Facebook’s prefab data center concept aims to slash construction time in half

Facebook’s prefab data center concept aims to slash construction time in half

The tech giant's newly developed Rapid Deployment Data Center concept utilizes modular and Lean design principles to streamline planning and construction.


By David Barista, Editor-in-Chief | August 4, 2014
In May, Facebook broke ground on an expansion to its data center campus in Lule
In May, Facebook broke ground on an expansion to its data center campus in Lule, Sweden. Using a new prefab construction proces

Less than a year after opening its ultra-green, hydropowered data center facility in Luleå, Sweden, Facebook is back at it in Mother Svea with yet another novel approach to data center design. In May, the tech giant broke ground on an expansion to its Luleå facility, which is rated as one of the most energy-efficient data centers in the world, with an average power usage effectiveness (PUE) of 1.05. 

With Luleå 2, the company expects to achieve the same energy performance, but with a construction and deployment schedule that is roughly half its typical data center project. To do so, the Building Team is implementing Facebook’s newly developed Rapid Deployment Data Center (RDDC) concept, which utilizes modular and Lean design principles to streamline planning and construction, reduce the amount of materials, and create facilities that are more site-agnostic, according to Marco Magarelli, AIA, Architect, Datacenter R&D with Facebook. 

“By deploying pre-manufactured assemblies, a majority of the components can be used interchangeably,” wrote Magarelli in a recent blog post on the RDDC concept. “It’s our hope that by standardizing the designs of our component assemblies, much like we do with OCP servers, we can deploy a unitized data center into almost any region in the world faster, leaner, and more cost effectively.”

Developed through the Facebook-initiated Open Compute Project, which aims to crowdsource data center design, the RDDC approach relies on two core prefab concepts:

Chassis assembly method. Pre-assembled steel frames 12 feet wide and 40 feet long serve as the “chassis,” on which the vital data center components—cable trays, power busways, containment panels, lighting, etc.—are bolted in a factory, much like an auto assembly line. The chassis are shipped to the site and mounted atop steel columns. The chassis are attached end to end to create the typical 60-foot-long cold aisle, with 10 feet of aisle space at each end. This series of connected chassis forms a “canopy,” under which the server racks reside.  

“Unlike containerized solutions, which are a full volumetric approach that includes a floor, this idea focuses solely on the framework that exists above the racks, to avoid shipping the empty space that will eventually be occupied by the racks,” said Magarelli.

Flat-pack assemblies. This Ikea-like approach neatly packs the walls and ceiling panels into standard, 8-foot modules that are easily transportable to a site on a flatbed trailer without requiring special permits for wide loads. Standard building products like metal studs and preassembled, unitized containment panels are then erected on the site and are fully self-supporting. 

The ceiling panels use Epicore metal deck product, which spans the 12-foot width of the cold aisle and racks. This serves the additional duty of carrying the loads of the trays, power bus, and light fixtures below it using a proprietary hanger clip for the threaded rods, according to Magarelli.

“Careful attention was paid to minimizing the number of unique components,” he wrote. “For example, 364 identical wall panels are used in each data hall.”

For more on Facebook’s Rapid Deployment Data Center method, visit: www.opencompute.org/blog/faster-leaner-smarter-better-data-centers.

Related Stories

| Mar 14, 2012

Hyatt joins Thornton Tomasetti as VP in Chicago

A forensic specialist, Hyatt has more than 10 years of experience performing investigations of structural failures throughout the U.S.

| Mar 14, 2012

Tsoi/Kobus and Centerbrook to design Jackson Laboratory facility in Farmington, Conn.

Building will house research into personalized, gene-based cancer screening and treatment.

| Mar 13, 2012

China's high-speed building boom

A 30-story hotel in Changsha went up in two weeks. Some question the safety in that, but the builder defends its methods.

| Mar 13, 2012

Commercial glazer Harmon expanding into Texas

Company expanding into the Texas market with a new office in Dallas and a satellite facility in Austin.

| Mar 13, 2012

Worker office space to drop below 100-sf in five years

The average for all companies for square feet per worker in 2017 will be 151 sf, compared to 176 sf, and 225 sf in 2010.

| Mar 12, 2012

Improving the performance of existing commercial buildings: the chemistry of sustainable construction

Retrofitting our existing commercial buildings is one of the key steps to overcoming the economic and environmental challenges we face.

| Mar 9, 2012

2012 Giants 300 survey due Friday, April 13

See how your firm ranks among the AEC industry leaders. 

| Mar 7, 2012

Firestone iPad app offers touch technology

Free app provides a preview of Firestone’s Roots to Rooftop Building Envelope Solution with an overview of all the products from ground and stormwater management solutions, to complete wall panel and commercial roofing system applications.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021