By By BD+C Staff | September 23, 2011
A sophisticated curtainwall facade will be installed at the new OSU Cancer and Critical Care facility.

 

 

 

 

 

 

 

 

 

The Ohio State University, and it's construction management team Turner Construction-Bovis Lend Lease, recently selected National Enclosure Co. to design and install the sophisticated curtainwall facade for the new Cancer and Critical Care facility. As part of the university's high-profile Project One initiative, the new facility adds nearly 800,000 sf and is located on the main campus in Columbus, Ohio. Completion of the approximately $15 million contract is expected to be December 2012.
The Ohio State University's Cancer and Critical Care facility is designed by internationally recognized Hellmuth, Obata + Kassabaum (HOK).
The design incorporates a highly energy efficient, unitized curtainwall facade for the tower, which is a key component in the design's projected achievement of LEED Gold status.
NEC has been selected as the Design Assist Contractor which integrates the firm with other team members to develop the final design implementation. NEC's contribution of a scalable design and installation technology will provide a standardized, factory-assembled unitized facade which will be adaptable and customized for the Cancer and Critical Care facility. 
This recently awarded contract demonstrates the industry demand for high-performance and technologically-innovative solutions for advance facades on architectural projects. Whether glass, terracotta, aluminum, stainless steel, granite or stone, NEC has developed a cost-effective solution which is changing the way advance architecture is being achieved. BD+C

Related Stories

Cladding and Facade Systems | Jun 5, 2023

27 important questions about façade leakage

Walter P Moore’s Darek Brandt discusses the key questions building owners and property managers should be asking to determine the health of their building's façade.  

Office Buildings | May 15, 2023

Sixteen-story office tower will use 40% less energy than an average NYC office building

This month marks the completion of a new 16-story office tower that is being promoted as New York City’s most sustainable office structure. That boast is backed by an innovative HVAC system that features geothermal wells, dedicated outdoor air system (DOAS) units, radiant heating and cooling, and a sophisticated control system to ensure that the elements work optimally together.

AEC Tech Innovation | May 12, 2023

Meet Diverge, Hensel Phelps' new ConTech investment company

Thai Nguyen, Director of Innovation with Hensel Phelps, discusses the construction giant's new startup investment platform, Diverge.

3D Printing | May 12, 2023

World’s first 3D-printed medical center completed

3D construction printing reached new heights this week as the world’s first 3D-printed medical center was completed in Thailand.

AEC Tech | May 9, 2023

4 insights on building product manufacturers getting ‘smart’

Overall, half of building product manufacturers plan to invest in one or more areas of technology in the next three years.

University Buildings | May 5, 2023

New health sciences center at St. John’s University will feature geothermal heating, cooling

The recently topped off St. Vincent Health Sciences Center at St. John’s University in New York City will feature impressive green features including geothermal heating and cooling along with an array of rooftop solar panels. The geothermal field consists of 66 wells drilled 499 feet below ground which will help to heat and cool the 70,000 sf structure.

Building Technology | May 4, 2023

3D printing for construction advances in Germany

The largest 3D-printed building in Europe will have a much lower carbon footprint.

Mass Timber | May 3, 2023

Gensler-designed mid-rise will be Houston’s first mass timber commercial office building

A Houston project plans to achieve two firsts: the city’s first mass timber commercial office project, and the state of Texas’s first commercial office building targeting net zero energy operational carbon upon completion next year. Framework @ Block 10 is owned and managed by Hicks Ventures, a Houston-based development company.

AEC Tech | May 1, 2023

Utilizing computer vision, AI technology for visual jobsite tasks

Burns & McDonnell breaks down three ways computer vision can effectively assist workers on the job site, from project progress to safety measures.

Design Innovation Report | Apr 27, 2023

BD+C's 2023 Design Innovation Report

Building Design+Construction’s Design Innovation Report presents projects, spaces, and initiatives—and the AEC professionals behind them—that push the boundaries of building design. This year, we feature four novel projects and one building science innovation.

boombox1
boombox2
native1

More In Category




Contractors

Contractors expect to spend more time on prefabrication, according to FMI study

Get ready for a surge in prefabrication activity by contractors. FMI, the consulting and investment banking firm, recently polled contractors about how much time they were spending, in craft labor hours, on prefabrication for construction projects. More than 250 contractors participated in the survey, and the average response to that question was 18%. More revealing, however, was the participants’ anticipation that craft hours dedicated to prefab would essentially double, to 34%, within the next five years.

halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021