Data center construction facing record-breaking inflation, delays

Data Centers

Data center construction facing record-breaking inflation, delays

Average cost to build has increased by 15%.


By Peter Fabris, Contributing Editor | October 31, 2022
Data Center Construction
Courtesy Pexels.

Data center construction projects face record-breaking inflation amid delays to materials deliveries and competition for skilled labor, according to research from global professional services company Turner & Townsend.

Average costs on data center projects rose 15% in 2022 compared to last year, with escalating prices for energy and key materials squeezing margins. Intense competition for labor from life sciences, gigafactories, and other large-scale advanced manufacturing facilities in North America is driving up labor costs. Some 92% of respondents reported that they are struggling to meet construction demand due to a shortfall of experienced site teams.

Supply chain woes resulting in extended equipment and material lead times are jeopardizing program completion dates, with delays of more than 12 weeks for some components. Of the 45 key markets covered in the survey, North America has five of the top ten most expensive world markets. This is prompting clients to re-evaluate their development strategies to consider building in less costly new or emerging regional markets such as Columbus and Canada.

Despite these challenges, optimism remains high in the sector with 71% of respondents seeing the sector as less susceptible to recessionary pressures than other industries.

Related Stories

Data Centers | Aug 28, 2017

Do AEC firms have the wattage to meet the demands of a charged-up data center sector?

As construction and leasing surge, one big contractor worries about his industry’s talent shortage. 

Data Centers | Aug 16, 2017

The world’s largest data center is being built 140 miles north of the Arctic Circle

The 600,000-sm facility will be on a secure property surrounded by a moat.

Healthcare Facilities | Jul 25, 2017

Healthcare technology: Preparing for the world of tomorrow

This article outlines the current data center landscape in the healthcare sector, industry trends, and challenges and opportunities new technologies present to the healthcare space.

Data Centers | Jul 21, 2017

Operational wellness was an objective for a new 911 call center near San Antonio

The Operations Center consolidates activities that previously were being handled at 25 locations. 

Data Centers | Oct 14, 2016

Where data centers meet design

As technology continues to evolve, we have to simultaneously adapt and help our clients think beyond the short term, writes Gensler's Martin Gollwitzer.

Data Centers | Oct 10, 2016

Data centers enter new era of innovation

AEC firms see opportunities as consultants for clients trying to figure out which data center solution works best for their IT, computing, and distribution needs. 

Data Centers | Sep 26, 2016

Micro data centers keep IT departments connected to computing

Over the past two years, SmithGroup has been getting more requests from clients for micro data centers.

Data Centers | Sep 19, 2016

New ANSI/ASHRAE data center standard is performance-based, more flexible

The aim of the standard was to ‘not stifle innovation.’

| Aug 10, 2016

DATA CENTER GIANTS: Information overload is pushing the limits of mission-critical facilities

Streamlined design and delivery approaches for individual business enterprises and co-location facilities are being born out of the necessity to bring new capacity online as quickly as possible.

| Aug 10, 2016

Top 50 Data Center Engineering Firms

Vanderweil Engineers, Jacobs, and Syska Hennessy Group top Building Design+Construction’s annual ranking of the nation’s largest data center sector engineering and E/A firms, as reported in the 2016 Giants 300 Report.

boombox1
boombox2
native1

More In Category

Data Centers

What’s next for data center design in 2024

Nuclear power, direct-to-chip liquid cooling, and data centers as learning destinations are among the emerging design trends in the data center sector, according to Scott Hays, Sector Leader, Sustainable Design, with HED. 




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021