FMI has released its newest survey “The 2012 U.S. Construction Industry FMI Productivity Report.”
The early effect of the recession on the nonresidential construction sector included significant productivity improvement. Downsizing has resulted in retaining the most experienced and best-trained personnel who are the most capable of working more efficiently and harder. However, this initial productivity spike has begun to wear off over time. While productivity does continue to improve, the rate of improvement is slowing.
More than half of the survey respondents did report improvement. However, for the majority it is only a slight change. Interestingly, 80 percent of respondents believe they can save at least five percent of their annual field labor cost through better management. These results are similar to a 2008 study conducted by FMI.
To that end, one of the largest areas for improvement is planning at the field manager level. Seventy percent of survey respondents experiencing improved productivity plan field resources at least five days in advance. Only 40 percent of those who said productivity has decreased plan that far ahead.
Another bright spot is the increasing use of new technologies like building information modeling and lean construction practices. Forty-two percent of respondents who have used prefabrication on projects have experienced improved productivity by 10 percent or more. Additionally, although only 35 percent of all respondents have employed integrated project delivery, 19 percent of them are reporting significant improvements in productivity.
To download a copy of the full report, click here.
Related Stories
| Feb 2, 2012
Call for Entries: 2012 Building Team Awards. Deadline March 2, 2012
Winning projects will be featured in the May issue of BD+C.
| Feb 2, 2012
VLK Architects selected for new Cypress, Texas elementary school
The Bridgeland Elementary School will be a new prototype school for the District. Designed to meet the requirements of The Collaborative for High Performance Schools.
| Feb 2, 2012
Mortenson Construction to build 2.4 MW solar project in North Carolina
Located on a 12 acre site in the Sandhills region, the 2.4 megawatt (MW) system is expected to generate approximately 3.5 million kilowatt hours (kWhs) of clean electricity on an annual basis.
| Feb 2, 2012
Shawmut Design and Construction launches sports venues division
Expansion caps year of growth for Shawmut.
| Feb 2, 2012
Fire rated glazing helps historic university preserve its past
When the University embarked on its first major addition since the opening of Hutchins Hall in 1933, preserving the Collegiate Gothic-style architecture was of utmost importance.
| Feb 2, 2012
Delk joins Gilbane Building Co.
Delk to focus on healthcare construction programs and highly complex higher education facilities for Gilbane Building Company’s Southwest region.
| Feb 2, 2012
Next phase of construction begins on Scripps Prebys Cardiovascular Institute
$456 million Institute will be comprehensive heart center for 21st Century.
| Feb 1, 2012
Increase notched in construction jobs, but unemployment rate still at 16%
AGC officials said that construction employment likely benefited from unseasonably warm weather across much of the country that extended the building season.
| Feb 1, 2012
Replacement windows eliminate weak link in the building envelope
Replacement or retrofit can help keep energy costs from going out the window.
| Feb 1, 2012
‘Augmented reality’ comes to the job site
A new software tool derived from virtual reality is helping Building Teams use the power of BIM models more effectively.