FMI has released its newest survey “The 2012 U.S. Construction Industry FMI Productivity Report.”
The early effect of the recession on the nonresidential construction sector included significant productivity improvement. Downsizing has resulted in retaining the most experienced and best-trained personnel who are the most capable of working more efficiently and harder. However, this initial productivity spike has begun to wear off over time. While productivity does continue to improve, the rate of improvement is slowing.
More than half of the survey respondents did report improvement. However, for the majority it is only a slight change. Interestingly, 80 percent of respondents believe they can save at least five percent of their annual field labor cost through better management. These results are similar to a 2008 study conducted by FMI.
To that end, one of the largest areas for improvement is planning at the field manager level. Seventy percent of survey respondents experiencing improved productivity plan field resources at least five days in advance. Only 40 percent of those who said productivity has decreased plan that far ahead.
Another bright spot is the increasing use of new technologies like building information modeling and lean construction practices. Forty-two percent of respondents who have used prefabrication on projects have experienced improved productivity by 10 percent or more. Additionally, although only 35 percent of all respondents have employed integrated project delivery, 19 percent of them are reporting significant improvements in productivity.
To download a copy of the full report, click here.
Related Stories
| Feb 28, 2012
Griffin Electric completes Medical University of South Carolina project
The 210,000-sf complex is comprised of two buildings, and houses research, teaching and office areas, plus conference spaces for the University.
| Feb 27, 2012
Consigli complete first building for Bigelow Ocean Sciences Campus
Designed by WBRC Architects Engineers in association with Perkins + Will.
| Feb 27, 2012
Hollister completes fit-out of 41,500-sf office space in Princeton, N.J.
Intricate interior project involved construction of more than 80 offices.
| Feb 27, 2012
Research Institute at Texas Children’s Hospital building receives LEED Gold
Innovative and sustainable design reflects best environmental building practices.
| Feb 26, 2012
Milwaukee U-Haul facility receives LEED-CI Silver
The new elements of the facility now include: efficient lighting with day-lighting controls and occupancy sensors, a high-efficiency HVAC system used in conjunction with a newly constructed thermal envelope to help reduce energy consumption, and the installation of low-flow fixtures to reduce water consumption.
| Feb 26, 2012
Hollister Construction awarded 42,000-sf office fit-out in Holtsville, N.Y.
Space leased by U.S. General Service Administration.
| Feb 26, 2012
Alvarez-Glasman & Colvin’s Chen LEED certified
Chen works closely with property owners to ensure that their properties meet and exceed all industry standards, and also provide long-term energy savings.
| Feb 24, 2012
ABI remains positive for three straight months
The AIA reported the January ABI score was 50.9, following a mark of 51.0 in December.
| Feb 24, 2012
Larry Lord joins HDR Architecture as south region science and technology director
A founding partner at Lord, Aeck & Sargent, Lord is nationally renowned for his leadership in architecture for complex projects.