FMI has released its newest survey “The 2012 U.S. Construction Industry FMI Productivity Report.”
The early effect of the recession on the nonresidential construction sector included significant productivity improvement. Downsizing has resulted in retaining the most experienced and best-trained personnel who are the most capable of working more efficiently and harder. However, this initial productivity spike has begun to wear off over time. While productivity does continue to improve, the rate of improvement is slowing.
More than half of the survey respondents did report improvement. However, for the majority it is only a slight change. Interestingly, 80 percent of respondents believe they can save at least five percent of their annual field labor cost through better management. These results are similar to a 2008 study conducted by FMI.
To that end, one of the largest areas for improvement is planning at the field manager level. Seventy percent of survey respondents experiencing improved productivity plan field resources at least five days in advance. Only 40 percent of those who said productivity has decreased plan that far ahead.
Another bright spot is the increasing use of new technologies like building information modeling and lean construction practices. Forty-two percent of respondents who have used prefabrication on projects have experienced improved productivity by 10 percent or more. Additionally, although only 35 percent of all respondents have employed integrated project delivery, 19 percent of them are reporting significant improvements in productivity.
To download a copy of the full report, click here.
Related Stories
| Oct 4, 2012
Electronic power tool builds project transparency
As building projects have grown in scope and complexity, so, too, has the task of document management. A new online tool is helping Building Teams meet that demand.
| Oct 4, 2012
HMC Architects in service to the community
HMC employees give back to their communities through toy drives and fundraising efforts like CANstruction, which benefits local food banks.
| Oct 4, 2012
Career development, workplace environment programs key to retention at HMC Architects
Architecture firm take a multifaceted approach to professional development.
| Oct 4, 2012
Foundation tightens HMC Architects bond with local communities
Founded in 2009 with an initial endowment of $1.9 million, HMC’s nonprofit Designing Futures Foundation (DFF) has donated about $230,000 in its three years of existence, including $105,000 in scholarships to California students. The grants help promising high schoolers with an interest in architecture, design, engineering, education, or healthcare pay for expenses like test preparation services, computers, and college entrance exam fees and tuition. The scholarships can be extended for up to five years of college.
| Oct 4, 2012
Gilbane publishes Fall 2012 construction industry economic report
Report outlines fluctuation in construction spending; predicts continued movement toward recovery.
| Oct 3, 2012
Fifth public comment period now open for update to USGBC's LEED Green Building Program
LEED v4 drafts and the public comment tool are now available on the newly re-launched, re-envisioned USGBC.org website.
| Oct 2, 2012
Mirvish and Gehry unveil conceptual design to transform Toronto’s entertainment district
Reimagining of King Street Entertainment District supports Toronto’s cultural corridor.
| Oct 2, 2012
Dow Business Services Center building named 2012 “America’s Best Buildings of the Year” winner
Building constructed with air sealing and insulation products from Dow Building Solutions.
| Oct 2, 2012
Bernards working on project at L.A. White Memorial Medical Center
The new facility is a $15-million, 41,000-sf concrete structure which includes three stories of medical office space atop a three-level parking garage.
| Oct 1, 2012
Tyco completes separation process, now largest pure-play fire protection and security business
Tyco Integrated Security focused on delivering security solutions to commercial businesses.