Experts pessimistic on Chicago’s $650 million McCormick Place expansion

Events Facilities

Experts pessimistic on Chicago’s $650 million McCormick Place expansion

Developers and city officials envision $250 million of annual growth, but the figure assumes that a new arena will lure conventions and draw full houses for basketball games.


By Mike Chamernik, Associate Editor | March 7, 2016
Experts pessimistic on Chicago’s $650 million McCormick Place expansion

The new DePaul Arena at McCormick Place Event Center. Courtesy Pelli Clarke Pelli Architects

After a decade and a half of downturn, Chicago envisions a new boom period for its South Loop convention center district. The Metropolitan Pier and Exposition Authority, known as McPier, is revamping McCormick Place, adding a hotel and arena through a $650 million McCormick Place Event Center expansion project.

Gensler designed the hotel, the 1,200-room, $450 million Marriott Marquis. The arena, designed by Pelli Clarke Pelli, is a basketball venue for DePaul, the city’s Division-I college hoops team. McPier funded a study that says the new buildings could generate $250 million in spending per year.

That figure, though, is fairly optimistic. The Chicago Tribune reports that experts are doubting the project, saying that the investments will ultimately cost taxpayers.

The McPier study has a few faulty assumptions. One, it is based on DePaul averaging nearly 10,000 fans a game, almost triple its current attendance. Two, McPier plans on using the arena for conventions, but studies have said that arenas are poor hosts for conventions due to their fixed seating. If the arena struggles to make money either in terms of basketball or conventions, then the hotel will have to make up that difference. 

Stadiums have been found to be unsuccessful drivers of economic growth, which is an issue because McPier has already borrowed hundreds of millions of dollars and maxed out its debt limit. 

"It was a dumb idea when it was proposed, it was a dumb idea when they approved it, and it will be a dumb idea in the future," Marc Ganis, a Chicago consultant who specializes in sports, said in the Tribune piece.

The Tribune has much more detail on the project, which is set to open in 2017.

Several issues have arisen with concerning the development over the last few years, including eminent domain battles, rising construction costs, and disagreements over $55 million in tax increment financing (TIF) funds.

Related Stories

| Feb 6, 2012

FMI releases 2012 Construction Productivity Report

Downsizing has resulted in retaining the most experienced and best-trained personnel who are the most capable of working more efficiently and harder.

| Feb 2, 2012

Shawmut Design and Construction launches sports venues division

Expansion caps year of growth for Shawmut.

| Jan 24, 2012

U of M installs new lighting at Crisler Player Development Center

Energy efficient lighting installed at PDC reduce costs and improves player performance.

| Jan 3, 2012

The Value of Historic Paint Investigations

An expert conservator provides a three-step approach to determining a historic building’s “period of significance”—and how to restore its painted surfaces to the correct patterns and colors. 

| Dec 27, 2011

Nova completes $60M Clearwater Conference Center

Comprising an entire city block, the 450,000 sq. ft. facility features over 400 meeting rooms, six theaters, a full-service health spa, complete with an indoor running track, and a commercial kitchen that can efficiently accommodate over 1,000 diners

| Dec 27, 2011

BD+C's Under 40 Leadership Summit update

The two-day Under 40 Leadership Summit continued with a Leadership Style interactive presentation; Great Solutions presentations from Under 40 attendees; the Owner’s Perspective panel discussion; and the Blue Ocean Strategy presentation.

| Dec 14, 2011

Tyler Junior College and Sika Sarnafil team up to save energy

Tyler Junior College wanted a roofing system that wouldn’t need any attention for a long time.

| Dec 5, 2011

Summit Design+Build begins renovation of Chicago’s Esquire Theatre

The 33,000 square foot building will undergo an extensive structural remodel and core & shell build-out changing the building’s use from a movie theater to a high-end retail center.

| Nov 9, 2011

Lincoln Center Pavilion wins national architecture and engineering award

The project team members include owner Lincoln Center for the Performing Arts, New York; design architect and interior designer of the restaurant, Diller Scofidio + Renfro, New York; executive architect, FXFOWLE, New York; and architect and interior designer of the film center, Rockwell Group, New York; structural engineer Arup (AISC Member), New York; and general contractor Turner Construction Company (AISC Member), New York. 

| Nov 9, 2011

Sika Sarnafil Roof Recycling Program recognized by Society of Plastics Engineers

Program leads the industry in recovering and recycling roofing membrane into new roofing products.

boombox1
boombox2
native1

More In Category




Adaptive Reuse

Detroit’s Michigan Central Station, centerpiece of innovation hub, opens

The recently opened Michigan Central Station in Detroit is the centerpiece of a 30-acre technology and cultural hub that will include development of urban transportation solutions. The six-year adaptive reuse project of the 640,000 sf historic station, created by the same architect as New York’s Grand Central Station, is the latest sign of a reinvigorating Detroit.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021