Fires on Amazon warehouse roofs seemingly caused by faulty PV installations

Fires on Amazon warehouse roofs seemingly caused by faulty PV installations

Problems prompted company to temporarily take all solar offline.


By Peter Fabris, Contributing Editor | September 14, 2022
Solar Panel Roof
Courtesy Pexels.

Amazon has made installing solar panels on rooftops a key part of its ESG strategy, but a series of events last year show how challenging greening up major facilities can be.

Between April 2020 and June 2021, solar panels on Amazon fulfillment center roofs caught fire or experienced electrical explosions at least six times. As a result, the company took all U.S. solar rooftops offline last year while it investigated the mishaps.

According to a CNBC report, Amazon hired a consultant to audit its rooftop solar systems in the U.S., Asia-Pacific, Europe, Middle East, and Africa. The study discovered several problems at various sites including mismatched module-to-module connectors, improper installation of connectors, poor wire management, and evidence of water intrusion in the inverters, CNBC reported.

Each fire reportedly cost the company an average of $2.7 million, which included third-party audits of rooftop solar systems, checks on how much electricity they were generating, and repairs for broken or faulty parts.

Despite the setbacks, Amazon remains committed to solar power and continues to monitor the situation, making repairs where needed. As of this April, Amazon had onsite solar at 176 facilities. Its solar program began in 2017.

Related Stories

| Feb 6, 2013

Arcadia (Calif.) High School opens $20 million performing arts center

A 60-year old wish for the community of Arcadia has finally come true with the opening of Arcadia Unified School District’s new $20 million Performing Arts Center.

| Jan 31, 2013

The Opus Group completes construction of corporate HQ for Church & Dwight Co.

The Opus Group announced today the completion of construction on a new 250,000-square-foot corporate headquarter campus for Church & Dwight Co., Inc., in Ewing Township, near Princeton, N.J.

| Jan 31, 2013

Map of U.S. illustrates planning times for commercial construction

Stephen Oliner, a UCLA professor doing research for the Federal Reserve Board, has made the first-ever estimate of planning times for commercial construction across the United States.

| Jan 29, 2013

Tutor Perini Corp. to Implement Textura Prequalification Management Companywide

Rollout across the Tutor Perini organization will enhance the subcontractor prequalification experience and enable a standardized process in support of the contractor default insurance program.

| Jan 22, 2013

Midwestern Construction Company Acquires Local Architecture Firm

St. Charles, Ill.-based design/build and construction firm acquires architecture firm.

| Jan 16, 2013

2013 40 Under 40 application process now open

Building Design+Construction's 40 Under 40 is open to AEC professionals from around the globe.

boombox1
boombox2
native1

More In Category

Geothermal Technology

Rochester, Minn., plans extensive geothermal network

The city of Rochester, Minn., home of the famed Mayo Clinic, is going big on geothermal networks. The city is constructing Thermal Energy Networks (TENs) that consist of ambient pipe loops connecting multiple buildings and delivering thermal heating and cooling energy via water-source heat pumps.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021