Fires on Amazon warehouse roofs seemingly caused by faulty PV installations

Fires on Amazon warehouse roofs seemingly caused by faulty PV installations

Problems prompted company to temporarily take all solar offline.


By Peter Fabris, Contributing Editor | September 14, 2022
Solar Panel Roof
Courtesy Pexels.

Amazon has made installing solar panels on rooftops a key part of its ESG strategy, but a series of events last year show how challenging greening up major facilities can be.

Between April 2020 and June 2021, solar panels on Amazon fulfillment center roofs caught fire or experienced electrical explosions at least six times. As a result, the company took all U.S. solar rooftops offline last year while it investigated the mishaps.

According to a CNBC report, Amazon hired a consultant to audit its rooftop solar systems in the U.S., Asia-Pacific, Europe, Middle East, and Africa. The study discovered several problems at various sites including mismatched module-to-module connectors, improper installation of connectors, poor wire management, and evidence of water intrusion in the inverters, CNBC reported.

Each fire reportedly cost the company an average of $2.7 million, which included third-party audits of rooftop solar systems, checks on how much electricity they were generating, and repairs for broken or faulty parts.

Despite the setbacks, Amazon remains committed to solar power and continues to monitor the situation, making repairs where needed. As of this April, Amazon had onsite solar at 176 facilities. Its solar program began in 2017.

Related Stories

| Feb 27, 2014

Metal Construction Association introduces two Environmental Product Declarations

Two Environmental Product Declarations (EPD), one for Metal Composite Material Panels and one for  Roll Formed Steel Panels for Roofs and Walls, are now available free of charge from the Metal Construction Association (MCA) on its website.

| Feb 27, 2014

Bluebeam Software launches Revu 12 for better field-ready document management and project collaboration

The latest version of the company’s flagship solution better enables users in document-intensive industries to digitally collaborate on project documents and more easily connect the office to the field.

| Feb 27, 2014

PocketCake lunches CPU designed for virtual reality simulations

The company's Virtual Reality Simulation Converter Assembly is three times more powerful than the average high-performance computer and allows for up to eight people to experience a virtual reality simulation at the same time.

| Feb 26, 2014

Adaptive reuse project brings school into historic paper mill

The project features nontraditional classrooms for collaborative learning, an arts and music wing, and a technologically sophisticated global resource center.

| Feb 26, 2014

Startup PocketCake aims to bring virtual reality simulations to the AEC masses

Founded in 2012, the development firm offers custom virtual reality simulations for the price of a typical architectural illustration.

| Feb 26, 2014

Billie Jean King National Tennis Center serving up three-phase expansion

The project includes the construction of two new stadiums and a retractable roof over the existing Arthur Ashe Stadium. 

| Feb 24, 2014

First look: UC San Diego opens net-zero biological research lab

The facility is intended to be "the most sustainable laboratory in the world," and incorporates natural ventilation, passive cooling, high-efficiency plumbing, and sustainably harvested wood.  

| Feb 21, 2014

Naturally ventilated hospital planned in Singapore

The Ng Teng Fong General Hospital will take advantage of the region's prevailing breezes to cool the spaces. 

| Feb 21, 2014

Calatrava ordered to pay millions for 'shortcomings in his work' on conference center project

Famed architect Santiago Calatrava must pay 2.9 million euros due to faulty design work on the Palacio de Congresos project in Oviedo, Spain. 

| Feb 19, 2014

Why you should start with a builder, part two

When it’s time to build or expand, the first step is finding a builder that fits your needs. Once you have found a builder, checked their references, visited with their previous clients and are ready to move forward, the next step is answering an initial set of questions that will direct your project.

boombox1
boombox2
native1

More In Category

Adaptive Reuse

Empty mall to be converted to UCLA Research Park

UCLA recently acquired a former mall that it will convert into the UCLA Research Park that will house the California Institute for Immunology and Immunotherapy at UCLA and the UCLA Center for Quantum Science and Engineering, as well as programs across other disciplines. The 700,000-sf property, formerly the Westside Pavilion shopping mall, is two miles from the university’s main Westwood campus. Google, which previously leased part of the property, helped enable and support UCLA’s acquisition.



Geothermal Technology

Rochester, Minn., plans extensive geothermal network

The city of Rochester, Minn., home of the famed Mayo Clinic, is going big on geothermal networks. The city is constructing Thermal Energy Networks (TENs) that consist of ambient pipe loops connecting multiple buildings and delivering thermal heating and cooling energy via water-source heat pumps.


halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021