The JW Marriott brand holds high standards for its luxury hotels, and the new property in Hanoi, Vietnam, is no different. The 74,384-sm building conveys a distinct Vietnamese flair, with its stylized dragon form inspired by local mythology and the country’s coastline.
Sited next to the Vietnam National Convention Center and the Hanoi Museum, convenient to nearby tourist attractions, the JW Marriott Hanoi greets visitors with a landscaped, semi-circular courtyard. Below this raised entry plaza lies a podium level housing two ballrooms; meeting facilities; dining, bar, and lounge areas; three levels of indoor parking; and back-of-house support functions. Atop the podium, the hotel includes a grand lobby, 450 guest rooms and suites, an executive lounge, a glass-enclosed rooftop swimming pool, and a fitness center.
The hotel is built for ADA compliance, even though no such laws currently exist in Vietnam. Accommodations include wider entry corridors in several rooms and special considerations in bathroom facilities. Elegant finishes are a priority throughout.
“It’s not easy working with Marriott’s standards,” remarks Building Team Awards judge Susan Heinking, AIA, NCARB, LEED AP O+M, Vice President and Director of Sustainability at VOA Associates. Indeed, this Building Team had to navigate a thicket of design requirements, including directives from owner Bitexco Group, Marriott International, and the neighboring Vietnam National Convention Center.
GOLD AWARD
Project summaryJW Marriott Hanoi Hotel
Hanoi, VietnamBUILDING TEAM
Submitting firm: Turner International – Vietnam (CM)
Owner/developer: Bitexco Group
Hotel operator: Marriott International
Architect: Carlos Zapata Studio
Architect of record: Viet Nam National Construction Consultants Corporation
Interior architects: Peter Silling & Associates Hotel Interior Design; DWP | Design Worldwide Partnership
Structural: Leslie E. Robertson Associates
Foundation: GECI
MEP: DSA Engineering Contractors: Hyundai Engineering & Construction; Delta Civil and Industrial Construction; Trung A. Stock ConstructionGENERAL INFORMATION
Project size: 74,384 sm
Construction cost: Confidential at owner’s request
Construction period: November 2009 to September 2013
Delivery method: PM/CM as agent, fast-trackMarriott’s in-house architectural group—responsible for overseeing design of all the brand’s hotels and resorts—was brought in at several stages for input and approval, but adherence to their standards proved difficult when financial problems led to a two-year delay.
Marriott criteria had changed in the interim, and new design styles caused previously selected finishes to be rejected. In addition, the clients decided to reorganize the site to make room for two villas, scrapping plans to build tennis courts and install a significant amount of landscaping.
Even basic communication was a concern, with Building Team members and consultants such as Turner Construction, Carlos Zapata Studio, Leslie E. Robertson Associates, and DSA Engineering scattered among offices in nine different countries. The firms decided early on that English would be the standard for all communications.
Vietnam is still a developing country in many aspects, so there was concern about the availability of skilled workers. Safety was also paramount, with Turner implementing weekly training sessions and audits to reinforce this priority for crews. Figuring out the best way to deploy teams—and to keep employees reporting through delays and cash-flow difficulties—made construction management even more complex.
The Building Team brought in international consultants and engineers when expertise was needed on elements unfamiliar to Vietnamese partner firms, such as the cantilevered design and structural steel construction. Sika, which supplied the waterproofing system for the podium roof, sent employees to train contractors on-site to prevent leaks that could threaten the ballrooms below.
The way the JW Marriott Hanoi came together in spite of the obstacles and difficulty level impressed the Building Team Awards judges. Says juror Matthew Dumich, AIA, of Adrian Smith + Gordon Gill Architecture: “It’s as if someone said, ‘No one knows how to do any of this stuff. Let’s do it anyway.’ And it works.”
A curtain wall system at the podium level brings natural light into the hotel’s café. Elegant finishes were a priority for the owner. PHOTO: NGUYEN HAI VAN / COURTESY TURNER VIETNAM
The structure is constructed on a podium, with ballrooms and restaurants on the lowest floor enjoying riverfront views. PHOTO: VU LONG / COURTESY TURNER VIETNAM
Related Stories
Sponsored | | Sep 30, 2014
How project managers can manage technology
Not long ago, the role of a construction project manager revolved around working with people: employees, vendors, consultants, designers, subcontractors and owners. Today, project managers primarily manage information. SPONSORED CONTENT
| Sep 30, 2014
With its 'stacked volumes' scheme, 3XN wins bid to design high-rise in Sydney
By dividing the 200-meter building into five separate volumes and placing atria throughout each volume, the spaces become smaller, more intimate social environments, according to the Danish architects.
| Sep 29, 2014
Living Building vs. LEED Platinum: Comparing the first costs and savings
Skanska USA's Steve Clem breaks down the costs and benefits of various ultra-green building standards and practices.
| Sep 29, 2014
10 common deficiencies in aging healthcare facilities
VOA's Douglas King pinpoints the top issues that arise during healthcare facilities assessments, including missing fire/smoke dampers, out-of-place fire alarms, and poorly constructed doorways.
| Sep 29, 2014
Snøhetta releases final plan for terraced central library in Calgary
The competition-winning New Central Library is now in the final design stages, after two years of community engagement on the part of design firms Snøhetta and DIALOG.
| Sep 25, 2014
Jean Nouvel unveils plans for National Art Museum of China
Of the design, Nouvel describes it as inspired by the simplicity of “a single brush stroke.”
Sponsored | | Sep 25, 2014
Your business doesn’t always need to change
By now, the idea that organizations must adapt to maintain both relevance and market share is so ingrained that it’s been reduced to pithy sayings. But is constant adaptation always the best policy? SPONSORED CONTENT
| Sep 25, 2014
Bjarke Ingels headed home for latest project: Aarhus Island
Aarhus Island will be a waterside development in Denmark's second-largest city. The mixed-use development will implement Ingels' signature angled look in its residential towers.
| Sep 24, 2014
Must see: Semi-submerged hotel planned for Qatar's man-made island
Plans for a new hotel in the Persian Gulf are taking Dubai’s Palm Islands concept to a whole new level—underwater, that is.
| Sep 24, 2014
5 business lessons from a 43-year Star veteran
Mary Ed Cain was supposed to be born a boy. That was the first time she surprised everyone. The second time came on a daily basis during her 43-year career at Star Building Systems. SPONSORED CONTENT