Georgia court limits contractors’ ability to foreclose on liens

Georgia court limits contractors’ ability to foreclose on liens

The Georgia Court of Appeals ruled in 182 Tenth, LLC v. Manhattan Construction Company that lien claimants such as contractors, subcontractors, and materialmen, may not foreclose on a lien that includes unpaid general condition costs.


December 7, 2012

On private construction projects, contractors ordinarily have the right to file a mechanic's or materialman’s lien under applicable state law to collect unpaid sums due on a construction contract. However, on July 11, the Georgia Court of Appeals ruled in 182 Tenth, LLC v. Manhattan Construction Company that lien claimants such as contractors, subcontractors, and materialmen, may not foreclose on a lien that includes unpaid general condition costs.

These non-lienable costs may include: overhead, administrative, preconstruction, mobilization, phone/water, power, job site trailer, safety, and premiums for builder’s risk and general liability insurance.

Click here to learn more. +

Related Stories

Codes and Standards | Dec 4, 2017

Trump tax proposal would kill historic tax credits

Developers would lose up to 20% discounts on some redevelopment projects.

Codes and Standards | Nov 30, 2017

Asheville, N.C. rezoning favors pedestrians, could change city’s character

Focus is on layout and look of new buildings rather than use.

Codes and Standards | Nov 29, 2017

Many New York City landlords have not addressed new flood codes

City revised building codes after Superstorm Sandy, but many owners not required to upgrade.

Codes and Standards | Nov 28, 2017

Nail-Laminated timber Canadian design and construction guide released

Includes practical strategies and guidance with lessons from real-life projects.

Codes and Standards | Nov 27, 2017

New standard to monitor building sealing performance

Increased understanding of how materials act when stretched and compressed is the goal.

Codes and Standards | Nov 27, 2017

Denver voters approve green roof mandate

Buildings of 25,000 sf or larger required to install vegetative roof or PVs.

Codes and Standards | Nov 21, 2017

USGBC adopts ‘RELi’ resilient building and design standard

The standard prescribes methods for designing more resilient buildings and communities.

Codes and Standards | Nov 21, 2017

Updated material transparency web site and hazardous building materials list unveiled

Improved versions of tools aimed at use of healthier construction supplies.

Codes and Standards | Nov 16, 2017

White roofing isn’t always the best choice

Adverse effects include heat reflection onto nearby walls.

Codes and Standards | Nov 15, 2017

U.S. finalizes tariffs on Canadian softwood lumber

The duties would add 20% or more to cost if trade negotiators can’t find common ground.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021