Design problems now the primary cause of construction claims and disputes

Codes and Standards

Design problems now the primary cause of construction claims and disputes

More likely to occur due to more tight timescales imposed upon third parties engaged in design.


By Peter Fabris, Contributing Editor | December 7, 2021
Cranes at a construction site

Courtesy Pixabay

Design problems are now the primary cause of construction claims and disputes, according to HKA's CRUX Insight 2020 report.

“Design problems are more likely to occur as a result of increasingly tight timescales imposed upon third parties engaged in design” that result in late or incomplete designs and conflict between the parties, the report says. “Failings in the management of third parties across increasingly complex supply chains” also cause major problems.

The consulting firm’s previous report had found that change in project scope was the number one cause for disputes. Projects have also become more prone to deficiencies in workmanship and unforeseen physical conditions, the report found.

The report’s data was primarily compiled before the start of the COVID-19 pandemic. The report examined construction issues in 1,185 projects worldwide with a combined value of $1.8 trillion. HKA expects an increase in arbitration over litigation to settle disputes in the coming years.

Related Stories

| Oct 18, 2012

Princeton, N.J. residents upset over proposal to exempt colleges from land use laws

Princeton, N.J. residents criticized proposed legislation that would exempt private colleges and universities from following local land use laws for construction projects.

| Oct 18, 2012

Utah contracting firm challenges state immigration law

Universal Contracting LLC of American Fork, Utah, has filed suit challenging the constitutionality of Utah’s 2011 immigration law.

| Oct 18, 2012

More than 65,000 construction, design jobs may be cut if sequestration takes place

About $2 billion worth of construction and design projects would be eliminated if scheduled federal budget cuts, referred to as sequestration, take effect on Jan. 2, 2013.

| Oct 18, 2012

OSHA investigating parking garage collapse that kills four at Doral, Fla. college

OSHA is investigating the collapse of a five-story concrete parking garage under construction at Miami Dade College West Campus in Doral, Fla. that killed four workers and injured several others.

| Oct 18, 2012

EPA commercial building lead paint rule pushed back to 2015

The U.S. Environmental Protection Agency's inclusion of commercial buildings in a residential lead paint rule is being delayed until 2015.

| Oct 18, 2012

Chicago pushing green roofs to reduce heat island effect

The city of Chicago has mandated that all new buildings that require any public funds must be LEED certified, usually with a green roof.

| Oct 11, 2012

OSHA launches pilot program for alternative dispute resolution on whistleblower complaints

The Occupational Safety and Health Administration (OSHA) is launching an alternative dispute resolution (ADR) pilot program for complaints filed with OSHA's Whistleblower Protection Program.

| Oct 11, 2012

Bill promotes investment in commercial, multifamily retrofits

The Commercial Building Modernization Act recently introduced in the Senate would extend and streamline a current tax deduction to encourage commercial and multifamily residential building owners to perform comprehensive energy-efficient retrofits.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021