Amazon has made installing solar panels on rooftops a key part of its ESG strategy, but a series of events last year show how challenging greening up major facilities can be.
Between April 2020 and June 2021, solar panels on Amazon fulfillment center roofs caught fire or experienced electrical explosions at least six times. As a result, the company took all U.S. solar rooftops offline last year while it investigated the mishaps.
According to a CNBC report, Amazon hired a consultant to audit its rooftop solar systems in the U.S., Asia-Pacific, Europe, Middle East, and Africa. The study discovered several problems at various sites including mismatched module-to-module connectors, improper installation of connectors, poor wire management, and evidence of water intrusion in the inverters, CNBC reported.
Each fire reportedly cost the company an average of $2.7 million, which included third-party audits of rooftop solar systems, checks on how much electricity they were generating, and repairs for broken or faulty parts.
Despite the setbacks, Amazon remains committed to solar power and continues to monitor the situation, making repairs where needed. As of this April, Amazon had onsite solar at 176 facilities. Its solar program began in 2017.
Related Stories
| Apr 16, 2012
Drake joins EYP as science and technology project executive
Drake’s more than 30 years of diversified design and project delivery experience spans a broad range of complex building types.
| Apr 16, 2012
$80 million in export financing for solar project in India
The project, “Rajasthan Sun Technique Energy Private Limited,” is a subsidiary of Reliance Power and is being co-financed by the Asian Development Bank and FMO, the Dutch development bank.
| Apr 13, 2012
Arcadis merges with Davis Langon & Seah
Merger will help company expand business in Asia.
| Apr 13, 2012
Goettsch Partners designs new music building for Northwestern
The showcase facility is the recital hall, an intimate, two-level space with undulating walls of wood that provide optimal acoustics and lead to the stage, as well as a 50-foot-high wall of cable-supported, double-skin glass
| Apr 13, 2012
Best Commercial Modular Buildings Recognized
Judges scored building entries on a number of criteria including architectural excellence, technical innovation, cost effectiveness, energy efficiency, and calendar days to complete, while marketing pieces were judged on strategy, implementation, and quantifiable results. Read More
| Apr 12, 2012
Solar PV carport, electrical charging stations unveiled in California
Project contractor Oltman Construction noted that the carport provides shaded area for 940 car stalls and generates 2 MW DC of electric power.
| Apr 11, 2012
Shawmut appoints Tripp as business development director
Tripp joined Shawmut in 1998 and previously held the positions of assistant superintendent, superintendent, and national construction manager.
| Apr 11, 2012
Corgan & SOM awarded contract to design SSA National Support Center
The new SSA campus is expected to meet all Federal energy and water conservation goals while achieving LEED Gold Certification from the United States Green Building Council.
| Apr 11, 2012
C.W. Driver completes Rec Center on CSUN campus
The state-of-the-art fitness center supports university’s goal to encourage student recruitment and retention.