In the aftermath of the 9/11 terrorist attacks, New York City enacted a requirement that all office buildings 100 feet tall or taller install sprinkler systems.
The deadline for meeting that code mandate is this July 1. Building owners must submit a final report on the sprinkler system by an engineer or architect by that date. The deadline is not for receiving approval from the city, says Daniel Colombini, principal and director of plumbing and fire protection engineering, Goldman Copeland.
“It’s important to allow time for the engineer or architect to inspect the building and for the building contractor, before that, to close out the building department application,” Colombini says. “It can take a month or more for the contractor to complete that process.”
Some spaces that were exempt under older codes, such as bathrooms and mechanical rooms, are now covered. “It’s essential to ensure that all such spaces are now sprinklered,” he adds. Extension requests are no longer being accepted by the city, and there is no process for appeal.
Related Stories
Codes and Standards | Apr 19, 2021
Failed landmark preservation effort in Chicago provides lessons for planners
Gentrification fears heightened among Pilsen neighborhood residents doomed ambitious preservation plan.
Codes and Standards | Apr 14, 2021
New Phase 1 Environmental Site Assessment standard debuts in 2021
Will affect 250,000 commercial real estate deals a year.
Codes and Standards | Apr 13, 2021
British Columbia moves to accelerate mass timber construction
Province funds demonstration projects as part of economic recovery.
Codes and Standards | Apr 12, 2021
WoodWorks and Think Wood release first Mass Timber Design Manual
Interactive collection of information on mass timber products, design best practices, taller wood construction and sustainability.
Codes and Standards | Apr 8, 2021
Sensors used in tunable lighting systems found to have high reliability
DOE study investigated items used to control lumen depreciation, chromaticity shifts, and changes in drivers.
Codes and Standards | Apr 7, 2021
Red tape ruined the U.K.’s home retrofit program
Lessons learned could help US avoid that fate.
Codes and Standards | Apr 6, 2021
Lendlease achieves net-zero carbon in Boston, Chicago multifamily portfolio
New projects in New York, Los Angeles on track to reach goal.
Codes and Standards | Apr 5, 2021
Specification for sliding door, lift and slide roller assemblies updated
Addresses market trend toward heavy sliding doors.
Codes and Standards | Apr 5, 2021
Construction employment rebounds in March following February drop
Rising costs, supply-chain woes, and cancellations threaten outlook.
Codes and Standards | Apr 2, 2021
Intl. Code Council’s new development system could be a brake on building decarbonization
Local governments lose influence on creating new energy efficiency rules.