EPA proposes new stormwater discharge regulations for construction sites

Codes and Standards

EPA proposes new stormwater discharge regulations for construction sites

Would apply to sites of one or more acres.


By Peter Fabris, Contributing Editor | May 16, 2016
EPA proposes new stormwater discharge regulations for construction sites

Photo: Dawn Easterday/Creative Commons.

The Environmental Protection Agency’s has proposed new National Pollution Discharge Elimination System (NPDES) general permit requirements regulating stormwater discharges from construction activities

The proposal applies to construction sites of one or more acres, or less than one acre, but part of a larger development. The proposal would:

  • Prohibit hazardous substances, such as paint or caulk containing polychlorinated biphenyls (PCBs) from authorized non-stormwater discharges of external building washdown waters.
  • Require permittees to include the EPA’s contact information in public notices that are already required to be posted in a prominent location near construction sites.
  • Require permittees to cover or use another method of temporary stabilization for inactive soil stockpiles and land clearing debris piles where the piles will be unused for 14 or more days.
  • Require permittees to keep waste container lids closed (or provide some other secure cover where containers do not have lids).
  • For demolition of structures with at least 10,000 sf of floor space built or renovated before 1980, require permittees to implement controls to minimize the exposure of PCB-containing building materials to precipitation and stormwater.
  • Require permittees to state on their Notice of Intent (NOI) form the type of construction activities that will be involved.

These potential permit changes could significantly increase the time, effort, and resources required to comply with stormwater management obligations, according to an article by the law firm Dykema, Gossett PLLC.

Related Stories

Codes and Standards | Jun 18, 2015

New document addresses school safety and security

In an effort to balance security and fire safety features within codes, standards and planning, NFPA hosted a two-day workshop, “School Safety, Codes and Security”, last December. The findings are now available in an NFPA report.

Codes and Standards | Jun 18, 2015

Two myths regarding NFPA 101 Life Safety Code debunked

NFPA life safety engineer Ron Coté settles the debate over second egress doors and exit signs.

Codes and Standards | Jun 18, 2015

How to prevent corrosion in sprinkler system piping

The technical committees responsible for NFPA 13, Installation of Sprinkler Systems, have been looking at ways to eliminate or reduce corrosion in sprinkler systems for several revision cycles.

Codes and Standards | Jun 11, 2015

Steel Framing Alliance updates ‘Thermal Design and Code Compliance for Cold-Formed Steel Walls’ design guide

Includes results of new tests and addresses IECC and ASHRAE compliance paths.

Codes and Standards | Jun 11, 2015

Helena, Mont., may charge commercial developers a fee to fund public art

The fee would apply to new construction or alteration of nonresidential buildings of at least 20,000 sf.

Codes and Standards | Jun 11, 2015

DBIA releases new document on choosing a project delivery method

Provides owners and others with factors to consider when choosing the best method of delivery for their project.

High-rise Construction | Jun 5, 2015

Japanese policymakers discuss mandate for toilets in elevators

This quirky-sounding building code is a safety measure for the earthquake-prone nation.

Codes and Standards | Jun 4, 2015

OSHA publishes guide to restroom access for transgender workers

The guide advises employers to allow employees to use restrooms that correspond to their gender identity.

Codes and Standards | Jun 4, 2015

Guide helps Building Teams maximize team integration

The guide includes forms to support a two- to four-hour workshop to help an owner select the most appropriate delivery strategy. 

Codes and Standards | Jun 4, 2015

NIBS, RICS to explore P3 as tool to achieve high-performance buildings

The idea of applying the P3 concept more to buildings, and especially building performance, is a potentially promising new avenue in the U.S., according to the trade groups.

boombox1
boombox2
native1

More In Category

Sustainability

Grimshaw launches free online tool to help accelerate decarbonization of buildings

Minoro, an online platform to help accelerate the decarbonization of buildings, was recently launched by architecture firm Grimshaw, in collaboration with more than 20 supporting organizations including World Business Council for Sustainable Development (WBCSD), RIBA, Architecture 2030, the World Green Building Council (WorldGBC) and several national Green Building Councils from across the globe.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021