flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

First look: K-State's Bill Snyder Family Stadium expansion

First look: K-State's Bill Snyder Family Stadium expansion

The West Side Stadium Expansion Project at Kansas State's Bill Snyder Family Stadium is the largest project in K-State Athletics history. 


By Mortenson Construction | August 29, 2013

Mortenson Construction officially completed Phase II of the Bill Snyder Stadium Master Plan on the Kansas State University campus in Manhattan, Kan., on August 21, 2013. The transformation was completed ahead of schedule, a full week before the defending Big 12 Champion Wildcats take on two-time defending FCS?National Champion North Dakota State in the first game of the season.

The largest project in K-State Athletics history will greatly improve the game-day experience for Kansas State University fans with new amenities, concessions, ADA seating, restrooms, premium seating, improved media and broadcast facilities, new field lighting – levels meet Bowl Championship Series (BCS) Games and high-definition TV broadcast requirements, a Hall of Fame, plaza improvements, and an enhanced tailgating experience.

"The Mortenson | GE Johnson team put an impressive amount of work in place in an aggressive eight-month time frame," said Derek Cunz, vice president at Mortenson Construction. "This accomplishment would not have been possible without the seamless collaboration between the design team, construction team, trade partners, University facilities and University athletics."

 

 

Other contributing factors cited by Cunz include:

  • Selection of Mortenson | GE Johnson as the single CM for the entire project, including FF&E, food service, signage, and furniture.
  • Early involvement between planning and design.
  • Focus on interim milestones.
  • Integration of Virtual Design and Construction into the daily planning.
  • Prefabrication of many exterior elements, plumbing, mechanical, and electrical.
  • Mortenson | GE Johnson self-performed the concrete and site work to manage the schedule, safety, and quality from the beginning of the project.

"We've sold a record number of season tickets," said K-State's Athletics Director, John Currie. "We'll have the most fans ever to come to the stadium this season, about 400,000, and set the all-time attendance record. We appreciate our partners Mortenson and GE Johnson and the great job they've done for our fans." Tickets for the opening game on Friday against North Dakota State are sold-out.

 

 

Project Statistics

  • 218,000 square feet of new construction
  • 12,000 cubic yards of concrete
  • 78,000 square feet of stone veneer
  • 390 peak workers on site every day during construction
  • 750,000+ craftworker hours worked
  • 1,250 tons of rebar
  • 479 days to build Kansas State's Northwest Gateway
  • 2,500 tons of structural and misc steel
  • 44 new private suites
  • 37 new loge boxes
  • 713 new club seats
  • 56 bid packages / trade partners
  • New lighting for East & West parking lots
  • Entire project funded by donors, premium seat gifts, and athletics revenue; NO State or University dollars.
  • Demolition of the existing press box December 15, 2012; first game being played August 30, 2013.
  • Zero disruptions/cancellations of events due to construction

Other team members include: AECOM / HEERY, Henderson Engineers, Olsson Associates, Bigelow Consulting, LeJeune Steel, Torgeson Electric, Central Mechanical, Bamford Fire Protection, Midwest Drywall, Gallegos Stone, Performance Masonry, Griffith Lumber, and Manko Windows.

 

Related Stories

| Jun 29, 2012

Guardian launches industry’s first glass visualizer for interior design

Online tool allows designers to explore the possibilities of glass.

| Jun 28, 2012

Federal applications of renewable energy

U.S. Army Fort Knox: Using the Earth for space heating and cooling. The U.S. Department of Energy’s (DOE) Federal Energy Management Program (FEMP) facilitates the Federal Government’s implementation of sound, cost-effective energy management and investment practices to enhance the nation’s energy security and environmental stewardship.

| Jun 27, 2012

HDR opens office in Beijing

The Beijing office is HDR’s second location in China; the firm’s other office is in Shanghai.

| Jun 27, 2012

KBE Building wins honor for Armed Forces Reserve Center

The construction phase was completed in just 16 months.

| Jun 27, 2012

SOM’s Baker receives honorary doctorate in engineering from Heriot-Watt University

Baker recognized for his career and influential contribution in the field of structural engineering.

| Jun 25, 2012

Living green wall planned for InterContinental Chicago

Project, with price tag of $2 million to $3 million, needs council approval.

| Jun 25, 2012

AIA-NJ honors DMR Architects

The academic building, completed in 2009, provides classrooms, computer labs, faculty offices, and meeting spaces for the College, which has a steady 7% annual increase in enrollment.

| Jun 25, 2012

Thornton Tomasetti appoints Hofmeister and Zhu to board of directors

The addition of Hofmeister and Zhu brings the number of directors to 10.

| Jun 20, 2012

WHR’s Tradewell Fellowship Marks 15th Anniversary

Fellowship program marks milestone with announcement of new program curator and 2012 fellow

| Jun 15, 2012

Beck Group/Atlanta wins AGC Build Georgia Award

Site-specific safety plan, BIM analysis and third-party structural review contributed to successful implementation.

boombox1
boombox2
native1

More In Category

Construction Costs

Data center construction costs for 2024

Gordian’s data features more than 100 building models, including computer data centers. These localized models allow architects, engineers, and other preconstruction professionals to quickly and accurately create conceptual estimates for future builds. This table shows a five-year view of costs per square foot for one-story computer data centers. 


Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.



Healthcare Facilities

Watch on-demand: Key Trends in the Healthcare Facilities Market for 2024-2025

Join the Building Design+Construction editorial team for this on-demand webinar on key trends, innovations, and opportunities in the $65 billion U.S. healthcare buildings market. A panel of healthcare design and construction experts present their latest projects, trends, innovations, opportunities, and data/research on key healthcare facilities sub-sectors. A 2024-2025 U.S. healthcare facilities market outlook is also presented.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021