Experts pessimistic on Chicago’s $650 million McCormick Place expansion

Events Facilities

Experts pessimistic on Chicago’s $650 million McCormick Place expansion

Developers and city officials envision $250 million of annual growth, but the figure assumes that a new arena will lure conventions and draw full houses for basketball games.


By Mike Chamernik, Associate Editor | March 7, 2016
Experts pessimistic on Chicago’s $650 million McCormick Place expansion

The new DePaul Arena at McCormick Place Event Center. Courtesy Pelli Clarke Pelli Architects

After a decade and a half of downturn, Chicago envisions a new boom period for its South Loop convention center district. The Metropolitan Pier and Exposition Authority, known as McPier, is revamping McCormick Place, adding a hotel and arena through a $650 million McCormick Place Event Center expansion project.

Gensler designed the hotel, the 1,200-room, $450 million Marriott Marquis. The arena, designed by Pelli Clarke Pelli, is a basketball venue for DePaul, the city’s Division-I college hoops team. McPier funded a study that says the new buildings could generate $250 million in spending per year.

That figure, though, is fairly optimistic. The Chicago Tribune reports that experts are doubting the project, saying that the investments will ultimately cost taxpayers.

The McPier study has a few faulty assumptions. One, it is based on DePaul averaging nearly 10,000 fans a game, almost triple its current attendance. Two, McPier plans on using the arena for conventions, but studies have said that arenas are poor hosts for conventions due to their fixed seating. If the arena struggles to make money either in terms of basketball or conventions, then the hotel will have to make up that difference. 

Stadiums have been found to be unsuccessful drivers of economic growth, which is an issue because McPier has already borrowed hundreds of millions of dollars and maxed out its debt limit. 

"It was a dumb idea when it was proposed, it was a dumb idea when they approved it, and it will be a dumb idea in the future," Marc Ganis, a Chicago consultant who specializes in sports, said in the Tribune piece.

The Tribune has much more detail on the project, which is set to open in 2017.

Several issues have arisen with concerning the development over the last few years, including eminent domain battles, rising construction costs, and disagreements over $55 million in tax increment financing (TIF) funds.

Related Stories

| Nov 15, 2013

First look: Jacob K. Javits Convention Center renovation and expansion [slideshow]

The massive upgrade included a 110,000-sf expansion – Javits North – as well as the installation of 240,000 sf of energy-efficient glass curtain wall on the existing facility and the region's largest green roof. 

| Nov 15, 2013

Metal makes its mark on interior spaces

Beyond its long-standing role as a preferred material for a building’s structure and roof, metal is making its mark on interior spaces as well. 

| Nov 13, 2013

Installed capacity of geothermal heat pumps to grow by 150% by 2020, says study

The worldwide installed capacity of GHP systems will reach 127.4 gigawatts-thermal over the next seven years, growth of nearly 150%, according to a recent report from Navigant Research.

| Nov 13, 2013

First look: Renzo Piano's addition to Louis Kahn's Kimbell Art Museum [slideshow]

The $135 million, 101,130-sf colonnaded pavilion by the famed architect opens later this month. 

| Oct 30, 2013

11 hot BIM/VDC topics for 2013

If you like to geek out on building information modeling and virtual design and construction, you should enjoy this overview of the top BIM/VDC topics.

| Oct 23, 2013

Gehry, Foster join Battersea Power Station redevelopment

Norman Foster and Frank Gehry have been selected to design a retail section within the £8 billion redevelopment of Battersea Power Station in London.

| Oct 18, 2013

Researchers discover tension-fusing properties of metal

When a group of MIT researchers recently discovered that stress can cause metal alloy to fuse rather than break apart, they assumed it must be a mistake. It wasn't. The surprising finding could lead to self-healing materials that repair early damage before it has a chance to spread. 

| Oct 1, 2013

13 structural steel buildings that dazzle

The Barclays Center arena in Brooklyn and the NASCAR Hall of Fame in Charlotte, N.C., are among projects named 2013 IDEAS2 winners by the American Institute of Steel Construction.

| Sep 26, 2013

6 ways to maximize home-field advantage in sports venue design

Home-field advantage can play a significant role in game outcomes. Here are ways AEC firms can help create the conditions that draw big crowds, energize the home team to perform better, and disrupt visiting players.

| Sep 24, 2013

8 grand green roofs (and walls)

A dramatic interior green wall at Drexel University and a massive, 4.4-acre vegetated roof at the Kauffman Performing Arts Center in Kansas City are among the projects honored in the 2013 Green Roof and Wall Awards of Excellence. 

boombox1
boombox2
native1

More In Category




Adaptive Reuse

Detroit’s Michigan Central Station, centerpiece of innovation hub, opens

The recently opened Michigan Central Station in Detroit is the centerpiece of a 30-acre technology and cultural hub that will include development of urban transportation solutions. The six-year adaptive reuse project of the 640,000 sf historic station, created by the same architect as New York’s Grand Central Station, is the latest sign of a reinvigorating Detroit.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021