flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Cuyahoga County Soldiers’ and Sailors’ Monument, Cleveland, Ohio

Cuyahoga County Soldiers’ and Sailors’ Monument, Cleveland, Ohio


By By Robert Cassidy, Editorial Director | October 12, 2010

The Cuyahoga County Soldiers’ and Sailors’ Monument was dedicated on the Fourth of July, 1894, to honor the memory of the more than 9,000 Cuyahoga County veterans of the Civil War. The small but impressive structure, with a 125-foot column topped by a statue named “Goddess of Freedom,” holds a place of prominence in Cleveland’s Public Square.

In August 2006, the Cuyahoga County Commissioners called for a modest renovation, cleaning, and relighting of the monument, under the supervision of county architect Berj A. Shakarian, AIA, CSI. The $1 million cost was to be raised by a nonprofit foundation, the Soldiers’ and Sailors’ Monument Support Group.

Extensive research by the Cleveland design firm Westlake Reed Leskosky (with Peter van Dijk, FAIA) determined that more extensive work was required than originally anticipated. The roof needed re-caulking. The marble tablets were bent out of shape and discolored. The stained-glass windows needed restoration. In all, the cost would double. Undeterred, the support group raised nearly $2 million from state and county funds and contributions from foundations, businesses, veterans’ groups, and private individuals.

The work began in late 2008. Perhaps the most unusual technical problem had to do with the commemorative tablets. The 4x7-foot slabs, about an inch thick, each weighing 350 pounds, had to be cleaned so that the marble veining could show through the original yellow tint. The traditional technique, mud-based poultice, was ruled out. Research determined that a latex-based cleaning product, if applied and allowed to dry for 13-15 hours, would form a film that could be peeled off. Though tedious, the technique cut the usual cleaning time from three months to three weeks.

Many of the many of the marble slabs were bent out of shape, and the Building Team considered using a method developed by Lord Raleigh in the 1920s—soak the slabs in hot water and bend them back under pressure—but the National Park Service nixed the idea. Instead, to at least stabilize the slabs, the team installed a fin-tube heating system, dehumidifiers, and air-conditioning to control the humidity that was deemed to be the likely cause of the distortion problem.

Detailed research into the marble decoration revealed that the monument had three levels of coloration: tinting (to allow the veining to show through); marbleizing (where veining is augmented or added); and ornamentation (where both tinting and marbleizing are used along with non-opaque colors).

Balancing their research findings, the demands of historical accuracy, and aesthetic interpretation, the team developed a palette of eight colors to restore the original polychromatic interior marbles to their original brilliance. Careful attention was paid to sealing the finishes.

Fourteen Tiffany-style stained-glass windows—two above the entry doors depicting sunrise and sunset, the other 12 portraying military regalia and imagery—were found to be bulging or missing glass. Team members traveled to Chicago to find perfect matches for the missing glass, and the windows were disassembled, repaired, cleaned, and reinstalled.

To enhance the visitor experience, new fluorescent, track, and LED lighting was carefully balanced to enhance the freshly tinted and re-inked lettering of the marble tablets and highlight various accent items.

The final touch had to do with a bronze relief of President Lincoln. Photographic research showed that, as late as 1932, Lincoln was holding the shackles of a freed slave in his right hand, but the shackles had gone missing for more than 40 years. The Building Team restored the shackles in time for the grand reopening last June.

“The research was the most difficult part,” said jurist Tom Brooks, VP, Restoration Division, Berglund Construction, Chicago. Added judge Darlene Ebel, Director, Facilities Information Management, University of Illinois at Chicago, “Restraint was used. It takes a lot of judgment to decide what level of restoration to do. What they did was absolutely right.”

“This is an inspiring project,” said George Karl Tuhowski, III, LEED AP, general superintendent, Leopardo Construction, Hoffman Estates, Ill. “No stone was left unturned.” BD+C

PROJECT SUMMARY

Building Team

Submitting firm: Soldiers’ and Sailors’ Monument Support Group

Owner: Cuyahoga County Soldiers’ and Sailors’ Monument Commission

Architect/Interior design/MEP engineer/Historic specialist: Westlake Reed  Leskosky with Peter van Dijk, FAIA

GC: EnviroCom Construction, Inc.

General Information

Size: 1,600 gsf with 125-foot column and statue

Construction cost: $2.0 million

Construction period: May 2009 to May 2010

Delivery method: Design-bid-build

Related Stories

Mixed-Use | Feb 13, 2015

First Look: Sacramento Planning Commission approves mixed-use tower by the new Kings arena

The project, named Downtown Plaza Tower, will have 16 stories and will include a public lobby, retail and office space, 250 hotel rooms, and residences at the top of the tower. 

Architects | Feb 13, 2015

OMA commissioned to design newest New York High Line addition

Rem Koolhaas is the latest addition to the list of starchitects working on projects near the High Line elevated park.

Codes and Standards | Feb 12, 2015

ASHRAE, USGBC, IES consider biomass requirements in green building standard

The proposal would add biomass to approved renewables.

Codes and Standards | Feb 12, 2015

New Appraisal Institute form aids in analysis of green commercial building features

The Institute’s Commercial Green and Energy Efficient Addendum offers a communication tool that lenders can use as part of the scope of work. 

Office Buildings | Feb 12, 2015

Is Houston headed for an office glut?

More than 13 million sf could be completed this year, adding to this metro’s double-digit vacancy woes.

Modular Building | Feb 12, 2015

New shipping container complex begins construction in Albuquerque

The Green Jeans Farmery already has a hydroponic farm component courtesy of owner and entrepreneur Roy Solomon.

Transit Facilities | Feb 12, 2015

Gensler proposes network of cycle highways in London’s unused underground

Unused tube lines would host pedestrian paths, cycle routes, cultural spaces, and retail outlets.

Healthcare Facilities | Feb 11, 2015

Primer: Using 'parallel estimating' to pinpoint costs on healthcare construction projects

As pressure increases to understand capital cost prior to the first spade touching dirt, more healthcare owners are turning to advanced estimating processes, like parallel estimating, to improve understanding of exposure, writes CBRE Healthcare's Andrew Sumner.

Transportation & Parking Facilities | Feb 11, 2015

11 of the nation’s best ‘Complete Streets’ policies of 2014

Austin, Texas, and Troy, N.Y., are among the cities with the strongest safe streets policies, according to a new report.

Sponsored | Roofing | Feb 11, 2015

New school blends with local architecture using Petersen metal roof

Perkins Eastman in Stamford, Conn., designed the school to emphasize and integrate the International Baccalaureate curriculum throughout.

boombox1
boombox2
native1

More In Category


Warehouses

California bill would limit where distribution centers can be built

A bill that passed the California legislature would limit where distribution centers can be located and impose other rules aimed at reducing air pollution and traffic. Assembly Bill 98 would tighten building standards for new warehouses and ban heavy diesel truck traffic next to sensitive sites including homes, schools, parks and nursing homes.



halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021