flexiblefullpage
billboard
interstitial1
catfish1
Currently Reading

Curtainwall façade installation at Ohio State Cancer and Critical Care facility

Curtainwall façade installation at Ohio State Cancer and Critical Care facility


By By BD+C Staff | September 23, 2011
A sophisticated curtainwall facade will be installed at the new OSU Cancer and Critical Care facility.

 

 

 

 

 

 

 

 

 

The Ohio State University, and it's construction management team Turner Construction-Bovis Lend Lease, recently selected National Enclosure Co. to design and install the sophisticated curtainwall facade for the new Cancer and Critical Care facility. As part of the university's high-profile Project One initiative, the new facility adds nearly 800,000 sf and is located on the main campus in Columbus, Ohio. Completion of the approximately $15 million contract is expected to be December 2012.
The Ohio State University's Cancer and Critical Care facility is designed by internationally recognized Hellmuth, Obata + Kassabaum (HOK).
The design incorporates a highly energy efficient, unitized curtainwall facade for the tower, which is a key component in the design's projected achievement of LEED Gold status.
NEC has been selected as the Design Assist Contractor which integrates the firm with other team members to develop the final design implementation. NEC's contribution of a scalable design and installation technology will provide a standardized, factory-assembled unitized facade which will be adaptable and customized for the Cancer and Critical Care facility. 
This recently awarded contract demonstrates the industry demand for high-performance and technologically-innovative solutions for advance facades on architectural projects. Whether glass, terracotta, aluminum, stainless steel, granite or stone, NEC has developed a cost-effective solution which is changing the way advance architecture is being achieved. BD+C

Related Stories

| Sep 23, 2011

Okanagan College sets sights on Living Buildings Challenge

The Living Building Challenge requires projects to meet a stringent list of qualifications, including net-zero energy and water consumption, and address critical environmental, social and economic factors. 

| Sep 20, 2011

PPG, Pleotint to co-market environmentally adaptive glazing technology with low-e glass

 Laminated between two lites of glass, SRT interlayer may be used monolithically or within an insulating glass unit. 

| Sep 14, 2011

Empire State Building achieves LEED Gold ?

The 2.85 million-sf building is celebrating its 80th anniversary while nearing completion of its renewal and repurposing to meet the needs of 21st Century businesses.

| Sep 14, 2011

Thornton Tomasetti’s Poon named to the Council on Tall Buildings and Urban Habitat’s Board of Trustees

 During his 30-plus years of experience, Poon has been responsible for the design and construction of super high-rise structures, mixed-used buildings, hotels, airports, arenas and residential buildings worldwide. 

| Sep 12, 2011

LACCD’s $6 billion BIM connection

 The Los Angeles Community College District requires every design-build team in its massive modernization program to use BIM, but what they do with their 3D data after construction is completed may be the most important change to business as usual.

| Sep 12, 2011

Scan, Deconstruct, Rebuild

How laser scanning helped improve construction schedules, plans, and final designs for a major reconstruction project.

| Sep 12, 2011

PVs play new roles as a teaching tool

Solar installations are helping K-12 schools around the country save money and teach students the intricacies of renewable energy sources.

| Sep 12, 2011

Living Buildings: Are AEC Firms up to the Challenge?

Modular Architecture > You’ve done a LEED Gold or two, maybe even a LEED Platinum. But are you and your firm ready to take on the Living Building Challenge? Think twice before you say yes.

| Sep 7, 2011

Administration, Maintenance and Operations Facility in South Bend achieves LEED Platinum

The facility achieved 52 LEED points, including those for site selection, energy, materials and resources and innovation.

| Aug 23, 2011

Acoustical design education model

Pass this exam and earn 1.0 AIA/CES Discovery learning units. You must go to www.BDCnetwork.com/EnhancedAcousticalDesign to take this exam.

boombox1
boombox2
native1

More In Category




Contractors

Contractors expect to spend more time on prefabrication, according to FMI study

Get ready for a surge in prefabrication activity by contractors. FMI, the consulting and investment banking firm, recently polled contractors about how much time they were spending, in craft labor hours, on prefabrication for construction projects. More than 250 contractors participated in the survey, and the average response to that question was 18%. More revealing, however, was the participants’ anticipation that craft hours dedicated to prefab would essentially double, to 34%, within the next five years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021