A grim Market Outlook foresees more shortages that impede construction

Contractors

A grim Market Outlook foresees more shortages that impede construction

Consigli’s new report, though, does offer glimmers of relief on the supply-chain front, and strategies for risk management.


By John Caulfield, Senior Editor | October 29, 2021
Consigli's latest market outlook expects labor shortages to continue through next year. Image: Pixabay
Labor shortages continue to impact construction projects, and could get worse next year, according to Consigli's latest Market Outlook. Image: Pixabay

The good news: the cargo and transportation snags that have encumbered building material availability this year showed signs of finally easing in September.

The bad news: the lack of material supply and increasing demand for labor are keeping prices high, to the point where manufacturers aren’t willing to hold price quotes for more than a week, if at all.

That, in a nutshell, is the state of the construction market, which the general contractor Consigli lays out in its Market Outlook for October 2021. The Outlook, written by the firm’s Director of Purchasing Peter Capone and Vice President of Preconstruction Jared Lachapelle, sends up red alerts about the availability of six product categories—steel joist, steel deck, MEP equipment, roofing insulation, lab casework, and mineral/rock wool—whose lead times for fabrication after release, as of Sept. 1, ranged from 20 to 40 weeks, with steel joists having the longest wait time.

The Outlook reports a 12 percent average price escalation for the 15 building materials tracked, and anticipates another 3 percent bump through the final quarter of this year. Roofing insulation, roofing membranes, gypsum wallboard, light-gauge metal framing, and glass exceed the overall averages.

As a result of large manufacturers not willing to take risks on escalating prices. “subcontractors are being changed market increases at the time of delivery,” states the report.

 

The lead times for several building materials exceeds 20 weeks. Image: Consigli
Consigli identifies several building materials for which there have been “significant” lead time delays and price hikes. Image: Consigli
 

MANAGING RISK TAKES DISCIPLINE

Consigli’s strategies for risk management include:

•lock in prices with subs that are willing to share risk

•buy in bulk quantities whenever possible

•consider alternative supply sources

•implement stringent quality assurance and control measures

•focus on weekly materials delivery verification

•pre-purchase and warehouse materials

•identify peak manpower needs

•utilize prefabrication that takes labor off site

•partner with trades through design-assist

Consigli thinks labor shortages could get worse in the second half of next year. The severity will depend, in part, on vaccination mandates at a time when a sizable number of construction workers still refuse to be vaccinated. But even a fully vaccinated workforce might struggle to keep pace with construction demand that the pending $1 trillion infrastructure bill, if passed, would further pressure.

The Outlook notes that some manufacturers are focusing their production capacities on commonly used materials like drywall and MEP equipment, which is limiting—and sometimes halting—the production of specialty products. And AEC firms need to be vigilant about maintaining compatibility and quality when manufacturers source products from alternate vendors.

Consigli sees some light at the end of this supply tunnel. Its Outlook notes that steel prices are starting to level off as production increases. But citing the National Roofing Contractors Association, Consigli also cautions that shortages in roofing materials and insulation (whose lead time right now is 24 weeks) will continue through next year because of raw materials supply issues.

Related Stories

| Dec 6, 2011

New office building features largest solar panel system in New Orleans

Woodward Design+Build celebrates grand opening of new green headquarters in Central City.

| Dec 5, 2011

New York and San Francisco receive World Green Building Council's Government Leadership Awards

USGBC commends two U.S. cities for their innovation in green building leadership.

| Dec 5, 2011

Summit Design+Build begins renovation of Chicago’s Esquire Theatre

The 33,000 square foot building will undergo an extensive structural remodel and core & shell build-out changing the building’s use from a movie theater to a high-end retail center.

| Dec 5, 2011

Fraser Brown MacKenna wins Green Gown Award

Working closely with staff at Queen Mary University of London, MEP Engineers Mott MacDonald, Cost Consultants Burnley Wilson Fish and main contractor Charter Construction, we developed a three-fold solution for the sustainable retrofit of the building.

| Dec 5, 2011

RJM Construction begins building Nova Classical Academy in St. Paul

As the general contractor, RJM is constructing the 94,000-sf building that will consolidate the St. Paul school’s two other locations. 

| Dec 5, 2011

Gables Residential brings mixed-use building to Houston's Tanglewood area

The design integrates a detailed brick and masonry facade, acknowledging the soft pastel color palette of the surrounding Mediterranean heritage of Tanglewood.

| Dec 5, 2011

SchenkelShultz Architecture designs Dr. Phillips Charities Headquarters building in Orlando

The building incorporates sustainable architectural features, environmentally friendly building products, energy-efficient systems, and environmentally-sensitive construction practices.

| Dec 2, 2011

What are you waiting for? BD+C's 2012 40 Under 40 nominations are due Friday, Jan. 20

Nominate a colleague, peer, or even yourself. Applications available here.

| Dec 2, 2011

Legrand joins White House initiative to spur energy efficiency in commercial buildings

Company agrees to aggressive energy savings and reporting.

boombox1
boombox2
native1

More In Category



Curtain Wall

7 steps to investigating curtain wall leaks

It is common for significant curtain wall leakage to involve multiple variables. Therefore, a comprehensive multi-faceted investigation is required to determine the origin of leakage, according to building enclosure consultants Richard Aeck and John A. Rudisill with Rimkus. 


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021