In the rapidly changing world of virtual design and construction, the mechanical-electrical-plumbing component of building information modeling has earned a reputation as something of a technology laggard. BIM for structural work? Beautiful. For architectural design? Lovely. For general construction? Terrifâ. But BIM for MEP? Not so hot.
That negative perception is changing, as MEP engineers find new ways to put BIM to more effective use in their workâwhich, in the case of a complex project like a hospital, can account for 30-40% of total construction costs.
Southland Industries, Garden Grove, Calif., is one such innovator. The design-build mechanical contractor is applying electronic surveying technology to BIM and 3D models to enhance the accuracy and reliability of prefabricated HVAC and plumbing systems. In so doing, it is saving time and money on complex hospital projects while improving quality.
Forging a unified Building Team
Three years ago, a major client commissioned Southland and its partners to design-build a complex of three facilities totaling more than a half-million square feetâa multi-story patient tower with a diagnostic/treatment center, a health services building, and a central utility plant.
The Building Teamâwhich in addition to Southland included HMC Architects (architect), Ted Jacob Engineering Group (M/E OR and electrical COR), Sasco Electric (design-assist electrical contractor), Berger Bros. (exterior framing), Sharpe Interior Systems (interior framing), and McCarthy Building Cos. (GC)âhad worked together successfully on a previous job for this healthcare provider. The client wanted to keep the same team and bring them together early in the design process, a practice that had not been followed in the earlier project.
Southlandâs role was to provide design-assist mechanical/plumbing services. According to Patrick Reed, Contract Executive in the firmâs healthcare division, the company grasped the opportunity to make better use of the available BIM/3D documents to improve its prefabrication of mechanical and plumbing systems.
Southland had been prefabbing piping and sheet metal in its 80,000-sf shop in Garden Grove, Calif., for decades. For the new project, Reed and his team planned to apply electronic surveying technology normally used for exterior applicationsâin this case, Trimble Total Station RTS-555, with AutoCAD CADMEP+ solution softwareâto the BIM models of the interior HVAC and plumbing systems.
âOur Northern California office had used a system like this in previous projects,â says Reed. For the new project, the goal was to take the data from the BIM model and prefab the mechanical and plumbing systems in whole assembliesâfor 100% of the job.
âYou can run into problems because the documents donât match whatâs out in the field,â says Reed. The surveying system would, it was hoped, provide the accuracy needed to make sure all the prefabbed pieces fit together perfectly at the site.
Dialing down the tolerances
Linking the interior survey to the BIM model proved an enormous time saver for prefabbing and installing such components as piping insert hangers, seismic inserts, and sleeves. âWe had not preassembled our hangers before,â says Reed. Instead, hangers would be delivered to the field and cut on site. âThe Trimble system allowed us to set a zero point on the metal deck so that we could prefab hangers to a half-inch accuracy in height,â he says.
The system also provided a level of accuracy of plus or minus one-eighth of an inch, versus a quarter-inch industry standard. âWe had a reproducibility that allowed us to use 98-99% of the inserts and prefabricated hangers, compared to about 85% in previous jobs,â says Reed. âThree-D coordination allowed that level of reproducibility.â
Plumbing and pipefitting installation was vastly improved. Instead of having crews of five or six using string and tape to measure and lay out mechanical system inserts, Southland was able to use two-person crews to do the same job more accurately, using the electronic survey equipment. âIt took about two weeks of training to learn how to use the device and the methodology,â recalls Reed. âAfter becoming proficient with the device, their productivity excelled.â
That training paid off in a 50% time savings for making these measurements. âA building on the scale we were working on would have 10,000 to 15,000 data points,â says Reed. âWe were hitting 800 or 900 points per deck per day. We could lay out a 25,000-sf floor plate in three or four days with a two-man crew. That would take a typical crew of six a week to perform the same task.â Even more important, says Reed, âOur accuracy was 99% in the field.â
The Southland team took that expertise and applied it to mechanical system penetrations through framed walls. âIn the past, weâd use tape and string,â says Reed. âWith Trimble, weâd go out with the model and make the measurements. Trimble was much more accurate, and this cut down problems with the drywall framer,â Sharpe Interior Systems.
Improving logistical flow on the job
Combining the interior survey with the BIM model produced other benefits as well. âTo us, prefab is more than just cutting pipe to length and welding it in the shop, or assembling ductwork in the shop,â says Reed. âNow, itâs taking the information from the BIM model so that we have right-size batching of whole sectionsâpreassembled, presoldered, prebracedâto ship to the site.â Reed says his team learned a lot about logistics, just-in-time workflow, and right-size batchingâpackaging, documenting, and numbering all the parts and pieces in the floor plan.
And because Southland was able to get its work done more quickly, the contractor could move along faster, too. âMcCarthy could pour a deck every three or four days,â says Reed.
However, Reed acknowledges that melding the electronic survey data into the BIM model did not always work perfectly. âIn some cases we had limitations when the files were too large,â he says. He cautions that electronic surveying for interior measurements works best for large-scale projects with repetitive floor plansâa high-rise hotel, for example.
Reedâs team also found that its original system for numbering and ordering hangers didnât work in the field and had to be changed midstream. Shipping preassembled trapeze hangers with the rods already installed also proved overly cumbersome. Instead, they taped the struts and other pieces to the rods and had crews put them together in the field. âThat solution sounds counterintuitive, but it was 15% faster to do it that way,â says Reed.
But thereâs no thought of going back to the old stick-and-tape ways of measuring interiors. Southland has adopted a standard of prefabricating 100% of all hangers for major new construction work. âThe Trimble systemâs accuracy eliminates a lot of human error,â says Reed. âItâs enabling us to take our prefab capability to the next level, to plan further in advance without having to do rework in the field.â
Related Stories
Green | Apr 22, 2015
GSA's Federal Center South Building honored with AIA Top Ten Plus Award for 'verified' sustainable performance
The annual award recognizes green building projects that have quantifiable metrics demonstrating the performance and positive impact of the sustainable design.
Architects | Apr 21, 2015
Megatrends shaping commercial building design
Genslerâs 2015 Design Forecast focuses on how changes in demographics, workplace preferences, and technology are affecting how and why structures get built.
Office Buildings | Apr 21, 2015
Stop the endless debate over open vs. closed work environments
Rather than be confused by the constant stream of opinions, leadership teams contemplating workplace investments should start with powerful employee engagement strategies that drive results.
BIM and Information Technology | Apr 21, 2015
Software tools shouldn't dictate the AEC process
With over 200 solutions on the market, construction software is one of the most complex and fragmented markets, writes Gensler's Mark Thole.
Cultural Facilities | Apr 20, 2015
Jean Nouvel loses court battle against Philharmonie de Paris over alleged design âsabotageâ
Nouvel boycotted the January opening of the facility and asked for his name to be removed from all references to the work.Â
Contractors | Apr 20, 2015
Too many construction projects donât meet ownersâ expectations: KPMG report
Causes for delays, overruns, and underperformance include project management talent shortages, distrust between owners and contractors, and the lack of fully integrated project management systems.  Â
High-rise Construction | Apr 17, 2015
Construction begins on Goettsch Partners-designed Nanning China Resources Center Tower
The tower's design is derived from its multiple uses, which include 170,000 sm of Class A office space, 5,000 sm of boutique retail, and a 45,000-sm luxury Shangri-La hotel.
Museums | Apr 16, 2015
SANAA and Snøhetta tie at first place for Budapest museum bid
The two firms submitted designs for the New National Gallery and Ludwig Museum, one of five planned museums to be constructed in a park just outside the urban center of Hungaryâs capital.Â
High-rise Construction | Apr 16, 2015
Construction begins on Seattle's Tibet-inspired Potala Tower
Construction on the 41-story Potala Tower in Seattle finally kicked off following a ground-breaking ceremony seven months ago.
Architects | Apr 14, 2015
Jeanne Gang, Bjarke Ingels among participants for inaugural Chicago Architecture Biennial
Some big names include Bjarke Ingels Group and Studio Gang Architects