A grim Market Outlook foresees more shortages that impede construction

Contractors

A grim Market Outlook foresees more shortages that impede construction

Consigli’s new report, though, does offer glimmers of relief on the supply-chain front, and strategies for risk management.


By John Caulfield, Senior Editor | October 29, 2021
Consigli's latest market outlook expects labor shortages to continue through next year. Image: Pixabay
Labor shortages continue to impact construction projects, and could get worse next year, according to Consigli's latest Market Outlook. Image: Pixabay

The good news: the cargo and transportation snags that have encumbered building material availability this year showed signs of finally easing in September.

The bad news: the lack of material supply and increasing demand for labor are keeping prices high, to the point where manufacturers aren’t willing to hold price quotes for more than a week, if at all.

That, in a nutshell, is the state of the construction market, which the general contractor Consigli lays out in its Market Outlook for October 2021. The Outlook, written by the firm’s Director of Purchasing Peter Capone and Vice President of Preconstruction Jared Lachapelle, sends up red alerts about the availability of six product categories—steel joist, steel deck, MEP equipment, roofing insulation, lab casework, and mineral/rock wool—whose lead times for fabrication after release, as of Sept. 1, ranged from 20 to 40 weeks, with steel joists having the longest wait time.

The Outlook reports a 12 percent average price escalation for the 15 building materials tracked, and anticipates another 3 percent bump through the final quarter of this year. Roofing insulation, roofing membranes, gypsum wallboard, light-gauge metal framing, and glass exceed the overall averages.

As a result of large manufacturers not willing to take risks on escalating prices. “subcontractors are being changed market increases at the time of delivery,” states the report.

 

The lead times for several building materials exceeds 20 weeks. Image: Consigli
Consigli identifies several building materials for which there have been “significant” lead time delays and price hikes. Image: Consigli
 

MANAGING RISK TAKES DISCIPLINE

Consigli’s strategies for risk management include:

•lock in prices with subs that are willing to share risk

•buy in bulk quantities whenever possible

•consider alternative supply sources

•implement stringent quality assurance and control measures

•focus on weekly materials delivery verification

•pre-purchase and warehouse materials

•identify peak manpower needs

•utilize prefabrication that takes labor off site

•partner with trades through design-assist

Consigli thinks labor shortages could get worse in the second half of next year. The severity will depend, in part, on vaccination mandates at a time when a sizable number of construction workers still refuse to be vaccinated. But even a fully vaccinated workforce might struggle to keep pace with construction demand that the pending $1 trillion infrastructure bill, if passed, would further pressure.

The Outlook notes that some manufacturers are focusing their production capacities on commonly used materials like drywall and MEP equipment, which is limiting—and sometimes halting—the production of specialty products. And AEC firms need to be vigilant about maintaining compatibility and quality when manufacturers source products from alternate vendors.

Consigli sees some light at the end of this supply tunnel. Its Outlook notes that steel prices are starting to level off as production increases. But citing the National Roofing Contractors Association, Consigli also cautions that shortages in roofing materials and insulation (whose lead time right now is 24 weeks) will continue through next year because of raw materials supply issues.

Related Stories

| Feb 24, 2012

Larry Lord joins HDR Architecture as south region science and technology director

A founding partner at Lord, Aeck & Sargent, Lord is nationally renowned for his leadership in architecture for complex projects.

| Feb 24, 2012

Pottorff elevated to principal at Ricci Greene Associates

Pottorff is recognized in the justice field as an expert solely dedicated to the design and planning of courts and urban jails in both the U.S. and Canada.

| Feb 24, 2012

Skanska hires Tingle as senior VP and national director for its Sports Center of Excellence

Tingle has worked in the architecture and construction industries for more than 30 years, and for the last 23 years, he has focused primarily on large-scale sports construction projects

| Feb 23, 2012

Federal budget cuts put major building projects on hold

A plan to build the National Bio and Agro-Defense Facility in Kansas is among several major building projects in jeopardy after the Obama administration’s 2013 budget was unveiled. The budget would cut all construction spending for the facility.

| Feb 23, 2012

Regulators investigating construction accident at World Trade Center

The New York Port Authority and the city’s fire and building departments are investigating an accident at the World Trade Center construction site in lower Manhattan after a crane dropped steel beams that fell about 40 stories onto the truck that delivered them.

| Feb 23, 2012

New Virginia statewide building code goes into effect March 1

After March 1, all building plans in Virginia must adhere to the 2009 code that was adopted a year ago.

| Feb 22, 2012

ACI BIM manual for cast-in-place concrete in development

The improved communication, coordination, and collaboration afforded by BIM implementation have already been shown to save time and money in projects.

| Feb 22, 2012

Siemens earns LEED certification for Maryland office

The Beltsville facility, which also earned the ENERGY STAR Label for energy performance, implemented a range of energy efficiency, water conservation and sustainable operations measures as part of the certification process.

| Feb 22, 2012

CISCO recognizes Gilbane for quality construction, design, and safety

The project employed more than 2,000 tradespeople for a total of 2.1 million hours worked – all without a single lost-time accident. 

boombox1
boombox2
native1

More In Category



Curtain Wall

7 steps to investigating curtain wall leaks

It is common for significant curtain wall leakage to involve multiple variables. Therefore, a comprehensive multi-faceted investigation is required to determine the origin of leakage, according to building enclosure consultants Richard Aeck and John A. Rudisill with Rimkus. 


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021