Cuyahoga County Soldiers’ and Sailors’ Monument, Cleveland, Ohio

Cuyahoga County Soldiers’ and Sailors’ Monument, Cleveland, Ohio


By By Robert Cassidy, Editorial Director | October 12, 2010

The Cuyahoga County Soldiers’ and Sailors’ Monument was dedicated on the Fourth of July, 1894, to honor the memory of the more than 9,000 Cuyahoga County veterans of the Civil War. The small but impressive structure, with a 125-foot column topped by a statue named “Goddess of Freedom,” holds a place of prominence in Cleveland’s Public Square.

In August 2006, the Cuyahoga County Commissioners called for a modest renovation, cleaning, and relighting of the monument, under the supervision of county architect Berj A. Shakarian, AIA, CSI. The $1 million cost was to be raised by a nonprofit foundation, the Soldiers’ and Sailors’ Monument Support Group.

Extensive research by the Cleveland design firm Westlake Reed Leskosky (with Peter van Dijk, FAIA) determined that more extensive work was required than originally anticipated. The roof needed re-caulking. The marble tablets were bent out of shape and discolored. The stained-glass windows needed restoration. In all, the cost would double. Undeterred, the support group raised nearly $2 million from state and county funds and contributions from foundations, businesses, veterans’ groups, and private individuals.

The work began in late 2008. Perhaps the most unusual technical problem had to do with the commemorative tablets. The 4x7-foot slabs, about an inch thick, each weighing 350 pounds, had to be cleaned so that the marble veining could show through the original yellow tint. The traditional technique, mud-based poultice, was ruled out. Research determined that a latex-based cleaning product, if applied and allowed to dry for 13-15 hours, would form a film that could be peeled off. Though tedious, the technique cut the usual cleaning time from three months to three weeks.

Many of the many of the marble slabs were bent out of shape, and the Building Team considered using a method developed by Lord Raleigh in the 1920s—soak the slabs in hot water and bend them back under pressure—but the National Park Service nixed the idea. Instead, to at least stabilize the slabs, the team installed a fin-tube heating system, dehumidifiers, and air-conditioning to control the humidity that was deemed to be the likely cause of the distortion problem.

Detailed research into the marble decoration revealed that the monument had three levels of coloration: tinting (to allow the veining to show through); marbleizing (where veining is augmented or added); and ornamentation (where both tinting and marbleizing are used along with non-opaque colors).

Balancing their research findings, the demands of historical accuracy, and aesthetic interpretation, the team developed a palette of eight colors to restore the original polychromatic interior marbles to their original brilliance. Careful attention was paid to sealing the finishes.

Fourteen Tiffany-style stained-glass windows—two above the entry doors depicting sunrise and sunset, the other 12 portraying military regalia and imagery—were found to be bulging or missing glass. Team members traveled to Chicago to find perfect matches for the missing glass, and the windows were disassembled, repaired, cleaned, and reinstalled.

To enhance the visitor experience, new fluorescent, track, and LED lighting was carefully balanced to enhance the freshly tinted and re-inked lettering of the marble tablets and highlight various accent items.

The final touch had to do with a bronze relief of President Lincoln. Photographic research showed that, as late as 1932, Lincoln was holding the shackles of a freed slave in his right hand, but the shackles had gone missing for more than 40 years. The Building Team restored the shackles in time for the grand reopening last June.

“The research was the most difficult part,” said jurist Tom Brooks, VP, Restoration Division, Berglund Construction, Chicago. Added judge Darlene Ebel, Director, Facilities Information Management, University of Illinois at Chicago, “Restraint was used. It takes a lot of judgment to decide what level of restoration to do. What they did was absolutely right.”

“This is an inspiring project,” said George Karl Tuhowski, III, LEED AP, general superintendent, Leopardo Construction, Hoffman Estates, Ill. “No stone was left unturned.” BD+C

PROJECT SUMMARY

Building Team

Submitting firm: Soldiers’ and Sailors’ Monument Support Group

Owner: Cuyahoga County Soldiers’ and Sailors’ Monument Commission

Architect/Interior design/MEP engineer/Historic specialist: Westlake Reed  Leskosky with Peter van Dijk, FAIA

GC: EnviroCom Construction, Inc.

General Information

Size: 1,600 gsf with 125-foot column and statue

Construction cost: $2.0 million

Construction period: May 2009 to May 2010

Delivery method: Design-bid-build

Related Stories

| Jun 28, 2012

Federal applications of renewable energy

U.S. Army Fort Knox: Using the Earth for space heating and cooling. The U.S. Department of Energy’s (DOE) Federal Energy Management Program (FEMP) facilitates the Federal Government’s implementation of sound, cost-effective energy management and investment practices to enhance the nation’s energy security and environmental stewardship.

| Jun 27, 2012

HDR opens office in Beijing

The Beijing office is HDR’s second location in China; the firm’s other office is in Shanghai.

| Jun 27, 2012

KBE Building wins honor for Armed Forces Reserve Center

The construction phase was completed in just 16 months.

| Jun 27, 2012

SOM’s Baker receives honorary doctorate in engineering from Heriot-Watt University

Baker recognized for his career and influential contribution in the field of structural engineering.

| Jun 25, 2012

Living green wall planned for InterContinental Chicago

Project, with price tag of $2 million to $3 million, needs council approval.

| Jun 25, 2012

AIA-NJ honors DMR Architects

The academic building, completed in 2009, provides classrooms, computer labs, faculty offices, and meeting spaces for the College, which has a steady 7% annual increase in enrollment.

| Jun 25, 2012

Thornton Tomasetti appoints Hofmeister and Zhu to board of directors

The addition of Hofmeister and Zhu brings the number of directors to 10.

| Jun 20, 2012

WHR’s Tradewell Fellowship Marks 15th Anniversary

Fellowship program marks milestone with announcement of new program curator and 2012 fellow

| Jun 15, 2012

Beck Group/Atlanta wins AGC Build Georgia Award

Site-specific safety plan, BIM analysis and third-party structural review contributed to successful implementation.

| Jun 15, 2012

Baldwin joins Charlotte office of Perkins Eastman as principal

Experience in healthcare planning and design to expand national healthcare practice in South and Mid-Atlantic.

boombox1
boombox2
native1

More In Category




Resiliency

U.S. is reducing floodplain development in most areas

The perception that the U.S. has not been able to curb development in flood-prone areas is mostly inaccurate, according to new research from climate adaptation experts. A national survey of floodplain development between 2001 and 2019 found that fewer structures were built in floodplains than might be expected if cities were building at random.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021