A grim Market Outlook foresees more shortages that impede construction

Contractors

A grim Market Outlook foresees more shortages that impede construction

Consigli’s new report, though, does offer glimmers of relief on the supply-chain front, and strategies for risk management.


By John Caulfield, Senior Editor | October 29, 2021
Consigli's latest market outlook expects labor shortages to continue through next year. Image: Pixabay
Labor shortages continue to impact construction projects, and could get worse next year, according to Consigli's latest Market Outlook. Image: Pixabay

The good news: the cargo and transportation snags that have encumbered building material availability this year showed signs of finally easing in September.

The bad news: the lack of material supply and increasing demand for labor are keeping prices high, to the point where manufacturers aren’t willing to hold price quotes for more than a week, if at all.

That, in a nutshell, is the state of the construction market, which the general contractor Consigli lays out in its Market Outlook for October 2021. The Outlook, written by the firm’s Director of Purchasing Peter Capone and Vice President of Preconstruction Jared Lachapelle, sends up red alerts about the availability of six product categories—steel joist, steel deck, MEP equipment, roofing insulation, lab casework, and mineral/rock wool—whose lead times for fabrication after release, as of Sept. 1, ranged from 20 to 40 weeks, with steel joists having the longest wait time.

The Outlook reports a 12 percent average price escalation for the 15 building materials tracked, and anticipates another 3 percent bump through the final quarter of this year. Roofing insulation, roofing membranes, gypsum wallboard, light-gauge metal framing, and glass exceed the overall averages.

As a result of large manufacturers not willing to take risks on escalating prices. “subcontractors are being changed market increases at the time of delivery,” states the report.

 

The lead times for several building materials exceeds 20 weeks. Image: Consigli
Consigli identifies several building materials for which there have been “significant” lead time delays and price hikes. Image: Consigli
 

MANAGING RISK TAKES DISCIPLINE

Consigli’s strategies for risk management include:

•lock in prices with subs that are willing to share risk

•buy in bulk quantities whenever possible

•consider alternative supply sources

•implement stringent quality assurance and control measures

•focus on weekly materials delivery verification

•pre-purchase and warehouse materials

•identify peak manpower needs

•utilize prefabrication that takes labor off site

•partner with trades through design-assist

Consigli thinks labor shortages could get worse in the second half of next year. The severity will depend, in part, on vaccination mandates at a time when a sizable number of construction workers still refuse to be vaccinated. But even a fully vaccinated workforce might struggle to keep pace with construction demand that the pending $1 trillion infrastructure bill, if passed, would further pressure.

The Outlook notes that some manufacturers are focusing their production capacities on commonly used materials like drywall and MEP equipment, which is limiting—and sometimes halting—the production of specialty products. And AEC firms need to be vigilant about maintaining compatibility and quality when manufacturers source products from alternate vendors.

Consigli sees some light at the end of this supply tunnel. Its Outlook notes that steel prices are starting to level off as production increases. But citing the National Roofing Contractors Association, Consigli also cautions that shortages in roofing materials and insulation (whose lead time right now is 24 weeks) will continue through next year because of raw materials supply issues.

Related Stories

| Jan 19, 2015

Architecture for Humanity closes office, plans to file for bankruptcy

After more than 15 years of work, the nonprofit design group Architecture for Humanity has closed its San Francisco office and plans to file for Chapter 7 bankruptcy protection.

| Jan 17, 2015

When is a train station not a train station? When it’s a performance venue

You can catch a train at Minneapolis’s new Target Field Station. You can also share in an experience. That’s what ‘Open Transit’ is all about.

| Jan 16, 2015

Artsy lifeguard stations will brighten Toronto’s snowy beach

Five winning designs have been unveiled for lifeguard stands that will double as public space art installations on Toronto's beach.

| Jan 16, 2015

New York City construction costs continue to climb

A study released by the New York Building Congress shows that construction costs in Manhattan have risen 5% in each of the last two years.

| Jan 15, 2015

A reconstructed Taliesin West is the largest Frank Lloyd Wright LEGO Model [slideshow]

Artist Adam Reed Tucker used 180,000 LEGO pieces and 420 hours of work to recreate Frank Lloyd Wright's Taliesin West campus.

| Jan 15, 2015

Construction materials prices fall in November

Construction input prices dipped 1.4% during the final month of 2014 and are down nearly 1% on a year-over-year basis, according to the Jan. 15 producer price index release from the U.S. Department of Labor. 

| Jan 15, 2015

Libeskind unveils 'zig zag' plan for recreational center near Vilnius ski area

Perched on the highest peak between Vilnius' historic quarter and downtown, the Vilnius Beacon will be a hub for visiting skiers and outdoor enthusiasts.

| Jan 14, 2015

10 change management practices that can ease workplace moves

No matter the level of complexity, workplace change can be a challenge for your client's employees. VOA's Angie Lee breaks down the process of moving offices as efficiently as possible, from creating a "change team" to hosting hard-hat tours.

| Jan 13, 2015

Steven Holl unveils design for $450 million redevelopment of Houston's Museum of Fine Arts

Holl designed the campus’ north side to be a pedestrian-centered cultural hub on a lively landscape with ample underground parking. 

| Jan 9, 2015

Santiago Calatrava talks with BBC about St. Nicholas Church on Ground Zero

Calatrava reveals that he wanted to retain the “tiny home” feel of the original church building that was destroyed with the twin towers on 9/11.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021