Georgia court limits contractors’ ability to foreclose on liens

Georgia court limits contractors’ ability to foreclose on liens

The Georgia Court of Appeals ruled in 182 Tenth, LLC v. Manhattan Construction Company that lien claimants such as contractors, subcontractors, and materialmen, may not foreclose on a lien that includes unpaid general condition costs.


December 7, 2012

On private construction projects, contractors ordinarily have the right to file a mechanic's or materialman’s lien under applicable state law to collect unpaid sums due on a construction contract. However, on July 11, the Georgia Court of Appeals ruled in 182 Tenth, LLC v. Manhattan Construction Company that lien claimants such as contractors, subcontractors, and materialmen, may not foreclose on a lien that includes unpaid general condition costs.

These non-lienable costs may include: overhead, administrative, preconstruction, mobilization, phone/water, power, job site trailer, safety, and premiums for builder’s risk and general liability insurance.

Click here to learn more. +

Related Stories

| Dec 15, 2011

NRDC charges Maine governor with weakening green wood requirement

The FSC program is administered through the Leadership in Energy and Environmental Design (LEED) and requires wood to be harvested in a sustainable way.

| Dec 15, 2011

Post-tornado, Tuscaloosa seeks to create walkable urban, retail areas

Block sizes initially were limited to a maximum perimeter of 1,750 feet, with no side of the block being longer than 500 feet.

| Dec 15, 2011

Allentown, Pa. city council asked to repeal union-friendly law

The mayor of Allentown, Pa. asked the City Council to repeal a year-old ordinance that forces contractors to hire union workers for large city projects funded with state and federal dollars.

| Dec 13, 2011

LEED-EB outpaces LEED for new construction

The U.S. Green Building Council's (USGBC's) LEED certifications for existing buildings standard is outpacing LEED for new buildings for the first time.

| Dec 13, 2011

Regulators charge pervasive abuse of construction workers in Connecticut

Federal and state regulators say they have uncovered what they call "widespread noncompliance" with minimum wage and overtime laws in Connecticut's construction industry.

| Dec 13, 2011

Philadelphia mayor signs order for project labor agreements

Philadelphia Mayor Michael Nutter signed an executive order establishing project labor agreements for major public works projects in Philadelphia.

| Dec 13, 2011

Improved code requirements for attic ventilation

The Roof Assembly Ventilation Coalition (RAVC) participated in the development of the code.

| Dec 12, 2011

LEED-EB Outpaces LEED for New Construction

The U.S. Green Building Council’s (USGBC’s) LEED certifications for existing buildings standard is outpacing LEED for new buildings for the first time.

| Dec 12, 2011

Philadelphia Mayor Signs Order for Project Labor Agreements

Philadelphia Mayor Michael Nutter signed an executive order establishing project labor agreements for major public works projects in Philadelphia.

| Dec 12, 2011

Improved Code Requirements for Attic Ventilation

The International Code Council (ICC) recently published the 2012 International Residential Code (IRC) that includes improved code requirements for balanced intake and exhaust for ventilated attics.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021