Danish hospital is constructed from 24 steel frame modules

Modular Building

Danish hospital is constructed from 24 steel frame modules

Onsite construction was completed in two weeks.


By David Malone, Associate Editor | March 17, 2020
MARS Radiology equipment in modules

All photos courtesy FortaPRO

Forta PRO, a Latvian-based modular construction company, and MT Højgaard, a Danish construction company, recently completed the MARS Satellite Radiology Clinic building in Copenhagen, Denmark. The new clinic will provide additional acute care services to patients for faster and more advanced medical research.

The MARS clinic was built as a modular building off-site in Latvia and then shipped across the Baltic Sea to the assembly location. It combines 24 steel frame modules weighing up to 27 tons each. The most substantial blocks are equipped with all the necessary protection systems to provide safe and efficient operation for quicker patient diagnostics. The modules were designed to fit the most modern medical equipment such as X-Ray, CT, and MRI scanners.

 

FortaPRO module being lifted into place

 

Onsite construction was completed in only two weeks without disrupting neighboring working clinical departments or blocking traffic pathways for ambulances. By assembling the modules in a factory, onsite dust and noise was mitigated as compared to traditional construction.

 

See Also: China builds 645,000-sf coronavirus hospital in 10 days

 

 

MARS Radiology clinic exterior

Related Stories

| Jan 23, 2014

Think you can recognize a metal building from the outside?

What looks like brick, stucco or wood on the outside could actually be a metal building. Metal is no longer easily detectable. It’s gotten sneakier visually. And a great example of that is the Madison Square retail center in Norman, Okla.

| Jan 17, 2014

Australian project transforms shipping containers into serene workplace

Australian firm Royal Wolf has put its money where its mouth is by creating an office facility out of shipping containers at its depot and fabrication center in Sunshine, Victoria.

| Jan 13, 2014

Custom exterior fabricator A. Zahner unveils free façade design software for architects

The web-based tool uses the company's factory floor like "a massive rapid prototype machine,” allowing designers to manipulate designs on the fly based on cost and other factors, according to CEO/President Bill Zahner.

| Jan 11, 2014

Getting to net-zero energy with brick masonry construction [AIA course]

When targeting net-zero energy performance, AEC professionals are advised to tackle energy demand first. This AIA course covers brick masonry's role in reducing energy consumption in buildings. 

| Jan 6, 2014

What is value engineering?

If you had to define value engineering in a single word, you might boil it down to "efficiency." That would be one word, but it wouldn’t be accurate.

| Dec 23, 2013

MBI commends start of module setting at B2, world's tallest modular building

The first modules have been set at B2 residential tower at Atlantic Yards in New York, set to become the tallest modular building in the world.

| Dec 13, 2013

Safe and sound: 10 solutions for fire and life safety

From a dual fire-CO detector to an aspiration-sensing fire alarm, BD+C editors present a roundup of new fire and life safety products and technologies. 

| Dec 10, 2013

16 great solutions for architects, engineers, and contractors

From a crowd-funded smart shovel to a why-didn’t-someone-do-this-sooner scheme for managing traffic in public restrooms, these ideas are noteworthy for creative problem-solving. Here are some of the most intriguing innovations the BD+C community has brought to our attention this year.

| Dec 10, 2013

Modular Pedia-Pod: Sustainability in healthcare construction [slideshow]

Greenbuild 2013 in Philadelphia was the site of a unique display—Pedia-Pod, a modular pediatric treatment room designed and built by NRB, in collaboration with the editors of Building Design+Construction, SGC Horizon LLC, and their team of medical design consultants.

| Nov 27, 2013

Wonder walls: 13 choices for the building envelope

BD+C editors present a roundup of the latest technologies and applications in exterior wall systems, from a tapered metal wall installation in Oklahoma to a textured precast concrete solution in North Carolina. 

boombox1
boombox2
native1

More In Category

Contractors

Contractors expect to spend more time on prefabrication, according to FMI study

Get ready for a surge in prefabrication activity by contractors. FMI, the consulting and investment banking firm, recently polled contractors about how much time they were spending, in craft labor hours, on prefabrication for construction projects. More than 250 contractors participated in the survey, and the average response to that question was 18%. More revealing, however, was the participants’ anticipation that craft hours dedicated to prefab would essentially double, to 34%, within the next five years.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021

Â