FMI has released its newest survey “The 2012 U.S. Construction Industry FMI Productivity Report.”
The early effect of the recession on the nonresidential construction sector included significant productivity improvement. Downsizing has resulted in retaining the most experienced and best-trained personnel who are the most capable of working more efficiently and harder. However, this initial productivity spike has begun to wear off over time. While productivity does continue to improve, the rate of improvement is slowing.
More than half of the survey respondents did report improvement. However, for the majority it is only a slight change. Interestingly, 80 percent of respondents believe they can save at least five percent of their annual field labor cost through better management. These results are similar to a 2008 study conducted by FMI.
To that end, one of the largest areas for improvement is planning at the field manager level. Seventy percent of survey respondents experiencing improved productivity plan field resources at least five days in advance. Only 40 percent of those who said productivity has decreased plan that far ahead.
Another bright spot is the increasing use of new technologies like building information modeling and lean construction practices. Forty-two percent of respondents who have used prefabrication on projects have experienced improved productivity by 10 percent or more. Additionally, although only 35 percent of all respondents have employed integrated project delivery, 19 percent of them are reporting significant improvements in productivity.
To download a copy of the full report, click here.
Related Stories
| Aug 26, 2014
6 lessons from a true IPD project: George Washington University Hospital
In its latest blog post, Skanska shares tips and takeaways from the firm's second true integrated project delivery project.
| Aug 26, 2014
Ranked: Top industrial sector AEC firms [2014 Giants 300 Report]
Stantec, Jacobs, and Turner top BD+C's rankings of the nation's largest industrial sector design and construction firms, as reported in the 2014 Giants 300 Report.
| Aug 26, 2014
High-rise concept uses 'sky street' to link towers [slideshow]
The design for a new complex in Shenzhen’s bay area consists of highly reflective glass towers, expansive garden space, and a horizontal glass structure that connects the buildings.
| Aug 25, 2014
Restoration of quake-ravaged Atascadero City Hall affirms city’s strength [2014 Reconstruction Awards]
The landmark city hall was severely damaged by the San Simeon earthquake in 2003. Reconstruction renewed the building’s stability, restored its exterior, and improved the functionality of the interior.
| Aug 25, 2014
Ranked: Top cultural facility sector AEC firms [2014 Giants 300 Report]
Arup, Gensler, and Turner head BD+C's rankings of design and construction firms with the most revenue from cultural facility projects, as reported in the 2014 Giants 300 Report.
| Aug 25, 2014
Tall wood buildings: Surveying the early innovators
Timber has been largely abandoned as a structural solution in taller buildings during the last century, in favor of concrete and steel. Perkins+Will's Rebecca Holt writes about the firm's work in surveying the burgeoning tall wood buildings sector.
| Aug 25, 2014
'Vanity space' makes up large percentage of world's tallest buildings [infographic]
Large portions of some skyscrapers are useless space used to artificially enhance their height, according to the Council on Tall Buildings and Urban Habitat.
| Aug 25, 2014
Photographer creates time-lapse video of 1 WTC using 30,000 photos
Choosing from 30,000 photos he took from the day construction began in 2006 to the day when construction was finished in 2012, Brooklyn-based photographer Benjamin Rosamund compressed 1,100 photos to create the two-minute video.
| Aug 25, 2014
Glazing plays key role in reinventing stairway design
Within the architectural community, a movement called "active design" seeks to convert barren and unappealing stairwells originally conceived as emergency contingencies into well-designed architectural focal points. SPONSORED CONTENT
| Aug 25, 2014
An easy trick for minimizing construction delays
About one out of every three construction projects is behind schedule or over budget, according to the Construction Industry Institute's Assessment of Owner Project Management Practices and Performance survey. SPONSORED CONTENT