A recent decision by the Armed Services Board of Contract Appeals illustrates the importance for GCs to obtain solid commitments from key subcontractors when seeking government contracts.
The ASBCA earlier this year dismissed a construction contractor’s claim for increased costs on a contract for the construction of dissolved oxygen injection systems in the Savannah River. The case involved a GC whose marine subcontractor withdrew its bid after a delay.
The contractor subsequently said that it would incur more than $3 million in increased costs. The ASBCA ruled that there was no evidence that the suspension of about 60 days to resolve a bid protest was anything but reasonable.
It also found that there was no causal connection between the suspension and the GC’s increased costs. The key lesson: prime contractors should promptly execute subcontracts with key subcontractors.
Related Stories
Codes and Standards | Apr 8, 2021
Sensors used in tunable lighting systems found to have high reliability
DOE study investigated items used to control lumen depreciation, chromaticity shifts, and changes in drivers.
Codes and Standards | Apr 7, 2021
Red tape ruined the U.K.’s home retrofit program
Lessons learned could help US avoid that fate.
Codes and Standards | Apr 6, 2021
Lendlease achieves net-zero carbon in Boston, Chicago multifamily portfolio
New projects in New York, Los Angeles on track to reach goal.
Codes and Standards | Apr 5, 2021
Specification for sliding door, lift and slide roller assemblies updated
Addresses market trend toward heavy sliding doors.
Codes and Standards | Apr 5, 2021
Construction employment rebounds in March following February drop
Rising costs, supply-chain woes, and cancellations threaten outlook.
Codes and Standards | Apr 2, 2021
Intl. Code Council’s new development system could be a brake on building decarbonization
Local governments lose influence on creating new energy efficiency rules.
Codes and Standards | Apr 1, 2021
Cuomo proposes strengthened NY building codes to boost efficiency
Would apply to appliance, equipment efficiency and reduce water use.
Codes and Standards | Mar 25, 2021
N.C.’s Outer Banks’ communities struggle for ways to keep the sea from overrunning them
Tax hikes for beach replenishment offer temporary solution.
Codes and Standards | Mar 24, 2021
Perkins&Will’s D.C. office pledges to eliminate embodied carbon in commercial interiors
Firm aims to reach goal on all designs by 2030.
Codes and Standards | Mar 23, 2021
The 15-minute city may not work in much of North America
Segregated neighborhoods and car-centric cities may not adapt to the European model.