retail sector AEC firms

BD+C's rankings of the nation's largest retail sector design and construction firms, as reported in the 2015 Giants 300 Report

BIM and Information Technology | Sep 7, 2015

The power of data: How AEC firms and owners are using analytics to transform design and construction

Case’s bldgs = data conference highlighted how collecting data about personal activities can inform design and extend the power of BIM/VDC.

Sponsored | Architects | Sep 4, 2015

Sydney-based Architectural Firm Dramatically Increases Productivity

ArchiOffice enables the firm to spend less time on managing projects by providing relevant information in one place.

Industrial Facilities | Sep 3, 2015

DATA CENTER SECTOR GIANTS: Fluor, Gensler, Holder Construction among top data center AEC firms

BD+C's rankings of the nation's largest data center sector design and construction firms, as reported in the 2015 Giants 300 Report

High-rise Construction | Sep 3, 2015

Rafael Viñoly's 'Walkie-Talkie' tower named U.K.'s worst new building

The curved, glass tower at 20 Fenchurch Street in London has been known to reflect intense heat onto the streets below (in one instance damaging a car) and cause severe wind gusts. 

Airports | Aug 31, 2015

Surveys gauge users’ satisfaction with airports

Several surveys gauge passenger satisfaction with airports, as flyers and airlines weigh in on technology, security, and renovations. 

Airports | Aug 31, 2015

Small and regional airports in a dogfight for survival

Small and regional airports are in a dogfight for survival. Airlines have either cut routes to non-hub markets, or don’t provide enough seating capacity to meet demand.

Airports | Aug 31, 2015

Airports expand rental car facilities to ease vehicular traffic at their terminals

AEC teams have found fertile ground in building or expanding consolidated rental car facilities, which are the No. 1 profit centers for most airports.

boombox1
boombox2
native1

More In Category

Warehouses

California bill would limit where distribution centers can be built

A bill that passed the California legislature would limit where distribution centers can be located and impose other rules aimed at reducing air pollution and traffic. Assembly Bill 98 would tighten building standards for new warehouses and ban heavy diesel truck traffic next to sensitive sites including homes, schools, parks and nursing homes.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021