Cuyahoga County Soldiers’ and Sailors’ Monument, Cleveland, Ohio

Cuyahoga County Soldiers’ and Sailors’ Monument, Cleveland, Ohio


By By Robert Cassidy, Editorial Director | October 12, 2010

The Cuyahoga County Soldiers’ and Sailors’ Monument was dedicated on the Fourth of July, 1894, to honor the memory of the more than 9,000 Cuyahoga County veterans of the Civil War. The small but impressive structure, with a 125-foot column topped by a statue named “Goddess of Freedom,” holds a place of prominence in Cleveland’s Public Square.

In August 2006, the Cuyahoga County Commissioners called for a modest renovation, cleaning, and relighting of the monument, under the supervision of county architect Berj A. Shakarian, AIA, CSI. The $1 million cost was to be raised by a nonprofit foundation, the Soldiers’ and Sailors’ Monument Support Group.

Extensive research by the Cleveland design firm Westlake Reed Leskosky (with Peter van Dijk, FAIA) determined that more extensive work was required than originally anticipated. The roof needed re-caulking. The marble tablets were bent out of shape and discolored. The stained-glass windows needed restoration. In all, the cost would double. Undeterred, the support group raised nearly $2 million from state and county funds and contributions from foundations, businesses, veterans’ groups, and private individuals.

The work began in late 2008. Perhaps the most unusual technical problem had to do with the commemorative tablets. The 4x7-foot slabs, about an inch thick, each weighing 350 pounds, had to be cleaned so that the marble veining could show through the original yellow tint. The traditional technique, mud-based poultice, was ruled out. Research determined that a latex-based cleaning product, if applied and allowed to dry for 13-15 hours, would form a film that could be peeled off. Though tedious, the technique cut the usual cleaning time from three months to three weeks.

Many of the many of the marble slabs were bent out of shape, and the Building Team considered using a method developed by Lord Raleigh in the 1920s—soak the slabs in hot water and bend them back under pressure—but the National Park Service nixed the idea. Instead, to at least stabilize the slabs, the team installed a fin-tube heating system, dehumidifiers, and air-conditioning to control the humidity that was deemed to be the likely cause of the distortion problem.

Detailed research into the marble decoration revealed that the monument had three levels of coloration: tinting (to allow the veining to show through); marbleizing (where veining is augmented or added); and ornamentation (where both tinting and marbleizing are used along with non-opaque colors).

Balancing their research findings, the demands of historical accuracy, and aesthetic interpretation, the team developed a palette of eight colors to restore the original polychromatic interior marbles to their original brilliance. Careful attention was paid to sealing the finishes.

Fourteen Tiffany-style stained-glass windows—two above the entry doors depicting sunrise and sunset, the other 12 portraying military regalia and imagery—were found to be bulging or missing glass. Team members traveled to Chicago to find perfect matches for the missing glass, and the windows were disassembled, repaired, cleaned, and reinstalled.

To enhance the visitor experience, new fluorescent, track, and LED lighting was carefully balanced to enhance the freshly tinted and re-inked lettering of the marble tablets and highlight various accent items.

The final touch had to do with a bronze relief of President Lincoln. Photographic research showed that, as late as 1932, Lincoln was holding the shackles of a freed slave in his right hand, but the shackles had gone missing for more than 40 years. The Building Team restored the shackles in time for the grand reopening last June.

“The research was the most difficult part,” said jurist Tom Brooks, VP, Restoration Division, Berglund Construction, Chicago. Added judge Darlene Ebel, Director, Facilities Information Management, University of Illinois at Chicago, “Restraint was used. It takes a lot of judgment to decide what level of restoration to do. What they did was absolutely right.”

“This is an inspiring project,” said George Karl Tuhowski, III, LEED AP, general superintendent, Leopardo Construction, Hoffman Estates, Ill. “No stone was left unturned.” BD+C

PROJECT SUMMARY

Building Team

Submitting firm: Soldiers’ and Sailors’ Monument Support Group

Owner: Cuyahoga County Soldiers’ and Sailors’ Monument Commission

Architect/Interior design/MEP engineer/Historic specialist: Westlake Reed  Leskosky with Peter van Dijk, FAIA

GC: EnviroCom Construction, Inc.

General Information

Size: 1,600 gsf with 125-foot column and statue

Construction cost: $2.0 million

Construction period: May 2009 to May 2010

Delivery method: Design-bid-build

Related Stories

Architects | Jun 15, 2016

Design Thinking makes its way into Yale School of Management

The school will introduce Design Observer co-founders Jessica Helfand and Michael Bierut as faculty.

Retail Centers | Jun 14, 2016

Zaha Hadid and Gensler among finalists for Sunset Strip billboard design competition

The concepts are curvy, sleek, and multidimensional, and feature sharp digital displays.

Movers+Shapers | Jun 14, 2016

VERTICAL INTEGRATOR: How Brooklyn’s Alloy LLC evolved from an architecture firm into a full-fledged development company

Led by an ambitious President and a CEO with deep pockets, Alloy LLC's six entities control the entire development process: real estate development, design, construction, brokerage, property management, and community development.

Office Buildings | Jun 14, 2016

Let's not forget introverts when it comes to workplace design

Recent design trends favor extroverts who enjoy collaboration. HDR's Lynn Mignola says that designers need to accommodate introverts, people who recharge with solitude, as well.

Building Team | Jun 13, 2016

BD+C launches Women in Design+Construction Conference

Inaugural 2.5-day event will convene 125+ leading AEC women in Dana Point, Calif., November 9-11, for professional development, networking, and career training.  

University Buildings | Jun 9, 2016

Designing for interdisciplinary communication in university buildings

Bringing people together remains the main objective when designing academic projects. SRG Design Principal Kent Duffy encourages interaction and discovery with a variety of approaches. 

BIM and Information Technology | Jun 7, 2016

Conquer computational design: 5 tips for starting your journey

Data-driven design expert Nathan Miller offers helpful advice for getting your firm ready to use CD tools and concepts. 

BIM and Information Technology | Jun 7, 2016

6 ways smart AEC firms are using computational design methods

Rapid prototyping, custom plug-ins, and data dashboards are among the common applications for computational design.

Building Team | Jun 2, 2016

Managing risk when building in challenging locations

AEC firms recognize the upsides of exploring new, emerging markets. Whitehorn Financial's Steve Whitehorn offers four principles that can help guide you to success.

Airports | Jun 1, 2016

LaGuardia Airport’s massive redevelopment begins construction

The development consortium has secured financing for the $4 billion project, and signed an operating lease through 2050.

boombox1
boombox2
native1

More In Category

Warehouses

California bill would limit where distribution centers can be built

A bill that passed the California legislature would limit where distribution centers can be located and impose other rules aimed at reducing air pollution and traffic. Assembly Bill 98 would tighten building standards for new warehouses and ban heavy diesel truck traffic next to sensitive sites including homes, schools, parks and nursing homes.




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021