Demand for data centers is “exploding,” says Raj Gupta, PE, LEED AP, CEO of Environmental Systems Design and emeritus member of BD+C’s Editorial Board. According to Gartner Inc., in 2010, 2% of data centers contained 52% of total data center floor space and accounted for 63% of data center hardware spending.
In 2015, 2% of data centers will contain 60% of data center floor space and account for 71% of data center hardware spending.
“Traditional in-house enterprise data centers are under attack,” says Jon Hardcastle, Gartner’s research director. Virtualization technologies are helping companies to utilize their infrastructure more effectively, and data centers are getting more efficient. The move to consolidated third-party data centers is trimming the total number of midsize facilities, while large data centers are benefitting from the rise of cloud computing. +
TOP 25 DATA CENTER SECTOR ARCHITECTURE FIRMS
Rank | Company | 2011 Data Center Revenue ($) |
1 | Corgan Associates | 22,854,000 |
2 | Gensler | 20,100,000 |
3 | HDR Architecture | 16,000,000 |
4 | LEO A DALY | 14,753,871 |
5 | PageSoutherlandPage | 12,890,000 |
6 | Integrated Design Group | 11,436,000 |
7 | Reynolds, Smith and Hills | 4,200,000 |
8 | RTKL Associates | 3,840,295 |
9 | CTA Architects Engineers | 3,787,800 |
10 | EwingCole | 3,000,000 |
11 | SMMA|Symmes Maini & McKee Associates | 2,123,426 |
12 | HLW International | 1,900,000 |
13 | Fentress Architects | 1,456,103 |
14 | Kirksey Architecture | 1,379,269 |
15 | PGAL | 1,096,000 |
16 | Heery International | 808,000 |
17 | Fishbeck, Thompson, Carr & Huber | 600,000 |
18 | Harley Ellis Devereaux | 600,000 |
19 | IBI Group | 563,474 |
20 | H+L Architecture | 537,059 |
21 | Ware Malcomb | 515,000 |
22 | Solomon Cordwell Buenz | 500,000 |
23 | HOK | 426,798 |
24 | Rule Joy Trammell + Rubio | 350,000 |
25 | Gresham, Smith and Partners | 234,347 |
TOP 25 DATA CENTER SECTOR ENGINEERING FIRMS
Rank | Company | 2011 Data Center Revenue ($) |
1 | Fluor Corp. | 212,484,600 |
2 | Jacobs | 119,930,000 |
3 | Syska Hennessy Group | 43,577,806 |
4 | URS Corp. | 34,475,000 |
5 | Merrick & Co. | 31,500,000 |
6 | AKF Group | 10,500,000 |
7 | Atkins North America | 10,035,923 |
8 | Parsons Brinckerhoff | 7,400,000 |
9 | Eaton Energy Solutions | 6,169,598 |
10 | KPFF Consulting Engineers | 5,000,000 |
11 | H.F. Lenz Co. | 4,741,000 |
12 | Burns & McDonnell | 4,500,000 |
13 | Stantec | 4,230,000 |
14 | Glumac | 4,196,563 |
15 | Science Applications International Corp. | 3,950,000 |
16 | Zak Companies | 3,043,228 |
17 | Michael Baker Jr., Inc | 2,970,000 |
18 | R.G. Vanderweil Engineers | 2,830,900 |
19 | RMF Engineering | 2,500,000 |
20 | ESD|Environmental Systems Design | 2,450,000 |
21 | H&A Architects & Engineers | 2,300,000 |
22 | RDK Engineers | 2,245,000 |
23 | Guernsey | 2,041,552 |
24 | Middough | 1,750,000 |
25 | M+W U.S. | 1,654,867 |
TOP 25 DATA CENTER SECTOR CONSTRUCTION FIRMS
Rank | Company | 2011 Data Center Revenue ($) |
1 | Holder Construction | 1,293,000,000 |
2 | DPR Construction | 666,292,020 |
3 | Turner Corporation, The | 434,435,518 |
4 | Whiting-Turner Contracting, The | 393,539,085 |
5 | Skanska USA | 369,889,632 |
6 | Mortenson Construction | 304,900,000 |
7 | Balfour Beatty US | 277,879,080 |
8 | Structure Tone | 259,250,000 |
9 | Jacobs | 119,930,000 |
10 | Gilbane Building | 104,166,000 |
11 | JE Dunn Construction | 89,426,706 |
12 | Weitz Co., The | 71,442,860 |
13 | James G. Davis Construction | 60,000,000 |
14 | Hensel Phelps Construction | 50,360,000 |
15 | Messer Construction | 49,404,845 |
16 | Hoffman Corp. | 46,541,098 |
17 | Manhattan Construction Group | 44,196,000 |
18 | Brasfield & Gorrie | 34,612,782 |
19 | URS Corp. | 34,475,000 |
20 | Sundt Construction | 28,801,944 |
21 | Kitchell | 24,310,000 |
22 | Ryan Companies US | 23,664,942 |
23 | Harkins Builders | 21,000,000 |
24 | McShane Companies, The | 20,000,000 |
25 | Yates Companies., The | 20,000,000 |
Related Stories
| May 11, 2012
Chapter 9 The Key to Commissioning That Works? It Never Stops
Why commissioning for existing and renovated buildings needs to be continuous to be effective.
| May 11, 2012
Chapter 8 High-Performance Reconstruction and Historic Preservation: Conflict and Opportunity
What historic preservationists and energy-performance advocates can learn from each other.
| May 11, 2012
VFA to acquire Altus Group's Capital Planning division
Strategic move strengthens VFA's facilities capital planning market osition in North America.
| May 11, 2012
Betz promoted to senior vice president for McCarthy’s San Diego Office
He will oversee client relations, estimating, office operations and personnel as well as integration of the company’s scheduling, safety and contracts departments.
| May 11, 2012
CRSI appoints Brace chairman
Stevens also elected to board of directors and vice-chair.
| May 11, 2012
Dempster named to AIA College of Fellows
Altoon Partners’ technical and construction services leader honored for his contributions.
| May 11, 2012
AIA launches education and training portal
New portal to host Contract Documents training, education resources in one convenient place.
| May 10, 2012
Chapter 7 When Modern Becomes Historic: Preserving the Modernist Building Envelope
This AIA CES Discovery course explores the special reconstruction questions posed by Modern-era buildings.
| May 10, 2012
Chapter 6 Energy Codes + Reconstructed Buildings: 2012 and Beyond
Our experts analyze the next generation of energy and green building codes and how they impact reconstruction.
| May 10, 2012
Chapter 5 LEED-EB and Green Globes CIEB: Rating Sustainable Reconstruction
Certification for existing buildings under these two rating programs has overtaken that for new construction.