An expanded and renovated complex brings together U. of Colorado’s sports programs

Sports and Recreational Facilities

An expanded and renovated complex brings together U. of Colorado’s sports programs

This two-year project enhances the experiences of athletes and fans alike.


By John Caulfield, Senior Editor | April 17, 2016

An aerial view of Folsom Field at the University of Colorado at Boulder, which has recently completed an extensive expansion and renovation of its sports complex that included the addition of a new Sports and Medicine Performance Center, built in partnership with Boulder Community Health and open to the public. Image: Courtesy of Mortenson Construction

A major expansion and renovation of the University of Colorado at Boulder’s football stadium, which had experienced cost overruns over the past two years, was recently completed. The $177 million project—which was financed with bond debt that the school’s athletic department will repay in full through fundraising, business contracts, and community partnerships—centralizes the university’s athletic programs, and is being touted as “transformational” by Mortenson Construction, for which this is its largest design-build sports project to date.

Among the project’s key elements are a 212,000-sf expansion of Folsom Field; a 38,000-sf renovation of Dal Ward Athletic Center, which now includes men’s and women’s Olympic sports locker rooms and an 11,285-sf weight room; the construction of a 108,000-sf, 90-foot high, net-zero-energy indoor practice facility that will serve all of the university’s sports programs and includes a six-lane 300-meter Olympic track; a 534-stall parking garage that Mortenson delivered under a separate contract; and the addition of Franklin Field, a 106,000-sf outdoor grass practice field next to the indoor facility.

 

This project included the construction of a 108,000-sf net zero energy indoor practice facility that includes a six-lane 300-meter Olympic track that allows the university fo host sanctioned tack and field events on campus. The facility is 90 feet high, enough clearance for the football team's kickers to practice. Image: Courtesy of Mortenson. 

 

The upgraded complex now includes Champions Center, the new home of CU’s football and Athletic Administration. The Center offers a state-of-the-art locker room and lounge, with dining facilities and rooftop terrace for game-day and special events.

A new Sports Medicine and Performance Center, built in partnership with Boulder Community Health, is now open to the public.

The upgrade added 2,604 solar panels that will generate 1,200 MWh/year of energy. And 1,876 stadium seats were replaced.

During the construction, Mortenson created an interactive model of the project that the community and other stakeholders could navigate using a game controller. The exhibit was displayed on a mobile TV in campus buildings near the stadium, and has served as a communication and fundraising tool.

The Building Team included Populous (architect), M-E Engineers (MEP), Martin/Martin (SE), J3 Engineering (CE), Wenk Associates (landscape architect), Ludvik Electrical (electrical trade partner), Mortenson Construction (GC), Murphy (mechanical trade partner).

A total of 3,161 workers were employed on this project, with the onsite workforce peaking at 600 for one day.  The Building Team had 550-plus days without a recordable injury on the Indoor Practice Field. 

Related Stories

Hotel Facilities | Apr 13, 2015

Figure-eight shaped hotel to open around PyeongChang 2018 Winter Olympics Facility

Just three miles away from the Olympic stadiums, the hotel will be a hub of its own.

Sports and Recreational Facilities | Apr 13, 2015

USTA breaks ground on what will be the country’s largest tennis complex

The 63-acre facility is being positioned as a cornerstone for a sports innovation and performance district in Lake Nona, Fla., a 7,000-acre master planned community that continues to expand.

Building Team Awards | Apr 10, 2015

14 projects that push AEC teaming to the limits

From Lean construction to tri-party IPD to advanced BIM/VDC coordination, these 14 Building Teams demonstrate the power of collaboration in delivering award-winning buildings. These are the 2015 Building Team Award winners.

Building Team Awards | Apr 9, 2015

Multifaced fitness center becomes campus landmark

A sloped running track and open-concept design put this Building Team to the test. 

Sports and Recreational Facilities | Apr 9, 2015

Design for new Milwaukee Bucks arena is ‘modest and modernist’

Designed by local firm Eppstein Uhen Architects and global firm Populous, the sports venue will prominently feature a swoop, which some journalists and critics have likened to an inverted Nike swoosh.

Structural Materials | Mar 30, 2015

12 projects earn structural steel industry's top building award

Calatrava's soaring Innovation Science and Technology Building at Florida Polytechnic University is among the 12 projects honored by the American Institute of Steel Construction in the 2015 IDEAS² awards competition. 

Sports and Recreational Facilities | Mar 24, 2015

Another plan for renovating Houston’s Astrodome blends public space and history

A ULI panel of experts recommends a $242 million renovation that converts the massive building into a park that ties into surrounding facilities.

Sponsored | Cladding and Facade Systems | Mar 24, 2015

Designers turn a struggling mall into a hub of learning and recreation

Architects help Nashville government transform a struggling mall into a new community space.

Sports and Recreational Facilities | Mar 19, 2015

Populous design wins competition for UK's most sustainable arena

The live-concert venue will seat an audience of 12,000, which the firm says will be masked by “the atmosphere and intimacy of a 4,000-seat amphitheatre.” 

Sports and Recreational Facilities | Mar 11, 2015

Foster + Partners wins bid for 2022 World Cup centerpiece stadium in Qatar

Norman Foster described the design as “an exciting step forward in stadium design—it will be the first to break the mold of the free-standing suburban concept, and instead anticipates the grid of this future city.” 

boombox1
boombox2
native1

More In Category




Mixed-Use

A surging master-planned community in Utah gets its own entertainment district

Since its construction began two decades ago, Daybreak, the 4,100-acre master-planned community in South Jordan, Utah, has been a catalyst and model for regional growth. The latest addition is a 200-acre mixed-use entertainment district that will serve as a walkable and bikeable neighborhood within the community, anchored by a minor-league baseball park and a cinema/entertainment complex.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021