Developers change gears at Atlantic Yards after high-rise modular proves difficult

Developers change gears at Atlantic Yards after high-rise modular proves difficult

Forest City Ratner Companies now has a Chinese partner that will move forward on the next three residential buildings, using conventional construction, while B2 continues to rise.


By BD+C Staff | April 23, 2014
B2 rendering, copyright SHoP
B2 rendering, copyright SHoP

At 32 stories, the B2 residential tower at Atlantic Yards near Brooklyn has been widely lauded as a bellwether for modular construction. But since construction started about 18 months ago, only five of the floors have been built—and developer Forest City Ratner Companies now has a Chinese partner that will move forward on the next three residential buildings, using conventional construction.

According to a report in the New York Times, Forest City Ratner's development partner, Greenland Holding Group, will now have a majority stake in the 22-acre Atlantic Yards mixed-use project. The Shanghai-based firm will oversee the next three residential tower projects, while Forest City Ratner continues to move forward with B2. Completion of the 348,000-sf modular tower, comprising 930 modules and 363 apartments, had been moved to late 2015, more than a year later than planned. 

MaryAnne Gilmartin, Forest City Ratner's chief executive, says technical difficulties have been substantial, both at the nearby factory that's creating the modules and on the Atlantic Yards job site. “It’s been terribly frustrating," she told the New York Times. "But I don’t think this is a referendum on modular. The best way to prove that this works is to build B2.”

The Building Team for B2 includes Skanska, FC + Skanska Modular (a collaboration between Forest City Ratner and Skanska, which is building the components), SHoP, and Arup.

Related Stories

Reconstruction & Renovation | Aug 9, 2016

Renascent architecture: Demolished Frank Lloyd Wright structures get new life

The Frank Lloyd Wright Revival Initiative is set to begin its reconstruction efforts with the Banff Pavilion, which was demolished in 1939.

Building Team | Aug 4, 2016

Thought leaders from architecture, engineering and construction to meet at 2016 Bluebeam eXtreme Conference

Bluebeam users inspire technological change through shared insights and training at three-day event.

| Aug 4, 2016

MULTIFAMILY BUILDING GIANTS: Rental complexes focus on affordability, accessibility, and specialty amenities

To address the affordability problem and attract tenants, owners and developers are experimenting with smaller and smaller units, amenity-rich environments, and “co-living” concepts.

| Aug 4, 2016

Top 110 Multifamily Architecture Firms

Perkins Eastman, CallisonRTKL, and Solomon Cordwell Buenz top Building Design+Construction’s annual ranking of the nation’s largest multifamily building sector architecture and A/E firms, as reported in the 2016 Giants 300 Report.

| Aug 3, 2016

GREEN BUILDING GIANTS: Sustainability leaders turn to wellness and technology to get an edge

AEC leaders in green building are stepping up to a higher level of innovation and to be a green leader today, you have to dig deeper into data.

| Aug 2, 2016

Top 130 Green Building Architecture Firms

Gensler, Stantec, and HOK top Building Design+Construction’s annual ranking of the nation’s largest green building sector architecture and A/E firms, as reported in the 2016 Giants 300 Report.

Architects | Aug 2, 2016

Bradley Lukanic named CannonDesign's CEO

In his new role, Lukanic takes helm of an experienced leadership team crafting and achieving optimal short- and long-term strategies and business outcomes

| Aug 1, 2016

K-12 SCHOOL GIANTS: In a new era of K-12 education, flexibility is crucial to design

Space flexibility is critical to classroom design. Spaces have to be adaptable, even allowing for drastic changes such as a doubling of classroom size.

| Jul 29, 2016

AIRPORT FACILITIES GIANTS: Airports binge on construction during busy year for travel

Terminal construction will grow by nearly $1 billion this year, and it will keep increasing. Airports are expanding and modernizing their facilities to keep passengers moving.

| Jul 29, 2016

Top 35 Airport Terminal Architecture and A/E Firms

Corgan, HOK, and Gensler top Building Design+Construction’s annual ranking of the nation’s largest airport terminal architecture and A/E firms, as reported in the 2016 Giants 300 Report.  

boombox1
boombox2
native1

More In Category


Museums

UT Dallas opens Morphosis-designed Crow Museum of Asian Art

In Richardson, Tex., the University of Texas at Dallas has opened a second location for the Crow Museum of Asian Art—the first of multiple buildings that will be part of a 12-acre cultural district. When completed, the arts and performance complex, called the Edith and Peter O’Donnell Jr. Athenaeum, will include two museums, a performance hall and music building, a grand plaza, and a dedicated parking structure on the Richardson campus.



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021