Creating a healthcare capital project plan: The truth behind the numbers

Creating a healthcare capital project plan: The truth behind the numbers

When setting up a capital project plan, it's one thing to have the data, but quite another to have the knowledge of the process. 


By Patrick Duke, Managing Director, CBRE Healthcare | December 3, 2013

Everything is moving in the right direction. You have put together capital budgets for a new ambulatory care center and new hospital that you believe will be approved by your capital allocation committee and board to begin in 2014. These capital projects are a focus of your organization in an effort to consolidate underutilized facilities that are geographically misplaced as a result of a recent merger with your former friendly competitor in the adjacent county. 

As you spend Friday afternoon thinking about your team's accomplishment preparing this solid approval package, you are brought back to reality with a new email that hits the inbox.

The email is from your CFO who has just wrapped up a conversation with one of his old college buddies working for a health system in the southern part of the U.S. He claims they are constructing two similar projects for far less than the budget you have submitted when comparing on a cost/SF and cost/bed comparison and about eight months earlier than your planned overall schedule. All the work you have completed with your team is now coming into question and you need to be prepared to support your position or lose credibility with your CFO. Where do you start?

Keep Calm and Ask Questions

Something just does not seem right about your CFO's information. You know the contractor that did the work on the project the CFO referenced and immediately know that is step one to providing some insight as to how they could provide pricing that was so much lower and a schedule that was faster for this other organization. After attempting to call your contact at the contractor, you spend the weekend with no resolution. On Monday morning, you finally reach your contact and present him with the following questions:

* What is the completed construction cost for both comparable facilities? You find out from the contractor that the ambulatory care center was constructed for $150/SF and the hospital for $305/SF. This compares to your cost estimates of $225/SF for the ambulatory care center $450/SF for the hospital. At this point you see why your CFO was a bit upset, but understand there must be more to it.

* What was the size and scope of both comparable facilities? You find out that both facilities are roughly the same size as the two for which you are seeking approval. However, there are some key differences that give you comfort. The ambulatory care center is being developed by a third party, and they are leasing to physicians. Therefore, the construction cost breakdown only includes a $45/SF tenant fit-out allowance. Also, site work was not included in the number provided by the contractor. It was another $10/SF. Since your organization is developing the ambulatory care center and paying for complete fit-out of the tenant spaces at an average of $90/SF, you quickly catch a difference that can be explained. Your site is a bit more difficult with topography and rock, so your site work cost is $15/SF.  

For the hospital, you find out that the comparable project includes two shelled floors that represent a total of 55,000 SF and in the future would add 64 beds. These metrics were included in the $/SF and $/bed metrics provided to your CFO. Your hospital, on the other hand, includes no shell space or future bed counts. At this point you begin to feel much better.

* When was the buy-out of the comparable projects and did you use union or non-union labor? The comparable projects were bought out in 2013 and your projects are not scheduled to be bought out until 2015. This is another encouraging sign for your future meeting with the CFO to explain these differences, as you assumed escalation of 3.5% per year based on 2013 cost data. In addition, you find out that the contractor was able to use non-union labor on the comparable projects and your market will require a Project Labor Agreement (PLA) and use of union labor. Depending on the market, this can account for a 15-30% variation in estimated labor costs. Surely the CFO accounted for these variations when comparing the costs he received from his friend.

* What were some of the features of the building design? The contractor quickly points out that the comparable facilities are built in a very basic manner and mechanical, electrical, and plumbing systems are code minimum. The organization he is working with has a tried-and-true approach to capital facilities with design standards in place they have utilized for years. They focus on keeping first costs down and are in markets where competition is not as fierce. On the other hand, your planned facilities are required to be LEED accredited. Furthermore, your organization is in a highly competitive market where patients from a preferred payer mix are looking for amenities and your donor base only wants their name associated with signature buildings. This alone accounts for another difference of about 10%-12% in your estimated cost and the cost of the comparable facilities.

* Did the construction cost include things like low-voltage systems or kitchen equipment for the new hospital? The contractor says that he included low-voltage systems to the extent they would rough in for nurse call and other such communication systems, but they did include cable installation or providing the packaged systems. He did say his number included kitchen equipment, while you had this included as a separate line item. This was another win for your case. In addition, your preferred buy-out approach is for the contractor to provide all low-voltage scope and the only cost you include outside of your construction budget is for network equipment, computers, and any clinical informatics systems. These are all handled by your internal IT department. Another fact that provides you with more rationale for the higher costs you have estimated.

* What about the schedule? You ask the contractor about his construction schedule and you find out that your estimate is only three months longer. Given weather patterns for your northern climate, this may even be a bit aggressive for you on second thought. As you try to figure out the additional five-month discrepancy you realize that your CFO was probably looking at the overall project schedule, including design and approvals and not just construction. With both facilities in states that have similar timetables for approval, it could not be that. The contractor then mentioned how they had a close relationship with the local planning board and how easy they were to deal with. After that statement you realized this probably was accounting for the remaining difference. The process for approvals in your municipality includes review by a planning and design board and you are also in a special historic district. Armed with this final piece of the puzzle you then prepare to meet with your CFO.

Preparing to Deliver the Message

Relieved that you now understand the difference between your projects and the comparable projects, you are still concerned that you have no solid solution as to how to present this information to your CFO at your meeting in two days. At home that evening, your wife, who is car shopping, asks you to review some online information with her. She shows you a comparison of two vehicles, side-by-side; with a list of features and a simple check box for the model that includes those features. There is also a comment column with explanations for each feature listed. It then hits you! You thank your wife and get your laptop fired up and prepare the information in this manner.

In your meeting with the CFO, you use the side-by-side comparison model you had viewed the evening before. Quickly, the CFO realizes the projects were not as far out of line as he once thought. In fact, when the comparison was made in the proper context, he actually requested that you go back and ensure the numbers would support the organization's vision with an adequate contingency at this stage in the process. Upon completing his request you forward him the revised package for board approval.

The Moral of the Story

If you have not been involved in a story like the one above, directly or indirectly, you probably have not been involved in the capital project delivery process during your career. In the Internet generation, vast amounts of data and information are only a search engine away. We believe this can actually be counterproductive when it is used in the wrong manner.

It is important to evaluate benchmarks closely when utilizing them to develop or compare a capital project plan. We touched on only a few of the items that may impact a project. Some additional concerns are as follows:

* How much new equipment and furniture is included in the budget versus reuse?

* Does the budget include land costs?

* Does the budget include financing costs?

* Are you capitalizing in-house project management and IT staff's labor effort to the project budget?

You begin to get the picture that it is one thing to have the data, but quite another to have the knowledge of the process and experience in setting up a capital project plan. Truly understanding all of the pieces involved in the puzzle will ensure you launch a project correctly for a successful outcome. As things are rarely what they seem, clearly defining the truth behind your numbers will alleviate stress and avoid endless frustration.

Related Stories

Urban Planning | Feb 5, 2024

Lessons learned from 70 years of building cities

As Sasaki looks back on 70 years of practice, we’re also looking to the future of cities. While we can’t predict what will be, we do know the needs of cities are as diverse as their scale, climate, economy, governance, and culture.

Giants 400 | Feb 5, 2024

Top 90 Shopping Mall, Big Box Store, and Strip Center Architecture Firms for 2023

Gensler, Arcadis North America, Core States Group, WD Partners, and MBH Architects top BD+C's ranking of the nation's largest shopping mall, big box store, and strip center architecture and architecture engineering (AE) firms for 2023, as reported in the 2023 Giants 400 Report.

Laboratories | Feb 5, 2024

DOE selects design-build team for laboratory focused on clean energy innovation

JE Dunn Construction and SmithGroup will construct the 127,000-sf Energy Materials and Processing at Scale (EMAPS) clean energy laboratory in Colorado to create a direct path from lab-scale innovations to pilot-scale production.

Architects | Feb 2, 2024

SRG Partnership joins CannonDesign to form 1,300-person design giant across 18 offices

SRG Partnership, a dynamic architecture, interiors and planning firm with studios in Portland, Oregon, and Seattle, Washington, has joined CannonDesign. This merger represents not only a fusion of businesses but a powerhouse union of two firms committed to making a profound difference through design.

Giants 400 | Feb 1, 2024

Top 90 Restaurant Architecture Firms for 2023

Chipman Design Architecture, WD Partners, Greenberg Farrow, GPD Group, and Core States Group top BD+C's ranking of the nation's largest restaurant architecture and architecture engineering (AE) firms for 2023, as reported in the 2023 Giants 400 Report.

Standards | Feb 1, 2024

Prioritizing water quality with the WELL Building Standard

In this edition of Building WELLness, DC WELL Accredited Professionals Hannah Arthur and Alex Kircher highlight an important item of the WELL Building Standard: water.

Luxury Residential | Feb 1, 2024

Luxury 16-story condominium building opens in Chicago

The Chicago office of architecture firm Lamar Johnson Collaborative (LJC) yesterday announced the completion of Embry, a 58-unit luxury condominium building at 21 N. May St. in Chicago’s West Loop.

Industry Research | Jan 31, 2024

ASID identifies 11 design trends coming in 2024

The Trends Outlook Report by the American Society of Interior Designers (ASID) is the first of a three-part outlook series on interior design. This design trends report demonstrates the importance of connection and authenticity.

Museums | Jan 30, 2024

Meier Partners' South Korean museum seeks to create a harmonious relationship between art and nature

For the design of the newly completed Sorol Art Museum in Gangneung, South Korea, Meier Partners drew from Korean Confucianism to achieve a simplicity of form, material, and composition and a harmonious relationship with nature. The museum is scheduled to open on February 14. It is the firm’s first completed project since restructuring as Meier Partners.

Luxury Residential | Jan 30, 2024

Lumen Fox Valley mall-to-apartments conversion completes interiors

Architecture and interior design firm Morgante Wilson Architects (MWA) today released photos of its completed interiors work at Lumen Fox Valley, a 304-unit luxury rental community and mall-to-apartments conversion.

boombox1
boombox2
native1

More In Category




halfpage1

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021