Design problems now the primary cause of construction claims and disputes

Codes and Standards

Design problems now the primary cause of construction claims and disputes

More likely to occur due to more tight timescales imposed upon third parties engaged in design.


By Peter Fabris, Contributing Editor | December 15, 2021
excavator
Courtesy Pixabay

Design problems are now the primary cause of construction claims and disputes, according to HKA's CRUX Insight 2020 report.

“Design problems are more likely to occur as a result of increasingly tight timescales imposed upon third parties engaged in design” that result in late or incomplete designs and conflict between the parties, the report says. “Failings in the management of third parties across increasingly complex supply chains” also cause major problems.

The consulting firm’s previous report had found that change in project scope was the number one cause for disputes. Projects have also become more prone to deficiencies in workmanship and unforeseen physical conditions, the report found.

The report’s data was primarily compiled before the start of the COVID-19 pandemic. The report examined construction issues in 1,185 projects worldwide with a combined value of $1.8 trillion. HKA expects an increase in arbitration over litigation to settle disputes in the coming years.

Related Stories

Codes and Standards | Jul 14, 2021

Biden’s infrastructure proposal includes massive investment in school buildings

‘Once in a lifetime opportunity’ to upgrade HVAC and other key systems.

Codes and Standards | Jul 13, 2021

Reluctance to fund maintenance on older condos is a serious problem

Owner associations defer needed work, putting properties at risk.

Codes and Standards | Jul 12, 2021

Regulations on hydrofluorocarbons reduce roof insulation options

Canada, some U.S. states ban HFC blowing agents used in closed-cell foam.

Codes and Standards | Jul 8, 2021

New York City shuts down 322 construction sites for unsafe conditions

Action comes as inspectors visit more than 2,100 sites.

Codes and Standards | Jul 7, 2021

Bechtel, Nautilus partner on sustainable, high-performance data centers

Facilities would use 70% less power for cooling, eliminate consumption of drinking water.

Codes and Standards | Jul 7, 2021

Surfside condo collapse could spur new legislation

Natl. Institute of Standards and Technology is investigating.

Codes and Standards | Jul 7, 2021

Intl. Code Council appoints committees to lead energy code development

One-third of appointees are government regulators.

Codes and Standards | Jul 1, 2021

COVID-19 made payment delays to contractors much worse

Only one in ten companies is always getting paid in full.

Codes and Standards | Jun 30, 2021

New resource for public sector organizations to develop energy data management program

Dept. of Energy document contains more than 30 examples of successful implementations.

Codes and Standards | Jun 29, 2021

Biden China policy may spur more increased U.S. PV manufacturing capacity

Senate bill proposes advanced solar manufacturing production credit.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021